Outage
Name
Outage
Id
Company Facility Flow
Gate
Segment/
JOTSFacility
Original
TTC In
Original
TTC Out
New
TTC
Start Time (PPT) Stop Time (PPT) Status Outage
Category
Outage
Type
Path
Impact
Report
TPs
Annotation Creation Time (PPT) EventId Last Updated (PPT)
  PPW 171983     10361     PPW     Riverton: 230 kV Cap Bank S/C 472               0.0      0.0      0.0      2021-02-18 09:03      2025-12-23 17:00      ACTIVE     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Riverton: 230 kV Cap Bank S/C 472:     2022-11-14 00:32     75797     2025-06-30 15:01  
  PPW 175805     9275     PPW     Hemingway-Summer Lake 500 kV line (Path 75 Schedule Limitation)          H500-SMLK(PPW) 

  H500-SMLK(PPW)   
  1500.0 

  1500.0   
  1500.0 

  1500.0   
  1386.0 

  1386.0   
  2021-06-02 12:00 

  2024-12-04 12:00   
  2024-12-04 12:00 

  2025-12-31 12:00   
  ACTIVE     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Hemingway-Summer Lake 500 kV line (Path 75 Schedule Limitation)..:Path Restriction Notes: Path 75 Westbound = 1386.:     2021-12-21 14:06     80760     2024-12-04 08:04  
  PPW 24-00488     15058     PPW     Burns: Series Cap Segment #1 & 2,Burns: MO 11D10 BYPASS,Burns: BURNSBNW 11D555 GND SW,Burns: BURNSBN          BORA-M500(PPW) 
  PACW-SMLK(PPW) 
  SMLK-H500(PPW) 

  BORA-M500(PPW) 
  PACW-SMLK(PPW) 
  SMLK-H500(PPW) 

  BORA-M500(PPW) 
  PACW-SMLK(PPW) 
  SMLK-H500(PPW)   
  1090.0 
  550.0 
  100.0 

  1090.0 
  550.0 
  100.0 

  1090.0 
  550.0 
  100.0   
  1090.0 
  550.0 
  100.0 

  1090.0 
  550.0 
  100.0 

  1090.0 
  550.0 
  100.0   
  1090.0 
  550.0 
  100.0 

  1070.0 
  535.0 
  96.0 

  1070.0 
  535.0 
  96.0   
  2024-01-09 03:48 
  2024-01-09 03:48 
  2024-01-09 03:48 

  2024-01-09 03:48 
  2024-01-09 03:48 
  2024-01-09 03:48 

  2025-11-07 16:00 
  2025-11-07 16:00 
  2025-11-07 16:00   
  2024-01-09 03:48 
  2024-01-09 03:48 
  2024-01-09 03:48 

  2025-11-07 16:00 
  2025-11-07 16:00 
  2025-11-07 16:00 

  2025-11-18 16:00 
  2025-11-18 16:00 
  2025-11-18 16:00   
  ACTIVE     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Investigating a possible failure of relay voltage sensing component.:Path 75 limited to 507 (Midpoint Series Caps bypassed for maint). SMLK-H500 = 96; BORA-M500 = 959;:     2024-01-03 10:34     138306     2025-09-08 12:00  
  PPW 24-06062     16750     PPW     Path 25 Schedule Limitation (Cascade 115 kV Tie)          CRAGVIEW-PACW(PPW) 

  CRAGVIEW-PACW(PPW)   
  108.0 

  108.0   
  108.0 

  108.0   
  0.0 

  0.0   
  2024-04-09 00:00 

  2024-04-09 02:35   
  2024-04-09 02:35 

  2026-04-09 00:00   
  ACTIVE     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:CRAGVIEW-PACW TTC = 0 PER PLANNING.:CRAGVIEW-PACW = 0 INDEFINITELY:     2024-04-09 09:34     143888     2025-04-07 18:15  
  PPW 24-06351     18270     PPW     Threemile Knoll: TIE CB 335,Threemile Knoll: CB 335 W Bus Disc,Threemile Knoll: SWITCH 356A               0.0      0.0      0.0      2024-04-12 22:23      2025-12-31 17:00      ACTIVE     TRANSMISSION     FORCED      ONPATH     PPW     continuous:***Commissioning Required*** Investigate failure of CB 335. :     2025-08-15 14:08     144180     2025-08-15 14:08  
  PPW 24-15751     17530     PPW     Threemile Knoll: Series Cap C2,Threemile Knoll: Series Cap C1          JBSN-JB345(PPW) 
  NUT-PATHC(PPW) 
  PATHC-NUT(PPW) 

  NUT-PATHC(PPW) 

  NUT-PATHC(PPW) 

  JBSN-JB345(PPW) 
  PATHC-NUT(PPW)   
  1600.0 
  0.0 
  1600.0 

  1172.0 

  1060.0 

  1600.0 
  1600.0   
  1600.0 
  0.0 
  1600.0 

  1172.0 

  1060.0 

  1600.0 
  1600.0   
  1417.0 
  0.0 
  1600.0 

  1172.0 

  1060.0 

  1433.0 
  1480.0   
  2024-09-18 00:30 
  2024-09-18 00:30 
  2024-09-18 00:30 

  2024-11-01 00:00 

  2025-04-01 00:00 

  2025-06-09 19:09 
  2025-06-09 19:09   
  2025-06-09 19:09 
  2024-11-01 00:00 
  2025-06-09 19:09 

  2025-04-01 00:00 

  2025-06-09 19:09 

  2025-12-31 17:30 
  2025-12-31 17:30   
  ACTIVE     TRANSMISSION     FORCED      ONPATH     PPW     continuous:Computer/controller for Series caps needs to be repaired/replaced. Tech support needed from Hitachi.:JBSN-JB345 = 2150. PacifiCorp = 1433. IPCo = 717 NUT-PATHC = 730 Summer/730 Winter. PATHC-NUT = 1480 Summer/1560 Winter. JBSN-JB345 = 2150. PacifiCorp = 1433. IPCo = 717 NUT-PATHC = 950 Summer/951 Winter. PATHC-NUT = 1480 Summer/1580 Winter.:     2024-11-30 22:07     153619     2025-06-09 19:12  
  PPW 24-16609     18322     PPW     Oquirrh-Terminal #1 345 kV line               0.0      0.0      0.0      2024-10-25 07:52      2025-09-18 00:00      ACTIVE     TRANSMISSION     URGENT      ONPATH     PPW     continuous:Relocate the Oquirrh-Terminal #1 345 kV line:No impact under normal conditions.:     2025-09-05 14:37     154477     2025-09-05 14:37  
  PPW 25-02017     17629     PPW     Crag View-PG&E Cascade section of the PG&E Cascade-Weed Junction 115 kV line          CRAG-CRAGVIEW(PPW) 
  CRAGVIEW-CRAG(PPW)   
  45.0 
  75.0   
  45.0 
  75.0   
  45.0 
  75.0   
  2025-06-30 06:00 
  2025-06-30 06:00   
  2025-10-31 17:00 
  2025-10-31 17:00   
  CANCELLED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Line reconductoring. Replacing structures.:CRAG-CRAGVIEW & CRAGVIEW-CRAG = 0. CRAG-CRAGVIEW & CRAGVIEW-CRAG = 0.:     2025-01-28 13:43     161094     2025-06-09 11:17  
  PPW 25-03418     17689     PPW     Crag View-PG&E Cascade section of the PG&E Cascade-Weed Junction 115 kV line          CRAG-CRAGVIEW(PPW) 
  CRAGVIEW-CRAG(PPW)   
  45.0 
  80.0   
  45.0 
  80.0   
  45.0 
  80.0   
  2025-06-30 07:00 
  2025-06-30 07:00   
  2025-10-31 17:00 
  2025-10-31 17:00   
  CANCELLED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Reconductor between structures.:CRAG-CRAGVIEW & CRAGVIEW-CRAG = 0.:     2025-02-18 12:38     162500     2025-05-27 09:55  
  PPW 25-10324     17986     PPW     Crag View-PG&E Cascade section of the PG&E Cascade-Weed Junction 115 kV line          CRAG-CRAGVIEW(PPW) 
  CRAGVIEW-CRAG(PPW) 

  CRAG-CRAGVIEW(PPW) 
  CRAGVIEW-CRAG(PPW)   
  45.0 
  75.0 

  45.0 
  75.0   
  45.0 
  75.0 

  45.0 
  75.0   
  45.0 
  75.0 

  0.0 
  0.0   
  2025-06-30 07:00 
  2025-06-30 07:00 

  2025-06-30 07:17 
  2025-06-30 07:17   
  2025-06-30 07:17 
  2025-06-30 07:17 

  2025-10-31 17:00 
  2025-10-31 17:00   
  ACTIVE     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Line reconductoring. Replacing structures.:CRAG-CRAGVIEW & CRAGVIEW-CRAG = 0. CRAG-CRAGVIEW & CRAGVIEW-CRAG = 0.:     2025-06-10 10:10     169449     2025-06-30 07:18  
  PPW 25-12844     18149     PPW     Parkway: CB 17,Carlisle: CB 11               0.0      0.0      0.0      2025-07-09 13:23      2025-09-09 15:00      ACTIVE     DISTRIBUTION     URGENT      ONPATH     PPW     continuous:Offload 2 MVA off PKW 17 onto CRL 11:     2025-07-09 13:23     171976     2025-07-09 13:43  
  PPW 25-13375     18179     PPW     Cold Springs: XFMR 1 T-3169,Cold Springs: CS 1W27,Cold Springs: CB 3W120,Cold Springs-Hermiston 69 k               0.0      0.0      0.0      2025-07-17 07:44      2025-09-12 09:00      ACTIVE     TRANSMISSION     URGENT      ONPATH     PPW     continuous:Replace T-3169, CB 3W120, SW 3W119:Umatilla, Hermiston & Hinkle will be radial from BPA McNary. Network Load Service Arrangements may be required. With Cold Springs XFMR #1 out of service, Echo Wind Generation will be tied to BPA McNary. Orchard Wind restricted to 8.5MW maximum output. Umatilla, Hermiston & Hinkle will be radial from BPA McNary. Network Load Service Arrangements may be required. With Cold Springs XFMR #1 out of service, Echo Wind Generation will be tied to BPA McNary. Orchard Wind required offline.:No planned work from 6/1-9/1., No planned work from 6/1-9/1.     2025-07-15 13:11     172511     2025-09-05 16:25  
  PPW 25-13805     18193     PPW     Jim Bridger-Mustang 230 kV line,Mustang-WAPA Spence 230 kV line,Jim Bridger: SWITCH 1H744          JBSN-WYOCENTRAL(PPW) 
  TOT4B-WYONORTH(PPW) 
  WAPAEAST-WAPANORTH(PPW) 
  WYOCENTRAL-JBSN(PPW) 
  WYOCENTRAL-WYOEAST(PPW) 
  WYOEAST-AEOW(PPW) 
  WYOEAST-WYOCENTRAL(PPW) 

  JBSN-WYOCENTRAL(PPW) 
  WAPAEAST-WAPANORTH(PPW) 
  WYOCENTRAL-JBSN(PPW) 
  WYOCENTRAL-WYOEAST(PPW) 
  WYOEAST-AEOW(PPW) 
  WYOEAST-WYOCENTRAL(PPW)   
  600.0 
  631.0 
  249.0 
  600.0 
  574.0 
  0.0 
  574.0 

  600.0 
  249.0 
  600.0 
  574.0 
  0.0 
  574.0   
  600.0 
  631.0 
  249.0 
  600.0 
  574.0 
  0.0 
  574.0 

  600.0 
  249.0 
  600.0 
  574.0 
  0.0 
  574.0   
  400.0 
  631.0 
  243.0 
  400.0 
  287.0 
  0.0 
  287.0 

  400.0 
  243.0 
  400.0 
  287.0 
  0.0 
  287.0   
  2025-07-18 13:20 
  2025-07-18 13:20 
  2025-07-18 13:20 
  2025-07-18 13:20 
  2025-07-18 13:20 
  2025-07-18 13:20 
  2025-07-18 13:20 

  2025-09-01 17:00 
  2025-09-01 17:00 
  2025-09-01 17:00 
  2025-09-01 17:00 
  2025-09-01 17:00 
  2025-09-01 17:00   
  2025-09-01 17:00 
  2025-09-25 17:00 
  2025-09-01 17:00 
  2025-09-01 17:00 
  2025-09-01 17:00 
  2025-09-01 17:00 
  2025-09-01 17:00 

  2025-09-25 17:00 
  2025-09-25 17:00 
  2025-09-25 17:00 
  2025-09-25 17:00 
  2025-09-25 17:00 
  2025-09-25 17:00   
  ACTIVE     TRANSMISSION     FORCED      ONPATH     PPW     continuous:Fix Jim Bridger SW 1H744 Broken Blade :AW/4B Curve 121. WAPAEAST-WAPANORTH = 243. WYOCENTRAL-WYOEAST=287. TOT4B-WYONORTH = 631. TOT 4B = 874. JBSN-WYOC & WYOC-JBSN = 400. Potential Real Time Impact to Wyoming Generation Great Divide will be radial from WAPA Spence via Mustang. Network Load Service Arrangements may be required. AW/4B Curve 121. WAPAEAST-WAPANORTH = 243. WYOCENTRAL-WYOEAST=287. TOT4B-WYONORTH = 631. TOT 4B = 874. JBSN-WYOC & WYOC-JBSN = 400. Potential Real Time Impact to Wyoming Generation Great Divide will be radial from WAPA Spence via Mustang. Network Load Service Arrangements may be required.:     2025-07-18 13:26     172941     2025-08-25 14:26  
  PPW 25-11020     18170     PPW     Dixonville: 115 kV Bus Differential Relay,Dixonville: CB 2U4          HYDROGEN-PACW(PPW) 

  HYDROGEN-PACW(PPW)   
  9999.0 

  9999.0   
  9999.0 

  9999.0   
  9999.0 

  9999.0   
  2025-08-04 09:00 

  2025-08-12 12:00   
  2025-08-12 12:00 

  2025-10-17 16:00   
  CANCELLED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Remove and replace 115 kV Bus Differential Relay Scheme:     2025-07-11 10:59     170145     2025-08-11 09:28  
  PPW 25-15876     18261     PPW     Populus: 345 kV Series Capacitor #1          JBSN-JB345(PPW) 

  JBSN-JB345(PPW)   
  1600.0 

  1600.0   
  1600.0 

  1600.0   
  1433.0 

  1600.0   
  2025-08-11 10:02 

  2025-09-05 18:32   
  2025-09-05 18:32 

  2025-09-05 20:00   
  COMPLETED     TRANSMISSION     FORCED      ONPATH     PPW     continuous:Cap locked out. Switch 352A would not open when attempting to switch it out on iTOA 25-15685:JBSN-JB345 = 2150. PacifiCorp = 1433. IPCo = 717.:     2025-08-11 10:02     175019     2025-09-05 18:32  
  PPW 25-15397     18243     PPW     Gadsby: Gadsby Unit 1 GSU XFMR 1,Gadsby: Gadsby Unit 1 GSU XFMR 2          THERMALGEN-PACE(PPW) 

  THERMALGEN-PACE(PPW)   
  9999.0 

  9999.0   
  9999.0 

  9999.0   
  9999.0 

  0.0   
  2025-08-12 06:00 

  2025-08-12 06:36   
  2025-08-12 06:36 

  2025-09-12 17:00   
  ACTIVE     TRANSMISSION     OPPORTUNITY      ONPATH     PPW     continuous:Fire system scaffold setup and work.:Gadsby Unit #1 unavailable.:     2025-08-05 14:27     174536     2025-08-12 06:36  
  PPW 25-03627     18235     PPW     Prospect Central: T-3069,70,71,Prospect Central: Sw 2R264,Prospect Central: SW 3R105,Prospect Centra          HYDROGEN-PACW(PPW) 

  HYDROGEN-PACW(PPW)   
  9999.0 

  9999.0   
  9999.0 

  9999.0   
  0.0 

  0.0   
  2025-08-18 08:57 

  2025-09-12 15:00   
  2025-09-12 15:00 

  2025-09-25 15:00   
  ACTIVE     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Remove existing XFMR relays and add new SEL-387E relay panel.:Prospect Hydro Project generation restricted to 14 MW.:     2025-08-04 09:39     162709     2025-09-02 13:01  
  PPW 25-13622     18208     PPW     Craven Creek-Naughton 230 kV line          NUT-TRONA(PPW) 
  TRONA-NUT(PPW) 

  NUT-TRONA(PPW) 
  TRONA-NUT(PPW) 

  NUT-TRONA(PPW) 
  TRONA-NUT(PPW)   
  407.0 
  475.0 

  407.0 
  475.0 

  407.0 
  475.0   
  407.0 
  475.0 

  407.0 
  475.0 

  407.0 
  475.0   
  407.0 
  475.0 

  401.0 
  401.0 

  401.0 
  401.0   
  2025-08-25 08:00 
  2025-08-25 08:00 

  2025-08-25 10:25 
  2025-08-25 10:25 

  2025-08-29 11:00 
  2025-08-29 11:00   
  2025-08-25 10:25 
  2025-08-25 10:25 

  2025-08-29 11:00 
  2025-08-29 11:00 

  2025-09-11 00:00 
  2025-09-11 00:00   
  ACTIVE     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:B-condition insulator replacement:NUT-TRONA & TRONA-NUT = 401 Summer/475 Winter:     2025-07-29 11:55     172758     2025-09-05 14:22  
  PPW 25-17118     18299     PPW     Jim Bridger: 345/20 kV Unit #4 Main Bank (T3654)          JBSN-JB345(PPW)      1600.0      1600.0      1600.0      2025-08-26 00:00      2025-09-05 14:20      COMPLETED     TRANSMISSION     FORCED      ONPATH     PPW     continuous:Boiler De-slag and Fine Screen Replacement:JBSN-JB345 = 2400. PacifiCorp = 1600. IPCo = 800.:Per Transmission Network Diagram 103551.122 v49 Unit 4 XFMR is BES     2025-08-26 00:07     176271     2025-09-05 14:20  
  PPW 25-13407     18188     PPW     BPA, Yale: Yale Runback SPS          HYDROGEN-PACW(PPW) 

  HYDROGEN-PACW(PPW) 

  HYDROGEN-PACW(PPW)   
  9999.0 

  9999.0 

  9999.0   
  9999.0 

  9999.0 

  9999.0   
  9999.0 

  9999.0 

  0.0   
  2025-08-25 08:00 

  2025-08-26 08:00 

  2025-08-26 10:57   
  2025-08-26 08:00 

  2025-08-26 10:57 

  2025-10-02 15:00   
  ACTIVE     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Yale Runback RAS Relays Out of Service:Yale and Merwin total output limited to 175MW maximum. Merwin and Yale are restricted below 174/227 MVA (Summer/Winter):     2025-07-18 09:19     172543     2025-08-26 10:57  
  PPW 25-17703     18308     PPW     Dave Johnston-TSGT Laramie River Station 230 kV line,TSGT Laramie River: LS.384          DJ-WYOEAST(PPW) 
  WYOEAST-AEOW(PPW) 
  WYOEAST-DJ(PPW) 

  DJ-WYOEAST(PPW) 
  WYOEAST-AEOW(PPW) 
  WYOEAST-DJ(PPW) 

  DJ-WYOEAST(PPW) 
  WYOEAST-AEOW(PPW) 
  WYOEAST-DJ(PPW)   
  790.0 
  0.0 
  790.0 

  790.0 
  0.0 
  790.0 

  790.0 
  0.0 
  790.0   
  790.0 
  0.0 
  790.0 

  790.0 
  0.0 
  790.0 

  790.0 
  0.0 
  790.0   
  790.0 
  0.0 
  790.0 

  478.0 
  0.0 
  478.0 

  790.0 
  0.0 
  790.0   
  2025-09-03 07:00 
  2025-09-03 07:00 
  2025-09-03 07:00 

  2025-09-03 07:03 
  2025-09-03 07:03 
  2025-09-03 07:03 

  2025-10-01 07:00 
  2025-10-01 07:00 
  2025-10-01 07:00   
  2025-09-03 07:03 
  2025-09-03 07:03 
  2025-09-03 07:03 

  2025-09-19 15:00 
  2025-09-19 15:00 
  2025-09-19 15:00 

  2025-10-20 15:00 
  2025-10-20 15:00 
  2025-10-20 15:00   
  ACTIVE     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:2025 structure replacements.:DJ-WYOEAST & WYOEAST-DJ = 442 (Dave Johnston-WAPA Stegall 230 kV line rating):     2025-09-02 07:40     176862     2025-09-03 07:03  
  PPW 25-13051     18190     PPW     Merwin-View Tap section of the Merwin-CCPD Cherry Grove 115 kV line          HYDROGEN-PACW(PPW) 

  HYDROGEN-PACW(PPW)   
  9999.0 

  9999.0   
  9999.0 

  9999.0   
  9999.0 

  0.0   
  2025-09-02 08:00 

  2025-09-03 07:56   
  2025-09-03 07:56 

  2025-09-05 17:00   
  Completed     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Replace the RAS Relays in Cherry Grove (Battleground) Line Bay:May be Slight Impact on South of Allston Path. Eliminates Merwin/Yale Generation Delivery to the Portland Load Area.:     2025-07-18 10:13     172183     2025-09-03 07:56  
  PPW 25-17067     18300     PPW     Populus: 345 kV Series Capacitor #1,Populus: SERIES CAP BYPASS SW 372A          JB345-POP(PPW) 
  JBSN-JB345(PPW) 
  NUT-PATHC(PPW)   
  1067.0 
  1600.0 
  1060.0   
  1067.0 
  1600.0 
  1060.0   
  1067.0 
  1600.0 
  1060.0   
  2025-09-02 09:00 
  2025-09-02 09:00 
  2025-09-02 09:00   
  2025-09-05 15:00 
  2025-09-05 15:00 
  2025-09-05 15:00   
  Completed     TRANSMISSION     URGENT      ONPATH     PPW     continuous:Troubleshoot and repair SW 352A:JBSN-JB345 = 2150. PacifiCorp = 1433. IPCo = 717. JBSN-JB345 = 1600. PacifiCorp = 1067. IPCo = 533. Potential Real Time Impact to Jim Bridger Generation. JB345-POP = 533 NUT-PATHC = 1000 Summer/1172 Winter.:     2025-08-26 10:17     176219     2025-09-02 14:54  
  PPW 25-16925     18291     PPW     NWE Peterson-Millcreek/Anaconda 230 kV line          ANTE-MLCK(PPW) 
  MLCK-ANTE(PPW)   
  66.0 
  90.0   
  66.0 
  90.0   
  0.0 
  0.0   
  2025-09-04 06:00 
  2025-09-04 06:00   
  2025-09-04 16:00 
  2025-09-04 16:00   
  Completed     TRANSMISSION     URGENT      ONPATH     PPW     continuous:230kV structure changeout.:MLCK-ANTE & ANTE-MLCK = 0.:     2025-08-22 14:33     176077     2025-08-22 14:33  
  PPW 25-17749     18309     PPW     Clearwater Switching Station: CB 2U153,Clearwater SS-Lemolo #1 115 kV line,Lemolo 1: CB 5U920,Lemolo          HYDROGEN-PACW(PPW) 

  HYDROGEN-PACW(PPW)   
  9999.0 

  9999.0   
  9999.0 

  9999.0   
  9999.0 

  9999.0   
  2025-09-03 07:00 

  2025-09-04 18:00   
  2025-09-04 16:00 

  2025-09-05 16:00   
  CANCELLED     TRANSMISSION     FORCED      ONPATH     PPW     continuous:DE-ENERGIZE CLEARWATER SS - LEMOLO 1 115kV & LEMOLO 1 DISTRIBUTION CB 5U920 FOR FEA "EMIGRANT FIRE"; CURRENT GROWTH PROJECTS POTENTIAL IMPACTS TO PAC ASSETS 9/3/2025:Lemolo #1 generator unavailable.:     2025-09-02 13:47     176911     2025-09-05 16:34  
  PPW 25-17214     18302     PPW     Jim Bridger-Populus #1 345 kV line,Populus: SERIES CAP LINE SWITCH 352A,Populus: 345 kV Series Capac          JB345-POP(PPW) 
  JBSN-JB345(PPW) 
  NUT-PATHC(PPW) 

  JB345-POP(PPW) 
  JBSN-JB345(PPW) 
  NUT-PATHC(PPW) 

  JB345-POP(PPW) 
  JBSN-JB345(PPW) 
  NUT-PATHC(PPW) 

  JB345-POP(PPW) 
  JBSN-JB345(PPW) 
  NUT-PATHC(PPW)   
  1067.0 
  1600.0 
  1060.0 

  1067.0 
  1600.0 
  1060.0 

  1067.0 
  1600.0 
  1060.0 

  1067.0 
  1600.0 
  1060.0   
  1067.0 
  1600.0 
  1060.0 

  1067.0 
  1600.0 
  1060.0 

  1067.0 
  1600.0 
  1060.0 

  1067.0 
  1600.0 
  1060.0   
  1067.0 
  1600.0 
  1060.0 

  1067.0 
  1600.0 
  1060.0 

  533.0 
  1033.0 
  1000.0 

  1067.0 
  1600.0 
  1060.0   
  2025-09-05 14:30 
  2025-09-05 14:30 
  2025-09-05 14:30 

  2025-09-05 15:00 
  2025-09-05 15:00 
  2025-09-05 15:00 

  2025-09-05 15:13 
  2025-09-05 15:13 
  2025-09-05 15:13 

  2025-09-05 18:00 
  2025-09-05 18:00 
  2025-09-05 18:00   
  2025-09-05 15:00 
  2025-09-05 15:00 
  2025-09-05 15:00 

  2025-09-05 15:13 
  2025-09-05 15:13 
  2025-09-05 15:13 

  2025-09-05 18:00 
  2025-09-05 18:00 
  2025-09-05 18:00 

  2025-09-05 20:00 
  2025-09-05 20:00 
  2025-09-05 20:00   
  COMPLETED     TRANSMISSION     URGENT      ONPATH     PPW     continuous:Switching to return line to service to reconnect jumper.:JBSN-JB345 = 1600. PacifiCorp = 1067. IPCo = 533. Potential Real Time Impact to Jim Bridger Generation. JB345-POP = 533 NUT-PATHC = 1000 Summer/1172 Winter. JBSN-JB345 = 2150. PacifiCorp = 1433. IPCo = 717. JBSN-JB345 = 2150. PacifiCorp = 1433. IPCo = 717.:     2025-08-26 12:02     176370     2025-09-05 18:02  
  PPW 25-18130     18321     PPW     Latham-Platte 230 kV line          AEOLUSGEN-AEOLUS(PPW) 
  OUTAGE-WYOCENTRAL(PPW) 
  STANDPIPE-WYOCENTRAL(PPW) 
  TOT4B-WYONORTH(PPW) 
  WAPAEAST-WAPANORTH(PPW) 
  WYOCENTRAL-STANDPIPE(PPW) 
  WYOEAST-AEOW(PPW) 

  AEOLUSGEN-AEOLUS(PPW) 
  OUTAGE-WYOCENTRAL(PPW) 
  STANDPIPE-WYOCENTRAL(PPW) 
  TOT4B-WYONORTH(PPW) 
  WAPAEAST-WAPANORTH(PPW) 
  WYOCENTRAL-STANDPIPE(PPW) 
  WYOEAST-AEOW(PPW) 

  AEOLUSGEN-AEOLUS(PPW) 
  OUTAGE-WYOCENTRAL(PPW) 
  STANDPIPE-WYOCENTRAL(PPW) 
  TOT4B-WYONORTH(PPW) 
  WAPAEAST-WAPANORTH(PPW) 
  WYOCENTRAL-STANDPIPE(PPW) 
  WYOEAST-AEOW(PPW)   
  2000.0 
  1.0 
  331.0 
  631.0 
  249.0 
  331.0 
  0.0 

  2000.0 
  1.0 
  331.0 
  631.0 
  249.0 
  331.0 
  0.0 

  2000.0 
  1.0 
  331.0 
  631.0 
  249.0 
  331.0 
  0.0   
  2000.0 
  1.0 
  331.0 
  631.0 
  249.0 
  331.0 
  0.0 

  2000.0 
  1.0 
  331.0 
  631.0 
  249.0 
  331.0 
  0.0 

  2000.0 
  1.0 
  331.0 
  631.0 
  249.0 
  331.0 
  0.0   
  2000.0 
  1.0 
  331.0 
  631.0 
  249.0 
  331.0 
  0.0 

  1270.0 
  0.0 
  0.0 
  592.0 
  233.0 
  0.0 
  0.0 

  1270.0 
  0.0 
  0.0 
  592.0 
  233.0 
  0.0 
  0.0   
  2025-09-07 06:00 
  2025-09-07 06:00 
  2025-09-07 06:00 
  2025-09-07 06:00 
  2025-09-07 06:00 
  2025-09-07 06:00 
  2025-09-07 06:00 

  2025-09-07 07:14 
  2025-09-07 07:14 
  2025-09-07 07:14 
  2025-09-07 07:14 
  2025-09-07 07:14 
  2025-09-07 07:14 
  2025-09-07 07:14 

  2025-09-07 16:00 
  2025-09-07 16:00 
  2025-09-07 16:00 
  2025-09-07 16:00 
  2025-09-07 16:00 
  2025-09-07 16:00 
  2025-09-07 16:00   
  2025-09-07 07:14 
  2025-09-07 07:14 
  2025-09-07 07:14 
  2025-09-07 07:14 
  2025-09-07 07:14 
  2025-09-07 07:14 
  2025-09-07 07:14 

  2025-09-07 16:00 
  2025-09-07 16:00 
  2025-09-07 16:00 
  2025-09-07 16:00 
  2025-09-07 16:00 
  2025-09-07 16:00 
  2025-09-07 16:00 

  2025-09-07 16:22 
  2025-09-07 16:22 
  2025-09-07 16:22 
  2025-09-07 16:22 
  2025-09-07 16:22 
  2025-09-07 16:22 
  2025-09-07 16:22   
  COMPLETED     TRANSMISSION     URGENT      ONPATH     PPW     continuous:Loose insulator pin:AW/4B Curve 107. WAPAEAST-WAPANORTH = 233. WYOCENTRAL-STANDPIPE = 0. TOT4B-WYONORTH = 592. TOT 4B = 825. Potential Real Time Impact to Wyoming Generation:     2025-09-05 13:53     177294     2025-09-07 16:22  
  PPW 25-03417     17688     PPW     Malin-PG&E Round Mountain #1 500 kV line          MALIN500-RDM500(PPW) 
  RDM500-MALIN500(PPW) 

  MALIN500-RDM500(PPW) 
  RDM500-MALIN500(PPW)   
  800.0 
  612.0 

  800.0 
  612.0   
  800.0 
  612.0 

  800.0 
  612.0   
  625.0 
  416.0 

  800.0 
  612.0   
  2025-09-08 06:00 
  2025-09-08 06:00 

  2025-09-29 06:00 
  2025-09-29 06:00   
  2025-09-12 17:00 
  2025-09-12 17:00 

  2025-10-03 17:00 
  2025-10-03 17:00   
  Active     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Install lab measurement and fault initiating test equipment on primary conductors (Grounded).:MALIN500-RDM500 = 625. RDM500-MALIN500 = 416.:     2025-02-18 12:23     162499     2025-04-10 08:52  
  PPW 25-17969     18317     PPW     Scheduling Limitation: Path 8 Schedule Limitation (MT-NW)          ANTE-MLCK(PPW) 
  COLSTRIP-TOWNSEND(PPW) 
  MLCK-ANTE(PPW)   
  66.0 
  157.0 
  90.0   
  66.0 
  157.0 
  90.0   
  66.0 
  0.0 
  66.0   
  2025-09-08 07:00 
  2025-09-08 07:00 
  2025-09-08 07:00   
  2025-09-11 16:00 
  2025-09-11 16:00 
  2025-09-11 16:00   
  Active     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:BPA Garrison-Taft 1 500kV Series Capacitor:COLSTRIP-TOWNSEND = 140; ANTE-MLCK = 59:     2025-09-04 10:47     177131     2025-09-04 10:47  
  PPW 25-13052     18191     PPW     Ariel-Merwin section of the Merwin-Cowlitz PUD Lewis River 115 kV line          HYDROGEN-PACW(PPW) 

  HYDROGEN-PACW(PPW)   
  9999.0 

  9999.0   
  9999.0 

  9999.0   
  0.0 

  0.0   
  2025-09-08 07:06 

  2025-09-08 08:00   
  2025-09-08 08:00 

  2025-09-12 17:00   
  ACTIVE     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Replace the RAS Relays in Lewis River Bay at Merwin.:May be Slight Impact on South of Allston Path. Eliminates Merwin/Yale Generation Delivery to the Portland Load Area. Possible real time restriction of Merwin and Yale generation.:     2025-07-18 10:57     172184     2025-09-08 07:06  
  PPW 25-05029     17751     PPW     Circuit 1,Circuit 2,Circuit 3,Circuit 4,Circuit 5,Circuit 6,Pryor Mountain Wind: 34.5kV Bus 1          WINDGEN-PACW(PPW) 

  WINDGEN-PACW(PPW)   
  9999.0 

  9999.0   
  9999.0 

  9999.0   
  0.0 

  9999.0   
  2025-07-09 11:00 

  2025-09-08 08:00   
  2025-07-11 16:00 

  2025-09-12 16:00   
  CANCELLED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Install avian protection.:Pryor Mountain Wind circuits 1-6 (120.6MW) unavailable.:     2025-03-14 11:21     164125     2025-03-17 12:03  
  PPW 25-17770     18310     PPW     NWE Peterson-Millcreek/Anaconda 230 kV line          ANTE-MLCK(PPW) 
  MLCK-ANTE(PPW)   
  66.0 
  90.0   
  66.0 
  90.0   
  0.0 
  0.0   
  2025-09-08 08:00 
  2025-09-08 08:00   
  2025-09-09 14:30 
  2025-09-09 14:30   
  Active     TRANSMISSION     URGENT      ONPATH     PPW     continuous:230kV structure changeout.:MLCK-ANTE & ANTE-MLCK = 0.:     2025-09-02 15:03     176932     2025-09-02 15:03  
  PPW 25-16581     18277     PPW     Ashton: XFMR 1          HYDROGEN-PACE(PPW) 

  HYDROGEN-PACE(PPW)   
  9999.0 

  9999.0   
  9999.0 

  9999.0   
  9999.0 

  0.0   
  2025-09-08 07:00 

  2025-09-08 08:15   
  2025-09-08 08:15 

  2025-09-09 15:00   
  ACTIVE     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Doble Testing:Generation Unavailable. Ashton units will be offline:     2025-08-19 10:57     175728     2025-09-08 08:15  
  PPW 25-05028     17750     PPW     Pryor Mountain Wind: 34.5kV Bus 2,Pryor Mountain Wind: 34.5kV Bus 1          WINDGEN-PACW(PPW) 

  WINDGEN-PACW(PPW) 

  WINDGEN-PACW(PPW) 

  WINDGEN-PACW(PPW)   
  9999.0 

  9999.0 

  9999.0 

  9999.0   
  9999.0 

  9999.0 

  9999.0 

  9999.0   
  9999.0 

  9999.0 

  0.0 

  0.0   
  2025-07-07 08:00 

  2025-09-08 08:00 

  2025-09-08 10:18 

  2025-09-10 11:00   
  2025-07-09 11:00 

  2025-09-08 10:18 

  2025-09-10 11:00 

  2025-09-12 16:00   
  ACTIVE     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Install avian protection.:Pryor Mountain Wind unavailable.:     2025-03-14 11:07     164124     2025-09-08 10:18  
  PPW 25-15869     18279     PPW     Latham: STATCOM          TOT4B-WYONORTH(PPW) 

  TOT4B-WYONORTH(PPW) 

  TOT4B-WYONORTH(PPW)   
  631.0 

  631.0 

  631.0   
  631.0 

  631.0 

  631.0   
  631.0 

  631.0 

  624.0   
  2025-09-08 07:00 

  2025-09-08 10:00 

  2025-09-08 11:00   
  2025-09-08 10:00 

  2025-09-08 11:00 

  2025-09-12 17:00   
  ACTIVE     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:ABB Techs Maintenance :AW/4B Curve 125. WAPAEAST-WAPANORTH = 249. TOT4B-WYONORTH = 624. TOT 4B = 880. Potential Real Time Impact to Wyoming Generation:     2025-08-20 11:28     175012     2025-09-08 11:01  
  PPW 25-15765     18283     PPW     Upalco-Emma Park 138 kV line          PACE-NTLOAD(PPW) 
  PACE-VNL(PPW) 
  VNL-PACE(PPW)   
  9999.0 
  140.0 
  138.0   
  9999.0 
  140.0 
  138.0   
  0.0 
  0.0 
  0.0   
  2025-09-11 08:00 
  2025-09-11 08:00 
  2025-09-11 08:00   
  2025-09-19 14:00 
  2025-09-19 14:00 
  2025-09-19 14:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:A-condition structure replacements:PACE-VNL = 0. VNL-PACE = Ashley load. Network Load Service Arrangements may be required for Ashley. Impact to TOT-1A & CRSP Schedules. Bonanza West (Path 33) = 645.:     2025-08-21 08:46     174906     2025-08-21 08:50  
  PPW 25-15268     18262     PPW     Prospect Central: CB 3R18,Prospect Central: SW 3R184,Prospect Central: SW 3R188          HYDROGEN-PACW(PPW) 

  HYDROGEN-PACW(PPW)   
  9999.0 

  9999.0   
  9999.0 

  9999.0   
  9999.0 

  0.0   
  2025-09-05 09:00 

  2025-09-12 09:00   
  2025-09-05 15:00 

  2025-09-12 15:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Switch out one position at a time to trip test each from the new XFMR Relaying panel.:Prospect 2 Unit 1 off-line for the duration of the outage.:     2025-08-12 13:42     174407     2025-09-02 13:18  
  PPW 25-16137     18276     PPW     BPA McNary-Cold Springs section of the BPA McNary-Wallula 230 kV line,Cold Springs: CS 1W27,Cold Spr          PACW-NTLOAD(PPW) 
  WINDGEN-PACW(PPW) 

  PACW-NTLOAD(PPW) 
  WINDGEN-PACW(PPW) 

  PACW-NTLOAD(PPW) 
  WINDGEN-PACW(PPW)   
  9999.0 
  9999.0 

  9999.0 
  9999.0 

  9999.0 
  9999.0   
  9999.0 
  9999.0 

  9999.0 
  9999.0 

  9999.0 
  9999.0   
  9999.0 
  9999.0 

  9999.0 
  9999.0 

  0.0 
  0.0   
  2025-09-03 10:00 
  2025-09-03 10:00 

  2025-09-05 10:00 
  2025-09-05 10:00 

  2025-09-12 10:00 
  2025-09-12 10:00   
  2025-09-03 16:30 
  2025-09-03 16:30 

  2025-09-05 16:30 
  2025-09-05 16:30 

  2025-09-12 16:30 
  2025-09-12 16:30   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Replace jumpers between SW 1W26, 1W28, cs 1W27:Umatilla, Hermiston & Hinkle will be radial from BPA McNary. Network Load Service Arrangements may be required. With Cold Springs XFMR #1 out of service, Echo Wind Generation will be tied to BPA McNary. Cold Springs will be radial from BPA McNary. Network Load Service Arrangements may be required.:     2025-08-19 09:30     175281     2025-09-08 08:15  
  PPW 25-15269     18263     PPW     Prospect Central: CB 3R19,Prospect Central: Sw 3R194,Prospect Central: Sw 3R198          HYDROGEN-PACW(PPW) 

  HYDROGEN-PACW(PPW)   
  9999.0 

  9999.0   
  9999.0 

  9999.0   
  9999.0 

  0.0   
  2025-09-08 09:00 

  2025-09-13 09:00   
  2025-09-08 15:00 

  2025-09-13 15:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Switch out one position at a time to trip test each from the new XFMR Relaying panel.:Prospect 2 Unit 2 is unavailable for the duration of the outage.:     2025-08-12 13:52     174408     2025-09-02 13:19  
  PPW 25-15687     18251     PPW     Yale: 115/13 kV Bank #1 - T365880, 1, 2               0.0      0.0      0.0      2025-09-15 05:00      2025-09-25 18:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Annual maintenance and runner welding. Penstock and scroll case DEWATERED.:     2025-08-08 08:54     174828     2025-08-08 08:54  
  PPW 25-11976     18051     PPW     Merwin-Yale 115 kV line,Merwin: CB 2P26,Merwin: CB 2P27,Merwin: 2P500 GND SW,Yale: SW 2P508          HYDROGEN-PACW(PPW) 

  HYDROGEN-PACW(PPW)   
  9999.0 

  9999.0   
  9999.0 

  9999.0   
  9999.0 

  0.0   
  2025-09-02 06:00 

  2025-09-15 06:00   
  2025-09-12 17:30 

  2025-09-26 17:30   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Replace structures and switches:Yale units 1 and 2 unavailable.:     2025-07-08 14:35     171108     2025-07-30 13:41  
  PPW 25-07196     17896     PPW     PGE Bethel-Parrish Gap 230 kV line          PACW-PACW.PGE(PPW) 
  PACW.PGE-PACW(PPW) 

  PACW-PACW.PGE(PPW) 
  PACW.PGE-PACW(PPW)   
  325.0 
  325.0 

  325.0 
  325.0   
  325.0 
  325.0 

  325.0 
  325.0   
  325.0 
  325.0 

  159.0 
  159.0   
  2025-09-02 07:00 
  2025-09-02 07:00 

  2025-09-15 07:00 
  2025-09-15 07:00   
  2025-09-05 18:00 
  2025-09-05 18:00 

  2025-09-18 18:00 
  2025-09-18 18:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Replace structures, 1/21, 1/23, 1/25.:PACW-PGE.PACW & PACW.PGE-PACW = 159 Summer/149 Winter Network load service arrangements may be required:     2025-05-05 08:36     166298     2025-06-25 13:00  
  PPW 25-03490     17720     PPW     Atlantic City: CB 1H120,Atlantic City: SW 1H118,Atlantic City-Rock Springs 230 kV line,Rock Springs:          TOT4B-WYONORTH(PPW) 
  WAPAEAST-WAPANORTH(PPW) 
  WYOCENTRAL-WYOEAST(PPW) 
  WYOEAST-AEOW(PPW) 
  WYOEAST-WYOCENTRAL(PPW) 

  TOT4B-WYONORTH(PPW) 
  WAPAEAST-WAPANORTH(PPW) 
  WYOCENTRAL-WYOEAST(PPW) 
  WYOEAST-AEOW(PPW) 
  WYOEAST-WYOCENTRAL(PPW) 

  TOT4B-WYONORTH(PPW) 
  WAPAEAST-WAPANORTH(PPW) 
  WYOCENTRAL-WYOEAST(PPW) 
  WYOEAST-AEOW(PPW) 
  WYOEAST-WYOCENTRAL(PPW) 

  TOT4B-WYONORTH(PPW) 
  WAPAEAST-WAPANORTH(PPW) 
  WYOCENTRAL-WYOEAST(PPW) 
  WYOEAST-AEOW(PPW) 
  WYOEAST-WYOCENTRAL(PPW)   
  631.0 
  249.0 
  574.0 
  0.0 
  574.0 

  631.0 
  249.0 
  574.0 
  0.0 
  574.0 

  631.0 
  249.0 
  574.0 
  0.0 
  574.0 

  631.0 
  249.0 
  574.0 
  0.0 
  574.0   
  631.0 
  249.0 
  574.0 
  0.0 
  574.0 

  631.0 
  249.0 
  574.0 
  0.0 
  574.0 

  631.0 
  249.0 
  574.0 
  0.0 
  574.0 

  631.0 
  249.0 
  574.0 
  0.0 
  574.0   
  631.0 
  249.0 
  574.0 
  0.0 
  574.0 

  631.0 
  249.0 
  574.0 
  0.0 
  574.0 

  631.0 
  249.0 
  574.0 
  0.0 
  574.0 

  571.0 
  235.0 
  287.0 
  0.0 
  287.0   
  2025-06-02 07:00 
  2025-06-02 07:00 
  2025-06-02 07:00 
  2025-06-02 07:00 
  2025-06-02 07:00 

  2025-07-28 07:00 
  2025-07-28 07:00 
  2025-07-28 07:00 
  2025-07-28 07:00 
  2025-07-28 07:00 

  2025-08-25 07:00 
  2025-08-25 07:00 
  2025-08-25 07:00 
  2025-08-25 07:00 
  2025-08-25 07:00 

  2025-09-15 07:00 
  2025-09-15 07:00 
  2025-09-15 07:00 
  2025-09-15 07:00 
  2025-09-15 07:00   
  2025-06-04 10:00 
  2025-06-04 10:00 
  2025-06-04 10:00 
  2025-06-04 10:00 
  2025-06-04 10:00 

  2025-07-30 10:00 
  2025-07-30 10:00 
  2025-07-30 10:00 
  2025-07-30 10:00 
  2025-07-30 10:00 

  2025-08-27 10:00 
  2025-08-27 10:00 
  2025-08-27 10:00 
  2025-08-27 10:00 
  2025-08-27 10:00 

  2025-09-17 10:00 
  2025-09-17 10:00 
  2025-09-17 10:00 
  2025-09-17 10:00 
  2025-09-17 10:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Breaker Minor Maintenance:AW/4B Curve 117. WAPAEAST-WAPANORTH = 235. WYOEAST-AEOW (Aeolus West) = 1632. TOT4B-WYONORTH = 571. TOT 4B = 806. Potential Real Time Impact to Wyoming Generation:     2025-02-27 14:05     162572     2025-08-29 09:37  
  PPW 25-08524     18212     PPW     Aeolus-Clover 500 kV line,Aeolus: 500 kV South Bus          AEOLUS-CLOVER(PPW) 
  CLOVER-AEOLUS(PPW)   
  1394.0 
  1000.0   
  1394.0 
  1000.0   
  0.0 
  0.0   
  2025-09-15 07:00 
  2025-09-15 07:00   
  2025-09-23 07:00 
  2025-09-23 07:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Switch work/reactor work/Station service/Remove shoo fly at Aeolus, Little Snake, Coyote, Clover:AEOLUS-CLOVER=0; CLOVER-AEOLUS=0.:     2025-07-30 11:41     167630     2025-07-31 10:49  
  PPW 25-06790     18284     PPW     Dave Johnston: #1 Main Bank T2127          THERMALGEN-PACW(PPW)      9999.0      9999.0      0.0      2025-09-15 07:00      2025-09-16 15:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:**Commissioning Required** Install metering CT/VT on the 115kV high side of the U1 GSU.:Dave Johnston Unit #1 unavailable.:     2025-08-21 08:53     165891     2025-08-21 08:53  
  PPW 25-16657     18280     PPW     Dave Johnston-TSGT Laramie River Station 230 kV line          DJ-WYOEAST(PPW) 
  WYOEAST-DJ(PPW) 

  DJ-WYOEAST(PPW) 
  WYOEAST-DJ(PPW)   
  790.0 
  790.0 

  790.0 
  790.0   
  790.0 
  790.0 

  790.0 
  790.0   
  790.0 
  790.0 

  478.0 
  478.0   
  2025-09-10 07:00 
  2025-09-10 07:00 

  2025-09-15 07:00 
  2025-09-15 07:00   
  2025-09-15 07:00 
  2025-09-15 07:00 

  2025-09-19 15:00 
  2025-09-19 15:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:**Commissioning Required** Replace CB 1H268 and SW 1H7046:DJ-WYOEAST & WYOEAST-DJ = 442 (Dave Johnston-WAPA Stegall 230 kV line rating):     2025-08-20 13:00     175808     2025-09-05 11:00  
  PPW 25-15532     18285     PPW     Hale-Spanish Fork 138kV line          THERMALGEN-PACE(PPW)      9999.0      9999.0      0.0      2025-09-15 08:00      2025-09-19 14:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:A-condition str replacements:Possible real-time restriction to Lakeside 1 (Dynamo) generation.:     2025-08-21 09:03     174673     2025-08-21 09:03  
  PPW 25-03879     17708     PPW     Sweet Home: Main Bus Disc CB 4M94,Sweet Home: Bypass Bus Disc CB 4M94,Sweet Home: Line Disc CB 4M94          HYDROGEN-PACW(PPW)      9999.0      9999.0      0.0      2025-09-15 08:00      2025-09-19 15:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Breaker maintenance.:Fall Creek Hydro Units 1, 2, and 3 unavailable.:     2025-02-25 10:20     162961     2025-02-25 10:20  
  PPW 25-13053     18192     PPW     Merwin-Chelatchie Tap section of the Merwin-Yale 115 kV line          HYDROGEN-PACW(PPW)      9999.0      9999.0      0.0      2025-09-15 08:00      2025-09-19 17:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Replace the RAS Relays in Yale Lakes Line Bay.:May be Slight Impact on South of Allston Path. Eliminates Merwin/Yale Generation Delivery to the Portland Load Area. Yale units 1 and 2 unavailable.:     2025-07-18 11:09     172185     2025-07-18 11:12  
  PPW 25-06481     17833     PPW     Malin-PG&E Round Mountain #1 500 kV line          MALIN500-RDM500(PPW) 
  RDM500-MALIN500(PPW)   
  800.0 
  612.0   
  800.0 
  612.0   
  625.0 
  416.0   
  2025-09-17 06:00 
  2025-09-17 06:00   
  2025-09-19 17:00 
  2025-09-19 17:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Install lab measurement and fault initiating test equipment on primary conductors (Grounded).:MALIN500-RDM500 = 625. RDM500-MALIN500 = 416.:     2025-04-10 08:55     165580     2025-04-10 08:55  
  PPW 26-00006     18288     PPW     Dave Johnston: #2 Main T2130          THERMALGEN-PACW(PPW)      9999.0      9999.0      0.0      2025-09-17 07:00      2025-09-18 15:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:**Commissioning Required** Install metering CT/VT on the 115kV high side of the U2 GSU:Dave Johnston Unit #2 unavailable.:     2025-08-21 12:54     165892     2025-08-21 12:54  
  PPW 25-17055     18306     PPW     Goshen-Threemile Knoll 345 kV line,Goshen (Idaho): TIE CB 10A5,Goshen (Idaho): LINE CB 10A8,Threemil          GSHN-TMK(PPW) 
  JBSN-JB345(PPW) 
  NUT-PATHC(PPW) 
  PATHC-NUT(PPW) 
  TMK-GSHN(PPW)   
  317.0 
  1600.0 
  1060.0 
  1600.0 
  533.0   
  317.0 
  1600.0 
  1060.0 
  1600.0 
  533.0   
  117.0 
  1066.0 
  945.0 
  1600.0 
  0.0   
  2025-09-17 08:00 
  2025-09-17 08:00 
  2025-09-17 08:00 
  2025-09-17 08:00 
  2025-09-17 08:00   
  2025-09-18 14:00 
  2025-09-18 14:00 
  2025-09-18 14:00 
  2025-09-18 14:00 
  2025-09-18 14:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Replacing "A" insulators:JBSN-JB345= 1950. PacifiCorp = 1300. IPCo = 650. Potential Real Time Impact to Jim Bridger Generation. JB345-TMK & TMK-JB345 = 0 NUT-PATHC = 945 Summer/900 Winter. PATHC-NUT = 1050 Summer/1050 Winter.:     2025-08-29 11:19     176207     2025-08-29 11:29  
  PPW 25-13284     18242     PPW     Pendleton-Athena section of the Pendleton-Walla Walla 69 kV line,Weston (OR): SW 3W31          WINDGEN-PACW(PPW) 

  WINDGEN-PACW(PPW)   
  9999.0 

  9999.0   
  9999.0 

  9999.0   
  9999.0 

  0.0   
  2025-09-04 09:00 

  2025-09-17 09:00   
  2025-09-04 17:00 

  2025-09-18 17:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Replacing structure:Combine Hills Generation is restricted to 20 MW only during the line switching process (at the beginning and end of the line outage). Chopin Wind is restricted to 0 MW for the whole duration while tied to Central:     2025-08-05 09:30     172418     2025-08-11 08:54  
  PPW 25-17886     18313     PPW     Point of Rocks-Bitter Creek section of the Point of Rocks-Latham 230 kV line          AEOLUSGEN-AEOLUS(PPW) 
  OUTAGE-WYOCENTRAL(PPW) 
  STANDPIPE-WYOCENTRAL(PPW) 
  TOT4B-WYONORTH(PPW) 
  WAPAEAST-WAPANORTH(PPW) 
  WYOCENTRAL-STANDPIPE(PPW) 
  WYOEAST-AEOW(PPW) 

  AEOLUSGEN-AEOLUS(PPW) 
  OUTAGE-WYOCENTRAL(PPW) 
  STANDPIPE-WYOCENTRAL(PPW) 
  TOT4B-WYONORTH(PPW) 
  WAPAEAST-WAPANORTH(PPW) 
  WYOCENTRAL-STANDPIPE(PPW) 
  WYOEAST-AEOW(PPW) 

  AEOLUSGEN-AEOLUS(PPW) 
  OUTAGE-WYOCENTRAL(PPW) 
  STANDPIPE-WYOCENTRAL(PPW) 
  TOT4B-WYONORTH(PPW) 
  WAPAEAST-WAPANORTH(PPW) 
  WYOCENTRAL-STANDPIPE(PPW) 
  WYOEAST-AEOW(PPW)   
  2000.0 
  1.0 
  331.0 
  631.0 
  249.0 
  331.0 
  0.0 

  2000.0 
  1.0 
  331.0 
  631.0 
  249.0 
  331.0 
  0.0 

  2000.0 
  1.0 
  331.0 
  631.0 
  249.0 
  331.0 
  0.0   
  2000.0 
  1.0 
  331.0 
  631.0 
  249.0 
  331.0 
  0.0 

  2000.0 
  1.0 
  331.0 
  631.0 
  249.0 
  331.0 
  0.0 

  2000.0 
  1.0 
  331.0 
  631.0 
  249.0 
  331.0 
  0.0   
  1270.0 
  0.0 
  0.0 
  592.0 
  233.0 
  0.0 
  0.0 

  1270.0 
  0.0 
  0.0 
  592.0 
  233.0 
  0.0 
  0.0 

  2000.0 
  1.0 
  331.0 
  631.0 
  249.0 
  331.0 
  0.0   
  2025-09-18 05:00 
  2025-09-18 05:00 
  2025-09-18 05:00 
  2025-09-18 05:00 
  2025-09-18 05:00 
  2025-09-18 05:00 
  2025-09-18 05:00 

  2025-09-18 06:00 
  2025-09-18 06:00 
  2025-09-18 06:00 
  2025-09-18 06:00 
  2025-09-18 06:00 
  2025-09-18 06:00 
  2025-09-18 06:00 

  2025-09-18 17:00 
  2025-09-18 17:00 
  2025-09-18 17:00 
  2025-09-18 17:00 
  2025-09-18 17:00 
  2025-09-18 17:00 
  2025-09-18 17:00   
  2025-09-18 06:00 
  2025-09-18 06:00 
  2025-09-18 06:00 
  2025-09-18 06:00 
  2025-09-18 06:00 
  2025-09-18 06:00 
  2025-09-18 06:00 

  2025-09-18 17:00 
  2025-09-18 17:00 
  2025-09-18 17:00 
  2025-09-18 17:00 
  2025-09-18 17:00 
  2025-09-18 17:00 
  2025-09-18 17:00 

  2025-09-18 18:00 
  2025-09-18 18:00 
  2025-09-18 18:00 
  2025-09-18 18:00 
  2025-09-18 18:00 
  2025-09-18 18:00 
  2025-09-18 18:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Replacing 3/028 structure, A condition.:AW/4B Curve 107. WAPAEAST-WAPANORTH = 233. WYOCENTRAL-STANDPIPE = 0. TOT4B-WYONORTH = 592. TOT 4B = 825. Potential Real Time Impact to Wyoming Generation:     2025-09-03 15:31     177048     2025-09-08 10:00  
  PPW 25-17887     18314     PPW     Echo Springs-Latham section of the Point of Rocks-Latham 230 kV line          AEOLUSGEN-AEOLUS(PPW) 
  OUTAGE-WYOCENTRAL(PPW) 
  STANDPIPE-WYOCENTRAL(PPW) 
  TOT4B-WYONORTH(PPW) 
  WAPAEAST-WAPANORTH(PPW) 
  WYOCENTRAL-STANDPIPE(PPW) 
  WYOEAST-AEOW(PPW)   
  2000.0 
  1.0 
  331.0 
  631.0 
  249.0 
  331.0 
  0.0   
  2000.0 
  1.0 
  331.0 
  631.0 
  249.0 
  331.0 
  0.0   
  1270.0 
  0.0 
  0.0 
  592.0 
  233.0 
  0.0 
  0.0   
  2025-09-19 08:00 
  2025-09-19 08:00 
  2025-09-19 08:00 
  2025-09-19 08:00 
  2025-09-19 08:00 
  2025-09-19 08:00 
  2025-09-19 08:00   
  2025-09-19 15:00 
  2025-09-19 15:00 
  2025-09-19 15:00 
  2025-09-19 15:00 
  2025-09-19 15:00 
  2025-09-19 15:00 
  2025-09-19 15:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Replacing 2/078 structure, A condition.:AW/4B Curve 107. WAPAEAST-WAPANORTH = 233. WYOCENTRAL-STANDPIPE = 0. TOT4B-WYONORTH = 592. TOT 4B = 825. Potential Real Time Impact to Wyoming Generation:     2025-09-03 15:39     177049     2025-09-03 15:40  
  PPW 25-17454     18303     PPW     Burns: Series Cap Segment #1 & 2,Burns: SW 11D10          BORA-M500(PPW) 
  SMLK-H500(PPW)   
  1090.0 
  100.0   
  1090.0 
  100.0   
  1070.0 
  96.0   
  2025-09-22 06:00 
  2025-09-22 06:00   
  2025-11-07 16:00 
  2025-11-07 16:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Bypass capacitors to keep IPCO 138kV system within system operating limits.:JBSN-JB345 = 2100. PacifiCorp = 1400. IPCo = 700; Path 75 limited to 535. SMLK-H500 = 96; BORA-M500 = 1070;:     2025-08-28 12:33     176613     2025-08-28 12:34  
  PPW 26-00002     17627     PPW     IPC Midpoint-Hemingway 500 kV line,IPCo Midpoint: 500/345 kV Bank T-501          H500-M500(PPW) 
  M500-H500(PPW) 
  PACW-NTLOAD(PPW) 

  H500-M500(PPW) 
  M500-H500(PPW) 
  PACW-NTLOAD(PPW)   
  800.0 
  1090.0 
  9999.0 

  800.0 
  1090.0 
  9999.0   
  800.0 
  1090.0 
  9999.0 

  800.0 
  1090.0 
  9999.0   
  350.0 
  350.0 
  0.0 

  800.0 
  1090.0 
  9999.0   
  2025-09-22 06:00 
  2025-09-22 06:00 
  2025-09-22 06:00 

  2026-02-23 08:00 
  2026-02-23 08:00 
  2026-02-23 08:00   
  2025-11-07 16:00 
  2025-11-07 16:00 
  2025-11-07 16:00 

  2026-05-29 15:00 
  2026-05-29 15:00 
  2026-05-29 15:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:This outage is for relocating the existing Midpoint T501 345kV/500kV transformer to a new 345kV station bay.:M500-H500 & H500-M500= 350. BORA-M500 = 959. No impact to Bridger West. Jim Bridger Generation may be restricted real time (as determined by Northwest Path Flow). Network Load Service Arrangements may be required for Southern Oregon Load. Note: TTC Schedules on Path 75 East & West are 0. However, the SOL is 350 West / 325 East (Limited by Bowmont Xfmrs). However, there is a potential of up to 300 mw of actual unscheduled inadvertent flow between Hemingway & Summer Lake. JBSN-JB345 = 2200. PacifiCorp = 1467. IPCo = 733. Jim Bridger Generation may be restricted real time (as determined by Northwest Path Flow).:     2025-01-28 09:16     161059     2025-05-05 13:54  
  PPW 25-16658     18290     PPW     Dave Johnston-WAPA Goshen 230 kV line          DJ-WYOEAST(PPW) 
  WYOEAST-AEOW(PPW) 
  WYOEAST-DJ(PPW)   
  790.0 
  0.0 
  790.0   
  790.0 
  0.0 
  790.0   
  441.0 
  0.0 
  441.0   
  2025-09-22 07:00 
  2025-09-22 07:00 
  2025-09-22 07:00   
  2025-09-26 15:00 
  2025-09-26 15:00 
  2025-09-26 15:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:**Commissioning Required** Replace CB 1H204 and SW 1H7052:DJ-WYOE & WYOE-DJ = 478 (Dave Johnston-TSGT Laramie River Station 230 kV line rating).:     2025-08-22 10:01     175809     2025-08-22 10:03  
  PPW 25-04835     18040     PPW     Weed Junction: SW 2G27,Weed Junction: PST T-3726,Weed Junction: WEEDJUNC CS 2G50,Crag View: C/S 2G48               0.0      0.0      0.0      2025-09-22 08:00      2025-10-07 14:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:TCOH on Phase shifter at weed JCT:     2025-07-02 08:32     163923     2025-09-03 15:57  
  PPW 25-14736     18229     PPW     Black Rock-Osceola 230 kV line          GON.PAV-PAVANT(PPW) 
  PAVANT-GON.PAV(PPW)   
  130.0 
  139.0   
  130.0 
  139.0   
  0.0 
  0.0   
  2025-09-22 08:30 
  2025-09-22 08:30   
  2025-09-23 17:00 
  2025-09-23 17:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Changing Wingarms between Blackrock and State Line:PAVANT-GON.PAV = 0. GON.PAV-PAVANT = 0.:     2025-08-01 11:11     173874     2025-08-01 11:11  
  PPW 25-14736     18230     PPW     Black Rock-Osceola 230 kV line               0.0      0.0      0.0      2025-09-22 08:30      2025-09-23 17:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Changing Wingarms between Blackrock and State Line:PAVANT-GON.PAV = 0. GON.PAV-PAVANT = 0.:     2025-08-01 11:11     173874     2025-08-01 11:11  
  PPW 25-03491     17721     PPW     Atlantic City: LINE CB 1H116,Atlantic City: SW 1H118,Wyopo: LINERUPTOR 1H99,Wyopo-Atlantic City sect          TOT4B-WYONORTH(PPW) 
  WAPAEAST-WAPANORTH(PPW) 
  WYOCENTRAL-WYOEAST(PPW) 
  WYOEAST-AEOW(PPW) 
  WYOEAST-WYOCENTRAL(PPW) 

  TOT4B-WYONORTH(PPW) 
  WAPAEAST-WAPANORTH(PPW) 
  WYOCENTRAL-WYOEAST(PPW) 
  WYOEAST-AEOW(PPW) 
  WYOEAST-WYOCENTRAL(PPW) 

  TOT4B-WYONORTH(PPW) 
  WAPAEAST-WAPANORTH(PPW) 
  WYOCENTRAL-WYOEAST(PPW) 
  WYOEAST-AEOW(PPW) 
  WYOEAST-WYOCENTRAL(PPW) 

  TOT4B-WYONORTH(PPW) 
  WAPAEAST-WAPANORTH(PPW) 
  WYOCENTRAL-WYOEAST(PPW) 
  WYOEAST-AEOW(PPW) 
  WYOEAST-WYOCENTRAL(PPW) 

  TOT4B-WYONORTH(PPW) 
  WAPAEAST-WAPANORTH(PPW) 
  WYOCENTRAL-WYOEAST(PPW) 
  WYOEAST-AEOW(PPW) 
  WYOEAST-WYOCENTRAL(PPW) 

  TOT4B-WYONORTH(PPW) 
  WAPAEAST-WAPANORTH(PPW) 
  WYOCENTRAL-WYOEAST(PPW) 
  WYOEAST-AEOW(PPW) 
  WYOEAST-WYOCENTRAL(PPW)   
  631.0 
  249.0 
  574.0 
  0.0 
  574.0 

  631.0 
  249.0 
  574.0 
  0.0 
  574.0 

  631.0 
  249.0 
  574.0 
  0.0 
  574.0 

  631.0 
  249.0 
  574.0 
  0.0 
  574.0 

  631.0 
  249.0 
  574.0 
  0.0 
  574.0 

  631.0 
  249.0 
  574.0 
  0.0 
  574.0   
  631.0 
  249.0 
  574.0 
  0.0 
  574.0 

  631.0 
  249.0 
  574.0 
  0.0 
  574.0 

  631.0 
  249.0 
  574.0 
  0.0 
  574.0 

  631.0 
  249.0 
  574.0 
  0.0 
  574.0 

  631.0 
  249.0 
  574.0 
  0.0 
  574.0 

  631.0 
  249.0 
  574.0 
  0.0 
  574.0   
  631.0 
  249.0 
  574.0 
  0.0 
  574.0 

  631.0 
  249.0 
  574.0 
  0.0 
  574.0 

  631.0 
  249.0 
  574.0 
  0.0 
  574.0 

  571.0 
  235.0 
  287.0 
  0.0 
  287.0 

  571.0 
  235.0 
  287.0 
  0.0 
  287.0 

  631.0 
  249.0 
  574.0 
  0.0 
  574.0   
  2025-06-04 11:00 
  2025-06-04 11:00 
  2025-06-04 11:00 
  2025-06-04 11:00 
  2025-06-04 11:00 

  2025-07-30 11:00 
  2025-07-30 11:00 
  2025-07-30 11:00 
  2025-07-30 11:00 
  2025-07-30 11:00 

  2025-08-27 11:00 
  2025-08-27 11:00 
  2025-08-27 11:00 
  2025-08-27 11:00 
  2025-08-27 11:00 

  2025-09-22 10:00 
  2025-09-22 10:00 
  2025-09-22 10:00 
  2025-09-22 10:00 
  2025-09-22 10:00 

  2025-09-22 11:00 
  2025-09-22 11:00 
  2025-09-22 11:00 
  2025-09-22 11:00 
  2025-09-22 11:00 

  2025-09-24 15:00 
  2025-09-24 15:00 
  2025-09-24 15:00 
  2025-09-24 15:00 
  2025-09-24 15:00   
  2025-06-06 16:30 
  2025-06-06 16:30 
  2025-06-06 16:30 
  2025-06-06 16:30 
  2025-06-06 16:30 

  2025-08-01 16:30 
  2025-08-01 16:30 
  2025-08-01 16:30 
  2025-08-01 16:30 
  2025-08-01 16:30 

  2025-08-29 16:30 
  2025-08-29 16:30 
  2025-08-29 16:30 
  2025-08-29 16:30 
  2025-08-29 16:30 

  2025-09-22 11:00 
  2025-09-22 11:00 
  2025-09-22 11:00 
  2025-09-22 11:00 
  2025-09-22 11:00 

  2025-09-24 15:00 
  2025-09-24 15:00 
  2025-09-24 15:00 
  2025-09-24 15:00 
  2025-09-24 15:00 

  2025-09-24 16:30 
  2025-09-24 16:30 
  2025-09-24 16:30 
  2025-09-24 16:30 
  2025-09-24 16:30   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Breaker Minor Maintenance 1H116:AW/4B Curve 117. WAPAEAST-WAPANORTH = 235. WYOEAST-AEOW (Aeolus West) = 1632. TOT4B-WYONORTH = 571. TOT 4B = 806. Potential Real Time Impact to Wyoming Generation:     2025-02-27 14:17     162573     2025-09-08 10:23  
  PPW 25-13898     18213     PPW     Little Snake: SW 11B4,Little Snake: Reactor #1 116.1 MVAR,Aeolus-Clover 500 kV line,Clover: SW 11B11          AEOLUS-CLOVER(PPW) 
  CLOVER-AEOLUS(PPW) 

  AEOLUS-CLOVER(PPW) 
  CLOVER-AEOLUS(PPW) 

  AEOLUS-CLOVER(PPW) 
  CLOVER-AEOLUS(PPW)   
  1394.0 
  1000.0 

  1394.0 
  1000.0 

  1394.0 
  1000.0   
  1394.0 
  1000.0 

  1394.0 
  1000.0 

  1394.0 
  1000.0   
  0.0 
  0.0 

  0.0 
  0.0 

  0.0 
  0.0   
  2025-09-23 06:30 
  2025-09-23 06:30 

  2025-09-23 08:30 
  2025-09-23 08:30 

  2025-10-02 07:30 
  2025-10-02 07:30   
  2025-09-23 08:30 
  2025-09-23 08:30 

  2025-10-02 07:30 
  2025-10-02 07:30 

  2025-10-02 09:30 
  2025-10-02 09:30   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Warranty work to replace oil valve on Little Snake reactor #1:CLOVER-AEOLUS and AEOLUS-CLOVER=0 DURING SWITCHING ONLY.:     2025-07-30 14:31     173034     2025-07-30 14:34  
  PPW 25-14749     18231     PPW     Pavant-Sigurd 230 kV line          PACE-PAVANT(PPW) 
  PAVANT-GON.PAV(PPW) 
  PAVANT-PACE(PPW)   
  150.0 
  139.0 
  150.0   
  150.0 
  139.0 
  150.0   
  0.0 
  0.0 
  0.0   
  2025-09-24 07:30 
  2025-09-24 07:30 
  2025-09-24 07:30   
  2025-09-26 17:00 
  2025-09-26 17:00 
  2025-09-26 17:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Change Wingarm and Insulator Changeouts:PACE-PAVANT, PAVANT-PACE & PAVANT-GON.PAV = 0. GON.PAV-PAVANT = Black Rock & Pavant load.:     2025-08-01 11:17     173887     2025-08-01 11:18  
  PPW 25-17893     18315     PPW     Atlantic City-Rock Springs 230 kV line          TOT4B-WYONORTH(PPW) 
  WAPAEAST-WAPANORTH(PPW) 
  WYOCENTRAL-WYOEAST(PPW) 
  WYOEAST-AEOW(PPW) 
  WYOEAST-WYOCENTRAL(PPW)   
  631.0 
  249.0 
  574.0 
  0.0 
  574.0   
  631.0 
  249.0 
  574.0 
  0.0 
  574.0   
  571.0 
  235.0 
  287.0 
  0.0 
  287.0   
  2025-09-25 06:00 
  2025-09-25 06:00 
  2025-09-25 06:00 
  2025-09-25 06:00 
  2025-09-25 06:00   
  2025-10-17 18:00 
  2025-10-17 18:00 
  2025-10-17 18:00 
  2025-10-17 18:00 
  2025-10-17 18:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Working on A conditions.:AW/4B Curve 117. WAPAEAST-WAPANORTH = 235. WYOCENTRAL-WYOEAST=287. TOT4B-WYONORTH = 571. TOT 4B = 806. Potential Real Time Impact to Wyoming Generation:     2025-09-03 15:56     177055     2025-09-04 12:27  
  PPW 25-16930     18318     PPW     Firehole-WAPA Flaming Gorge 230 kV line,Little Mountain (WY): LINERUPTER 1H26,Little Mtn-Flaming Gor          FGE-WYOCENTRAL(PPW) 
  THERMALGEN-PACE(PPW) 
  WYOCENTRAL-FGE(PPW) 

  FGE-WYOCENTRAL(PPW) 
  THERMALGEN-PACE(PPW) 
  WYOCENTRAL-FGE(PPW)   
  200.0 
  9999.0 
  200.0 

  200.0 
  9999.0 
  200.0   
  200.0 
  9999.0 
  200.0 

  200.0 
  9999.0 
  200.0   
  200.0 
  9999.0 
  200.0 

  0.0 
  0.0 
  0.0   
  2025-09-24 07:00 
  2025-09-24 07:00 
  2025-09-24 07:00 

  2025-09-25 07:00 
  2025-09-25 07:00 
  2025-09-25 07:00   
  2025-09-24 14:00 
  2025-09-24 14:00 
  2025-09-24 14:00 

  2025-09-25 14:00 
  2025-09-25 14:00 
  2025-09-25 14:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Perform WECC Critical maintenance on Powerline Carrier between Firehole Substation and WAPA Flaming Gorge Sub.:Flaming Gorge aggregate generation limited below 90MW. FGE-WYOCENTRAL & WYOCENTRAL-FGE: 0:     2025-09-04 12:04     176082     2025-09-04 14:28  
  PPW 25-11740     18044     PPW     Huntington-Spanish Fork 345 kV line               0.0      0.0      0.0      2025-09-25 07:00      2025-09-30 16:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Spanish Fork-Huntington Pole Replacement:No impact under normal conditions.:     2025-07-02 13:57     170869     2025-07-02 13:57  
  PPW 25-15979     18286     PPW     Pomona-BPA Vantage 230 kV line          MIDC-YAKIMA(PPW) 
  PACW-NTLOAD(PPW) 
  YAKIMA-MIDC(PPW)   
  402.0 
  9999.0 
  402.0   
  402.0 
  9999.0 
  402.0   
  402.0 
  0.0 
  402.0   
  2025-09-29 07:00 
  2025-09-29 07:00 
  2025-09-29 07:00   
  2025-10-03 17:00 
  2025-10-03 17:00 
  2025-10-03 17:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Changning out dampers on the river crossing 3/39:No impact to Yakima load service with two 230 kV lines in service. Network Load Service Arrangements may be required.:     2025-08-21 11:33     175122     2025-08-21 11:33  
  PPW 25-17736     18320     PPW     Rolling Hills Wind Collector: 34 kV Circuit #6          WINDGEN-PACW(PPW)      9999.0      9999.0      0.0      2025-09-30 07:00      2025-09-30 14:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:RH1-610 pad mount transformer vault replacement:Rolling Hills Wind Collector Feeder #6 unavailable.:     2025-09-05 13:12     176898     2025-09-05 13:12  
  PPW 25-13899     18220     PPW     Coyote: Reactor #1 116.1 MVAR,Coyote: SW 11B4,Aeolus-Clover 500 kV line,Aeolus: SW 11G56,Clover: SW          AEOLUS-CLOVER(PPW) 
  CLOVER-AEOLUS(PPW) 

  AEOLUS-CLOVER(PPW) 
  CLOVER-AEOLUS(PPW)   
  1394.0 
  1000.0 

  1394.0 
  1000.0   
  1394.0 
  1000.0 

  1394.0 
  1000.0   
  0.0 
  0.0 

  0.0 
  0.0   
  2025-10-02 08:30 
  2025-10-02 08:30 

  2025-10-10 08:30 
  2025-10-10 08:30   
  2025-10-02 09:30 
  2025-10-02 09:30 

  2025-10-10 09:30 
  2025-10-10 09:30   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Warranty work to replace oil valve on Coyote reactor #1:CLOVER-AEOLUS and AEOLUS-CLOVER=0 DURING SWITCHING ONLY.:     2025-07-31 10:35     173035     2025-07-31 10:41  
  PPW 25-09173     17952     PPW     Hopland-Union Gap section of the BPA Moxee-Union Gap 115 kV line,Hopland: C/S 2Y53,Hopland: Bank #1,               0.0      0.0      0.0      2025-10-02 12:00      2025-10-24 23:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Install Conduit and Panel 4R. Replace SW 2Y52, 2Y531 and MO, 115kV Bus Tie SW and XFMR BK #1 Relay upgrade. :Hopland will be fed from BPA Moxee. Network Load Service Arrangements may be required.:     2025-05-31 21:25     168280     2025-08-26 15:51  
  PPW 25-15980     18287     PPW     GCPD Wanapum-Pomona 230 kV line,Pomona Heights: POMONAHE GND SW 1Y507          MIDC-YAKIMA(PPW) 
  PACW-NTLOAD(PPW) 
  YAKIMA-MIDC(PPW)   
  402.0 
  9999.0 
  402.0   
  402.0 
  9999.0 
  402.0   
  402.0 
  0.0 
  402.0   
  2025-10-06 07:00 
  2025-10-06 07:00 
  2025-10-06 07:00   
  2025-10-10 17:00 
  2025-10-10 17:00 
  2025-10-10 17:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Changing out insulators at pole 5/24. replace armor rod on multiple structures.:No impact to Yakima load service with two 230 kV lines in service. Network Load Service Arrangements may be required.:     2025-08-21 12:00     175123     2025-08-21 12:01  
  PPW 25-15674     18258     PPW     Mile Hi: CB 5L104          OTHERGEN-PACW(PPW) 

  OTHERGEN-PACW(PPW)   
  9999.0 

  9999.0   
  9999.0 

  9999.0   
  9999.0 

  0.0   
  2025-09-03 08:00 

  2025-10-07 08:00   
  2025-09-03 16:00 

  2025-10-08 16:00   
  SCHEDULED     DISTRIBUTION     PLANNED      ONPATH     PPW     continuous:Relay setting change and test.:Metzger Solar unavailable.:     2025-08-09 12:00     174815     2025-08-26 14:45  
  PPW 25-15692     18259     PPW     Mile Hi: CB 5L105          OTHERGEN-PACW(PPW) 

  OTHERGEN-PACW(PPW)   
  9999.0 

  9999.0   
  9999.0 

  9999.0   
  9999.0 

  0.0   
  2025-09-04 08:00 

  2025-10-09 08:00   
  2025-09-04 16:00 

  2025-10-10 16:00   
  SCHEDULED     DISTRIBUTION     PLANNED      ONPATH     PPW     continuous:Relay setting change and testing.:Black Cap Solar unavailable.:     2025-08-09 12:00     174833     2025-08-26 14:46  
  PPW 25-13902     18221     PPW     Coyote: Reactor #2 116.1 MVAR,Coyote: SW 11B9,Aeolus: SW 11G56,Clover: SW 11B114,Aeolus-Clover 500 k          AEOLUS-CLOVER(PPW) 
  CLOVER-AEOLUS(PPW) 

  AEOLUS-CLOVER(PPW) 
  CLOVER-AEOLUS(PPW)   
  1394.0 
  1000.0 

  1394.0 
  1000.0   
  1394.0 
  1000.0 

  1394.0 
  1000.0   
  0.0 
  0.0 

  0.0 
  0.0   
  2025-10-10 08:30 
  2025-10-10 08:30 

  2025-10-20 08:30 
  2025-10-20 08:30   
  2025-10-10 09:30 
  2025-10-10 09:30 

  2025-10-20 09:30 
  2025-10-20 09:30   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Warranty work to replace oil valve on Coyote reactor #2:CLOVER-AEOLUS and AEOLUS-CLOVER=0 DURING SWITCHING ONLY.:     2025-07-31 10:43     173038     2025-07-31 10:43  
  PPW 25-09054     17933     PPW     Gala Solar: Xfmr T1          OTHERGEN-PACW(PPW) 

  OTHERGEN-PACW(PPW)   
  9999.0 

  9999.0   
  9999.0 

  9999.0   
  0.0 

  9999.0   
  2025-09-29 18:45 

  2025-10-14 07:00   
  2025-10-01 16:00 

  2025-10-15 16:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Three-year substation preventative maintenance.:Gala Solar offline.:     2025-05-21 14:37     168161     2025-05-21 14:37  
  PPW 25-07860     17890     PPW     WAPA Thermopolis-Hilltop-WAPA Lovell 115 kV line          YTP-WYONORTH(PPW)      400.0      400.0      377.0      2025-10-14 07:00      2025-10-20 11:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Replace Nahne Jensen Line switches NJ-5761 and NJ-5765.:YTP-WYONORTH = 377. YTS = Series #11: TTC of 589 (PACE = 377 & LAPT = 212).:     2025-05-02 13:30     166966     2025-05-02 13:30  
  PPW 25-00010     16953     PPW     Hemingway-Summer Lake 500 kV line          H500-SMLK(PPW) 
  PACW-NTLOAD(PPW) 
  SMLK-H500(PPW) 

  H500-SMLK(PPW) 
  PACW-NTLOAD(PPW) 
  SMLK-H500(PPW)   
  1500.0 
  9999.0 
  100.0 

  1500.0 
  9999.0 
  100.0   
  1500.0 
  9999.0 
  100.0 

  1500.0 
  9999.0 
  100.0   
  1500.0 
  9999.0 
  100.0 

  0.0 
  0.0 
  0.0   
  2025-04-01 08:00 
  2025-04-01 08:00 
  2025-04-01 08:00 

  2025-10-17 08:00 
  2025-10-17 08:00 
  2025-10-17 08:00   
  2025-09-14 18:00 
  2025-09-14 18:00 
  2025-09-14 18:00 

  2025-10-31 18:00 
  2025-10-31 18:00 
  2025-10-31 18:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Spacer Replacements:H500-SMLK & SMLK-H500 = 0; BORA-M500 = 959; Network Load Service Arrangements may be required for Southern Oregon Load.:     2024-04-30 09:25     144659     2024-12-20 09:45  
  PPW 25-08635     17922     PPW     BPA Captain Jack-Grizzly-Ponderosa #1 500 kV line          BPAT.PACW-PONDEROSA230(PPW)      267.0      267.0      267.0      2025-10-21 08:00      2025-10-21 09:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:DE-ENERGIZE LINE FOR DEADLINE SWITCHING AT POND:BPAT.PACW-PONDEROSA230 = 555 Summer/ 700 Winter:     2025-05-15 11:16     167741     2025-05-15 11:16  
  PPW 25-09174     18000     PPW     Hopland-Union Gap section of the BPA Moxee-Union Gap 115 kV line,Hopland: Bank #1,Hopland: Bank #2               0.0      0.0      0.0      2025-10-24 23:00      2025-10-25 05:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Install Bus between SW 2Y51, 2Y61 and 115kV Bus Tie SW:Hopland will be fed from BPA Moxee. Network Load Service Arrangements may be required.:     2025-06-16 08:07     168281     2025-08-26 15:52  
  PPW 25-16679     18281     PPW     BPA: AC, DC, WS, and Synchrophasor RAS Controllers          THERMALGEN-PACW(PPW)      9999.0      9999.0      0.0      2025-10-25 11:00      2025-10-25 11:30      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:RAS WS-A CONTROLLER,MUNRO: RAS WS-B CONTROLLER ANNUAL SYSTEM TESTING :Chehalis Powerhouse unavailable.:     2025-08-20 13:56     175830     2025-08-20 14:05  
  PPW 25-07978     17897     PPW     WAPA Thermopolis-Hilltop-WAPA Lovell 115 kV line          YTP-WYONORTH(PPW) 

  YTP-WYONORTH(PPW) 

  YTP-WYONORTH(PPW)   
  400.0 

  400.0 

  400.0   
  400.0 

  400.0 

  400.0   
  400.0 

  400.0 

  377.0   
  2025-06-25 11:01 

  2025-07-21 07:00 

  2025-10-27 07:00   
  2025-06-27 16:00 

  2025-07-24 15:00 

  2025-10-29 11:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Replace broken insulators:YTP-WYONORTH = 377. YTS = Series #11: TTC of 589 (PACE = 377 & LAPT = 212).:     2025-05-05 09:53     167084     2025-07-03 09:09  
  PPW 25-08632     17921     PPW     BPA Captain Jack-Grizzly-Ponderosa #1 500 kV line          BPAT.PACW-PONDEROSA230(PPW)      267.0      267.0      267.0      2025-10-31 14:00      2025-10-31 15:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:DE-ENERGIZE LINE FOR DEADLINE SWITCHING AT POND:BPAT.PACW-PONDEROSA230 = 555 Summer/ 700 Winter:     2025-05-15 11:14     167738     2025-05-15 11:14  
  PPW 25-16504     18274     PPW     Malin-PG&E Round Mountain #2 500 kV line          MALIN500-RDM500(PPW) 
  RDM500-MALIN500(PPW)   
  800.0 
  612.0   
  800.0 
  612.0   
  600.0 
  416.0   
  2025-11-05 05:30 
  2025-11-05 05:30   
  2025-11-06 17:30 
  2025-11-06 17:30   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Path restriction for PAC 25-15610.:MALIN500-RDM500 = 600. RDM500-MALIN500 = 416.:     2025-08-18 13:34     175649     2025-08-18 13:34  
  PPW 25-18118     18319     PPW     BPA McNary: CB L366,BPA McNary: Bypass Bus SW to CB L366,BPA McNary: Line SW to CB L366,BPA McNary:          WINDGEN-PACW(PPW)      9999.0      9999.0      0.0      2025-11-13 07:00      2025-11-13 15:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Circuit breaker maintenance.:Orchard Wind Farm restricted to 0 MW.:     2025-09-05 11:26     177282     2025-09-05 11:26  
  PPW 25-10042     17988     PPW     Jim Bridger-Mustang 230 kV line,Mustang-WAPA Spence 230 kV line          JBSN-WYOCENTRAL(PPW) 
  TOT4B-WYONORTH(PPW) 
  WAPAEAST-WAPANORTH(PPW) 
  WYOCENTRAL-JBSN(PPW) 
  WYOCENTRAL-WYOEAST(PPW) 
  WYOEAST-AEOW(PPW) 
  WYOEAST-WYOCENTRAL(PPW)   
  600.0 
  631.0 
  249.0 
  600.0 
  574.0 
  0.0 
  574.0   
  600.0 
  631.0 
  249.0 
  600.0 
  574.0 
  0.0 
  574.0   
  400.0 
  631.0 
  243.0 
  400.0 
  287.0 
  0.0 
  287.0   
  2025-11-19 07:15 
  2025-11-19 07:15 
  2025-11-19 07:15 
  2025-11-19 07:15 
  2025-11-19 07:15 
  2025-11-19 07:15 
  2025-11-19 07:15   
  2025-11-21 14:00 
  2025-11-21 14:00 
  2025-11-21 14:00 
  2025-11-21 14:00 
  2025-11-21 14:00 
  2025-11-21 14:00 
  2025-11-21 14:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Mustang: Remove 230 kV Shoo Fly:AW/4B Curve 121. WAPAEAST-WAPANORTH = 243. WYOEAST-AEOW (Aeolus West) = 1627. TOT4B-WYONORTH = 631. TOT 4B = 874. JBSN-WYOC & WYOC-JBSN = 400. Potential Real Time Impact to Wyoming Generation Great Divide will be radial from WAPA Spence via Mustang. Network Load Service Arrangements may be required.:     2025-06-10 12:20     169155     2025-06-10 12:50  
  PPW 26-00007     17980     PPW     Hemingway-Summer Lake 500 kV line          BORA-M500(PPW) 
  H500-SMLK(PPW) 
  PACW-NTLOAD(PPW) 
  SMLK-H500(PPW)   
  1090.0 
  1500.0 
  9999.0 
  100.0   
  1090.0 
  1500.0 
  9999.0 
  100.0   
  959.0 
  0.0 
  0.0 
  0.0   
  2026-05-11 08:00 
  2026-05-11 08:00 
  2026-05-11 08:00 
  2026-05-11 08:00   
  2026-05-22 18:00 
  2026-05-22 18:00 
  2026-05-22 18:00 
  2026-05-22 18:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Spacer Replacements:H500-SMLK & SMLK-H500 = 0; BORA-M500 = 959; Network Load Service Arrangements may be required for Southern Oregon Load.:     2025-06-09 09:44     168591     2025-06-09 09:46  
  PPW 24-04189     16311     PPW     Cove (OR): 230/69 kV Bank #2 (T3398)          COVEPACW-ROUNDBUTTE(PPW) 
  ROUNDBUTTE-COVEPACW(PPW) 

  COVEPACW-ROUNDBUTTE(PPW) 
  ROUNDBUTTE-COVEPACW(PPW) 

  COVEPACW-ROUNDBUTTE(PPW) 
  ROUNDBUTTE-COVEPACW(PPW) 

  COVEPACW-ROUNDBUTTE(PPW) 
  ROUNDBUTTE-COVEPACW(PPW) 

  COVEPACW-ROUNDBUTTE(PPW) 
  ROUNDBUTTE-COVEPACW(PPW)   
  123.0 
  123.0 

  123.0 
  123.0 

  123.0 
  123.0 

  123.0 
  123.0 

  123.0 
  123.0   
  123.0 
  123.0 

  123.0 
  123.0 

  123.0 
  123.0 

  123.0 
  123.0 

  123.0 
  123.0   
  123.0 
  123.0 

  123.0 
  123.0 

  123.0 
  123.0 

  123.0 
  123.0 

  60.0 
  60.0   
  2024-07-01 12:00 
  2024-07-01 12:00 

  2024-10-14 12:00 
  2024-10-14 12:00 

  2025-04-28 12:00 
  2025-04-28 12:00 

  2025-07-07 12:00 
  2025-07-07 12:00 

  2026-07-06 12:00 
  2026-07-06 12:00   
  2024-07-21 12:00 
  2024-07-21 12:00 

  2024-11-01 12:00 
  2024-11-01 12:00 

  2025-05-30 12:00 
  2025-05-30 12:00 

  2025-08-01 12:00 
  2025-08-01 12:00 

  2026-07-31 12:00 
  2026-07-31 12:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:T-3398 LTC Maintenance and Bushing Replacement:COVEPACW-ROUNDBUTTE & ROUNDBUTTE-COVEPACW = 60.:     2024-03-15 09:39     142013     2025-06-18 08:34  