3:30 PM Update: Subject: ANO-Pleasantville 500 KV line outage

Current assessment of weather damage to Entergy 500 kV transmission facilities and structures in Arkansas results in estimated restoration times ranging from two weeks to as little as one day for all impacted facilities. Day estimates include Wednesday, Feb. 6 during which resource availability is being assessed and resources staged to begin restoration work. Difficult terrain, length of damaged spans are major factors in varied estimates of restoration time. As assessment of damage is further refined and assessed, estimated restoration times may change. Updates on estimated restoration times will be posted when available. Restoration efforts will

Two (2) 500 kV transmission lines:

1. ANO – Pleasant Hill
2. Pleasant Hill – Mayflower

Seven (7) 161 kV transmission lines:

1. Morrilton East – Atkins
2. Moreland – St. Vincent
3. Sage switching station – Mountain View
4. Sage switching station – Melbourne
5. Marked Tree – Marion
6. Clinton West AECC – Clinton Industrial AECC
7. Independence – Searcy/Price

Impact of weather damage on ANO output

As reported through Nuclear Regulatory Agency, reduced output from ANO was directly related to weather-related damage to transmission facilities in Arkansas.

DISTRIBUTION CUSTOMER IMPACT

Total 14,000 est. today (mid-afternoon- 2/6/2008)