(Information below provided to Jackson Miss. media,
December, 2006)
New Autotransformer Most Recent Project to Boost
Reliability for Entergy
Entergy is installing a new 500kV/230kV autotransformer at
the company’s Ray Braswell substation 8.5 miles west of
The autotransformer weighs approximately 715,000 pounds and
when fully assembled is approximately 67 feet long, 69 feet high and 81.3 feet
wide.
An autotransformer moves power from a higher voltage to a
lower voltage for distribution to retail consumers.
The Ray Braswell substation is part of the power network
that supplies electricity to thousands of
Manufactured by Asea Brown Boveri at that company’s manufacturing facility in Varennes, Canada,, and delivered by rail to Jackson and by
heavy-duty trailer to the Entergy substation, the autotransformer not only
improves reliability of service for Entergy Mississippi customers, but bolsters
the reliability of the entire Entergy transmission system which covers more
than 15,000 miles in four states and in New Orleans and serves approximately
2.7 million customers.
Autotransformer One Piece of a Bigger Reliability Picture
Installation of the new autotransformer at the substation
west of
Last summer, Entergy completed a project that relieved
overloading of the Amite to Fernwood transmission
line, part of the transmission system tie between Entergy
The entire transmission line is approximately 32 miles long,
with 15 miles in
Prior to its rebuilding and upgrading, if part of this
region’s extreme high voltage transmission network were to fault and trip while
heavily loaded, this line would have overloaded until Entergy was able to redispatch generation to relieve the overload. The rebuilding
and upgrading eliminates this situation.
New
The third part of the series of expansions and upgrades was
the new transformer that went into service last June at Entergy's Twinkletown substation in Walls,
Located in
Installing the transformer enhances reliability of service
to Entergy
In addition to the transformer, the project included
construction of a 230kV line into and out of the substation, three Entergy
feeders and one feeder serving the Coahoma Electric Power Association.
Completion of this project created the option to add a third
transmission line eastward that could ultimately connect to the company's Getwell substation near Hernando in DeSoto
County, thereby providing service to distribution substations located along
that transmission line, should demand grow.