PPW Outages 
Apr 26, 2025 - Apr 30, 2026
Report created on Apr 30, 2025 at 21:28 (PPT)
Outage
Name
Outage
Id
Company Facility Flow
Gate
Segment/
JOTSFacility
Original
TTC In
Original
TTC Out
New
TTC
Start Time (PPT) Stop Time (PPT) Status Outage
Category
Outage
Type
Path
Impact
Report
TPs
Annotation Creation Time (PPT) EventId Last Updated (PPT)
  PPW 171983     10361     PPW     Riverton: 230 kV Cap Bank S/C 472               0.0      0.0      0.0      2021-02-18 09:03      2025-06-05 17:00      ACTIVE     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Riverton: 230 kV Cap Bank S/C 472:     2022-11-14 00:32     75797     2025-01-30 13:48  
  PPW 175805     9275     PPW     Hemingway-Summer Lake 500 kV line (Path 75 Schedule Limitation)          H500-SMLK(PPW) 

  H500-SMLK(PPW)   
  1500.0 

  1500.0   
  1500.0 

  1500.0   
  1386.0 

  1386.0   
  2021-06-02 12:00 

  2024-12-04 12:00   
  2024-12-04 12:00 

  2025-12-31 12:00   
  ACTIVE     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Hemingway-Summer Lake 500 kV line (Path 75 Schedule Limitation)..:Path Restriction Notes: Path 75 Westbound = 1386.:     2021-12-21 14:06     80760     2024-12-04 08:04  
  PPW 23-19877     14565     PPW     Populus: 345 kV Series Capacitor #1 (C2)          JBSN-JB345(PPW) 

  JBSN-JB345(PPW)   
  1600.0 

  1600.0   
  1600.0 

  1600.0   
  1600.0 

  1433.0   
  2023-10-27 05:26 

  2023-10-27 05:26   
  2023-10-27 05:26 

  2025-12-31 17:00   
  ACTIVE     TRANSMISSION     FORCED      ONPATH     PPW     continuous:Segment two controller not working properly:JBSN-JB345 = 2150. PacifiCorp = 1433. IPCo = 717.:     2023-12-04 13:10     134273     2024-12-30 12:03  
  PPW 24-00488     15058     PPW     Burns: Series Cap Segment #1 & 2          BORA-M500(PPW) 
  PACW-SMLK(PPW) 
  SMLK-H500(PPW) 

  BORA-M500(PPW) 
  PACW-SMLK(PPW) 
  SMLK-H500(PPW)   
  1090.0 
  550.0 
  100.0 

  1090.0 
  550.0 
  100.0   
  1090.0 
  550.0 
  100.0 

  1090.0 
  550.0 
  100.0   
  1090.0 
  550.0 
  100.0 

  1070.0 
  535.0 
  96.0   
  2024-01-09 03:48 
  2024-01-09 03:48 
  2024-01-09 03:48 

  2024-01-09 03:48 
  2024-01-09 03:48 
  2024-01-09 03:48   
  2024-01-09 03:48 
  2024-01-09 03:48 
  2024-01-09 03:48 

  2025-05-30 23:59 
  2025-05-30 23:59 
  2025-05-30 23:59   
  ACTIVE     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Investigating a possible failure of relay voltage sensing component.:Path 75 limited to 507 (Midpoint Series Caps bypassed for maint). SMLK-H500 = 96; BORA-M500 = 959;:     2024-01-03 10:34     138306     2025-04-25 09:57  
  PPW 24-06062     16750     PPW     Path 25 Schedule Limitation (Cascade 115 kV Tie)          CRAGVIEW-PACW(PPW) 

  CRAGVIEW-PACW(PPW)   
  108.0 

  108.0   
  108.0 

  108.0   
  0.0 

  0.0   
  2024-04-09 00:00 

  2024-04-09 02:35   
  2024-04-09 02:35 

  2026-04-09 00:00   
  ACTIVE     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:CRAGVIEW-PACW TTC = 0 PER PLANNING.:CRAGVIEW-PACW = 0 INDEFINITELY:     2024-04-09 09:34     143888     2025-04-07 18:15  
  PPW 24-06351     17531     PPW     Threemile Knoll: TIE CB 335               0.0      0.0      0.0      2024-04-12 22:23      2025-05-26 17:00      ACTIVE     TRANSMISSION     FORCED      ONPATH     PPW     continuous:***Commissioning Required*** Investigate failure of CB 335. :     2024-12-02 14:23     144180     2025-04-25 12:27  
  PPW 24-15751     17530     PPW     Threemile Knoll: Series Cap C2,Threemile Knoll: Series Cap C1          JBSN-JB345(PPW) 
  NUT-PATHC(PPW) 
  PATHC-NUT(PPW) 

  NUT-PATHC(PPW) 

  JBSN-JB345(PPW) 
  NUT-PATHC(PPW) 
  PATHC-NUT(PPW) 

  NUT-PATHC(PPW) 

  NUT-PATHC(PPW)   
  1600.0 
  1060.0 
  1600.0 

  1172.0 

  1600.0 
  1172.0 
  1600.0 

  1060.0 

  1172.0   
  1600.0 
  1060.0 
  1600.0 

  1172.0 

  1600.0 
  1172.0 
  1600.0 

  1060.0 

  1172.0   
  1433.0 
  717.0 
  1560.0 

  829.0 

  1433.0 
  829.0 
  1560.0 

  717.0 

  829.0   
  2024-09-18 00:30 
  2024-09-18 00:30 
  2024-09-18 00:30 

  2024-11-01 00:00 

  2025-01-06 17:30 
  2025-01-06 17:30 
  2025-01-06 17:30 

  2025-04-01 00:00 

  2025-11-01 00:00   
  2025-01-06 17:30 
  2024-11-01 00:00 
  2025-01-06 17:30 

  2025-01-06 17:30 

  2025-12-31 17:30 
  2025-04-01 00:00 
  2025-12-31 17:30 

  2025-11-01 00:00 

  2025-12-31 17:30   
  ACTIVE     TRANSMISSION     FORCED      ONPATH     PPW     continuous:Computer/controller for Series caps needs to be repaired/replaced. Tech support needed from Hitachi.:JBSN-JB345 = 2150. PacifiCorp = 1433. IPCo = 717 NUT-PATHC = 730 Summer/730 Winter. PATHC-NUT = 1480 Summer/1560 Winter. JBSN-JB345 = 2150. PacifiCorp = 1433. IPCo = 717 NUT-PATHC = 950 Summer/951 Winter. PATHC-NUT = 1480 Summer/1580 Winter.:     2024-11-30 22:07     153619     2024-12-30 12:01  
  PPW 24-16485     17353     PPW     Populus: 345 kV Series Capacitor #1          JBSN-JB345(PPW) 

  JBSN-JB345(PPW) 

  JBSN-JB345(PPW)   
  1600.0 

  1600.0 

  1600.0   
  1600.0 

  1600.0 

  1600.0   
  1600.0 

  1367.0 

  1433.0   
  2024-10-23 07:30 

  2024-10-23 07:45 

  2025-03-31 11:15   
  2024-10-23 07:45 

  2025-03-31 11:15 

  2025-05-31 17:00   
  ACTIVE     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Required scheduled maintenance.:JBSN-JB345 = 2150. PacifiCorp = 1433. IPCo = 717.:     2024-10-01 13:14     154353     2025-03-31 11:21  
  PPW 24-16609     17387     PPW     Oquirrh-Terminal #1 345 kV line               0.0      0.0      0.0      2024-10-25 07:52      2025-06-25 14:00      ACTIVE     TRANSMISSION     URGENT      ONPATH     PPW     continuous:Relocate the Oquirrh-Terminal #1 345 kV line:No impact under normal conditions.:     2024-10-10 12:23     154477     2025-03-26 11:43  
  PPW 24-15258     17624     PPW     Clover: Sta Serv 2 Fuse          OTHERGEN-PACE(PPW)      9999.0      9999.0      9999.0      2024-11-05 15:21      2025-05-28 14:00      CANCELLED     TRANSMISSION     URGENT      ONPATH     PPW     continuous:XFMR #1 Tertiary station service fuse cutout to new SS XFMR #30 terminal clearance:No restriction:     2025-01-24 14:44     153126     2025-04-18 14:12  
  PPW 25-00075     17529     PPW     Crag View-PG&E Cascade section of the PG&E Cascade-Weed Junction 115 kV line          CRAG-CRAGVIEW(PPW) 
  CRAGVIEW-CRAG(PPW) 

  CRAG-CRAGVIEW(PPW) 
  CRAGVIEW-CRAG(PPW) 

  CRAGVIEW-CRAG(PPW)   
  45.0 
  80.0 

  45.0 
  80.0 

  80.0   
  45.0 
  80.0 

  45.0 
  80.0 

  80.0   
  45.0 
  80.0 

  45.0 
  80.0 

  80.0   
  2025-01-22 17:30 
  2025-01-22 17:30 

  2025-01-22 19:30 
  2025-01-22 19:30 

  2025-01-23 00:23   
  2025-01-22 19:30 
  2025-01-22 19:30 

  2025-01-23 00:23 
  2025-01-23 00:23 

  2025-04-30 17:00   
  COMPLETED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Remove shoefly, demolition existing equipment, build new equipment. Test program.:CRAG-CRAGVIEW & CRAGVIEW-CRAG = 0. CRAGVIEW-CRAG = 0. CRAG-CRAGVIEW = Crag View Area Load radial from Cascade (10 mw Summer/13 mw Winter). Network Load Service Arrangements may be required.:     2024-11-27 09:22     157837     2025-04-30 16:58  
  PPW 25-00045     17422     PPW     DG&T Bonanza-Gen: DG&T Bonanza-Gen Unit #1          THERMALGEN-PACE(PPW)      9999.0      9999.0      0.0      2025-03-31 23:01      2025-05-29 22:59      Active     GENERATION     PLANNED      ONPATH     PPW     continuous:Unit outage.:Bonanza Unit #1 unavailable.:     2024-10-21 11:28     155619     2024-10-21 11:28  
  PPW 25-05688     17794     PPW     DG&T Bonanza: Unit #1 Main Bank          THERMALGEN-PACE(PPW) 

  THERMALGEN-PACE(PPW)   
  9999.0 

  9999.0   
  9999.0 

  9999.0   
  9999.0 

  0.0   
  2025-03-31 23:01 

  2025-04-01 00:26   
  2025-04-01 00:26 

  2025-05-29 22:59   
  ACTIVE     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Unit outage.:DG&T Bonanza Unit #1 unavailable.:     2025-03-27 08:53     164786     2025-04-01 00:29  
  PPW 25-05264     17778     PPW     Aeolus: 500/230 kV XFMR #1               0.0      0.0      0.0      2025-04-01 07:00      2025-06-03 14:00      Active     DISTRIBUTION     PLANNED      ONPATH     PPW     continuous:Remove SS on Aeolus XFMR #1:     2025-03-21 13:31     164361     2025-03-21 13:31  
  PPW 25-01795     17622     PPW     Klamath Co-Gen: GSU 201          THERMALGEN-PACW(PPW) 

  THERMALGEN-PACW(PPW)   
  9999.0 

  9999.0   
  9999.0 

  9999.0   
  9999.0 

  0.0   
  2025-04-01 10:00 

  2025-04-01 10:10   
  2025-04-01 10:10 

  2025-06-02 14:00   
  ACTIVE     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Crane work at inlets:     2025-01-24 13:46     160871     2025-04-01 10:10  
  PPW 25-01798     17623     PPW     Klamath Co-Gen: GSU 301          THERMALGEN-PACW(PPW) 

  THERMALGEN-PACW(PPW)   
  9999.0 

  9999.0   
  9999.0 

  9999.0   
  9999.0 

  0.0   
  2025-04-01 10:00 

  2025-04-01 10:42   
  2025-04-01 10:42 

  2025-06-02 14:00   
  ACTIVE     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:GSU 301 bladder replacement and buckholtz replacement.:Klamath Co-Gen Unit 301 unavailable.:     2025-01-24 14:02     160874     2025-04-01 10:46  
  PPW 25-06064     17804     PPW     Aeolus: 500/230 kV XFMR #1               0.0      0.0      0.0      2025-04-04 12:03      2025-06-03 15:00      ACTIVE     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:**Commissioning REQ**Relocate the spare single phase transformer into the position of the failed single phase transformer. Return Switching needs to be written on 25-06064SW-2:     2025-04-02 13:19     165162     2025-04-04 12:04  
  PPW 25-06166     17809     PPW     Jim Bridger: 345/20 kV Unit #4 Main Bank (T3654)          JBSN-JB345(PPW)      1600.0      1600.0      1600.0      2025-04-04 16:25      2025-05-18 23:59      ACTIVE     TRANSMISSION     URGENT      ONPATH     PPW     continuous:Unit Overhaul:JBSN-JB345 = 2400. PacifiCorp = 1600. IPCo = 800.:     2025-04-04 06:43     165264     2025-04-04 16:30  
  PPW 25-06241     17814     PPW     Dynamo: ABS 113A,Dynamo: STB (Unit 10)          THERMALGEN-PACE(PPW)      9999.0      9999.0      0.0      2025-04-06 07:43      2025-06-16 23:00      ACTIVE     TRANSMISSION     URGENT      ONPATH     PPW     continuous:Open switch 113A per plant request for scheduled outage:Dynamo Unit 10 unavailable.:     2025-04-07 08:22     165339     2025-04-07 08:22  
  PPW 25-06376     17819     PPW     Dynamo: XFMR 1          THERMALGEN-PACE(PPW)      9999.0      9999.0      0.0      2025-04-13 12:00      2025-05-10 12:00      Active     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Unit outage.:Lakeside #1 Unit #11 unavailable.:     2025-04-08 14:26     165474     2025-04-08 14:26  
  PPW 25-02828     17662     PPW     Scheduling Limitation: Path 8 Schedule Limitation (MT-NW)          COLSTRIP-TOWNSEND(PPW)      157.0      157.0      157.0      2025-04-14 07:00      2025-05-22 16:00      CANCELLED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Remove Cap Bank 1.:COLSTRIP-TOWNSEND = 123:     2025-02-07 17:57     161907     2025-04-04 14:09  
  PPW 25-05687     17791     PPW     Grace: 138/6.6 kV XFMR #6               0.0      0.0      0.0      2025-04-22 08:33      2025-05-01 14:00      ACTIVE     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Doble Testing XFMR 5 :     2025-03-27 07:55     164785     2025-04-30 13:09  
  PPW 25-05686     17792     PPW     Grace: 138/6.6 kV XFMR #5               0.0      0.0      0.0      2025-04-22 08:33      2025-05-01 17:00      ACTIVE     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Doble Testing XFMR 5 :     2025-03-27 07:55     164784     2025-04-28 07:31  
  PPW 25-04333     17732     PPW     Grace: CB 125,Grace: 138/6.6 kV XFMR #5          HYDROGEN-PACE(PPW)      9999.0      9999.0      0.0      2025-04-28 07:00      2025-05-01 15:00      Active     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:CB L125 scheduled maintenance (BMMO):Grace Unit #4 unavailable:     2025-03-05 10:38     163419     2025-03-05 10:41  
  PPW 25-07435     17874     PPW     Aeolus: Capacitor #2 220 MVAR               0.0      0.0      0.0      2025-04-28 07:00      2025-05-12 14:00      CANCELLED     TRANSMISSION     URGENT      ONPATH     PPW     continuous:Repair Aeolus Cap #2:     2025-04-24 14:38     166541     2025-04-25 08:10  
  PPW 25-02804     17680     PPW     Ager-Yreka section of COPCO No. 2-Yreka 115 kV line          CRAGVIEW-CRAG(PPW) 

  CRAGVIEW-CRAG(PPW) 

  CRAGVIEW-CRAG(PPW) 

  CRAGVIEW-CRAG(PPW) 

  CRAGVIEW-CRAG(PPW) 

  CRAGVIEW-CRAG(PPW)   
  80.0 

  80.0 

  80.0 

  80.0 

  80.0 

  80.0   
  80.0 

  80.0 

  80.0 

  80.0 

  80.0 

  80.0   
  80.0 

  80.0 

  80.0 

  80.0 

  60.0 

  60.0   
  2025-03-24 06:00 

  2025-04-14 06:00 

  2025-04-28 06:00 

  2025-04-28 06:30 

  2025-04-28 07:29 

  2025-04-30 17:00   
  2025-03-25 17:00 

  2025-04-16 17:00 

  2025-04-28 06:30 

  2025-04-28 07:29 

  2025-04-30 17:00 

  2025-04-30 18:00   
  Completed     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:replace hot splices identified with IR flight:CRAGVIEW-CRAG = 60 summer/ 80 winter.:     2025-02-12 15:53     161883     2025-04-30 17:05  
  PPW 25-00940     17600     PPW     IPCO Borah-Populus #2 345 kV line,IPCO Borah: C343 Series Cap (Populus #2)          EIMPACE-EIMIPCO(PPW) 
  JBSN-JB345(PPW) 
  NUT-PATHC(PPW) 
  PATHC-NUT(PPW) 

  EIMPACE-EIMIPCO(PPW) 
  NUT-PATHC(PPW) 
  PATHC-NUT(PPW) 

  EIMPACE-EIMIPCO(PPW) 
  NUT-PATHC(PPW) 
  PATHC-NUT(PPW)   
  2350.0 
  1600.0 
  1060.0 
  1600.0 

  2350.0 
  1060.0 
  1600.0 

  2350.0 
  1060.0 
  1600.0   
  2350.0 
  1600.0 
  1060.0 
  1600.0 

  2350.0 
  1060.0 
  1600.0 

  2350.0 
  1060.0 
  1600.0   
  2125.0 
  1600.0 
  250.0 
  1375.0 

  2350.0 
  1060.0 
  1600.0 

  2350.0 
  1060.0 
  1600.0   
  2025-04-28 07:59 
  2025-04-28 07:59 
  2025-04-28 07:59 
  2025-04-28 07:59 

  2025-04-29 09:12 
  2025-04-29 09:12 
  2025-04-29 09:12 

  2025-04-29 10:00 
  2025-04-29 10:00 
  2025-04-29 10:00   
  2025-04-29 09:12 
  2025-04-29 09:12 
  2025-04-29 09:12 
  2025-04-29 09:12 

  2025-04-29 10:00 
  2025-04-29 10:00 
  2025-04-29 10:00 

  2025-05-02 14:00 
  2025-05-02 14:00 
  2025-05-02 14:00   
  COMPLETED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Maintenance on series capacitor and bypass switch.:NUT-PATHC = 250 Summer PATHC-NUT = 1375. Potential Real Time Generation Restriction. NUT-PATHC = 800 Summer/900 Winter.:     2025-01-10 11:23     160015     2025-04-29 09:27  
  PPW 25-06293     17820     PPW     Carbon-Spanish Fork #2 138 kV line          OTHERGEN-PACE(PPW) 
  PACE-VNL(PPW) 
  VNL-PACE(PPW) 

  OTHERGEN-PACE(PPW) 
  PACE-VNL(PPW) 
  VNL-PACE(PPW)   
  9999.0 
  140.0 
  138.0 

  9999.0 
  140.0 
  138.0   
  9999.0 
  140.0 
  138.0 

  9999.0 
  140.0 
  138.0   
  9999.0 
  140.0 
  138.0 

  0.0 
  75.0 
  75.0   
  2025-04-28 08:00 
  2025-04-28 08:00 
  2025-04-28 08:00 

  2025-04-28 08:19 
  2025-04-28 08:19 
  2025-04-28 08:19   
  2025-04-28 08:19 
  2025-04-28 08:19 
  2025-04-28 08:19 

  2025-05-02 14:00 
  2025-05-02 14:00 
  2025-05-02 14:00   
  ACTIVE     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:B-condition str and x-arm replacements:PACE-VNL & VNL-PACE = 75 Summer, 112 Winter. Graphite Solar limited to 10 MW. If both Carbon - Spanish Fork 138 kV lines are out-of-service, PACE-VNL = 0; VNL-PACE = Carbon area load:     2025-04-08 14:56     165391     2025-04-28 08:21  
  PPW 25-00809     17596     PPW     BPA Ponderosa, Ponderosa (West): 230/115 kV Bank #1,BPA Ponderosa: CB A384,BPA Ponderosa: CB A395          PONDEROSA115-PONDEROSAPAC(PPW) 

  PONDEROSA115-PONDEROSAPAC(PPW)   
  182.0 

  182.0   
  182.0 

  182.0   
  182.0 

  182.0   
  2025-04-28 08:00 

  2025-04-28 08:39   
  2025-04-28 08:39 

  2025-05-01 15:00   
  ACTIVE     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:PCB ground switch, Diagnostic service, routine services, and inspection services.:PONDEROSA115-PONDEROSAPAC =182 Summer/270 Winter.:     2025-01-08 10:17     159884     2025-04-28 08:41  
  PPW 25-02008     17659     PPW     Populus: 345 kV Series Capacitor #1,Populus: 345 kV Series Capacitor #1 (C1),Populus: 345 kV Series          JBSN-JB345(PPW)      1600.0      1600.0      1600.0      2025-04-28 09:00      2025-04-28 16:00      CANCELLED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:GE is coming to work on the Cap Bank. Fix all the problems there are with the Cap bank and return it to full operational working.:JBSN-JB345 = 2150. PacifiCorp = 1433. IPCo = 717.:     2025-02-07 15:12     161085     2025-04-08 10:58  
  PPW 25-05752     17795     PPW     Concho: SWITCH 89-H          WINDGEN-PACE(PPW) 

  WINDGEN-PACE(PPW) 

  WINDGEN-PACE(PPW)   
  9999.0 

  9999.0 

  9999.0   
  9999.0 

  9999.0 

  9999.0   
  9999.0 

  0.0 

  9999.0   
  2025-04-28 08:00 

  2025-04-28 11:10 

  2025-04-30 09:32   
  2025-04-28 11:10 

  2025-04-30 09:32 

  2025-05-02 15:00   
  COMPLETED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Isolate T-lines for work on Concho SW 89H.:     2025-03-27 14:46     164850     2025-04-30 09:33  
  PPW 25-06210     17816     PPW     Pilot Butte: T-3949 Bank #4          OTHERGEN-PACW(PPW) 

  OTHERGEN-PACW(PPW)   
  9999.0 

  9999.0   
  9999.0 

  9999.0   
  9999.0 

  0.0   
  2025-04-28 21:00 

  2025-04-28 21:16   
  2025-04-28 21:16 

  2025-05-09 22:55   
  ACTIVE     DISTRIBUTION     PLANNED      ONPATH     PPW     continuous:T-3949 LTC Maintenance:Bear Creek solar unavailable. Neff Solar unavailable. Collier Solar unavailable.:     2025-04-08 12:06     165308     2025-04-28 21:16  
  PPW 23-13230     17831     PPW     Pilot Butte: 69 kV West Bus,Pilot Butte-CEC Tap 69 kV line,China Hat-Pilot Butte 69 kV line               0.0      0.0      0.0      2025-04-28 23:59      2025-04-29 08:13      COMPLETED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Take outage on the 69kV West Bus to remove SO Loop Line #2 conductor and 69kV CEC Line conductor from Substation dead-end to first pole out side the substation, including Jumpers to bus. :Collier Solar , Neff Solar, and Bear Creek Solar off-line for duration of the outage:     2025-04-09 21:52     126599     2025-04-29 08:16  
  PPW 25-06368     17835     PPW     Big Grassy-Jefferson 161 kV line          BGSY-GSHN(PPW) 
  GSHN-BGSY(PPW) 
  PACE-NTLOAD(PPW) 

  BGSY-GSHN(PPW) 
  GSHN-BGSY(PPW) 
  PACE-NTLOAD(PPW) 

  BGSY-GSHN(PPW) 
  GSHN-BGSY(PPW) 
  PACE-NTLOAD(PPW)   
  35.0 
  143.0 
  9999.0 

  35.0 
  143.0 
  9999.0 

  35.0 
  143.0 
  9999.0   
  35.0 
  143.0 
  9999.0 

  35.0 
  143.0 
  9999.0 

  35.0 
  143.0 
  9999.0   
  35.0 
  143.0 
  9999.0 

  0.0 
  0.0 
  0.0 

  35.0 
  143.0 
  9999.0   
  2025-04-29 08:00 
  2025-04-29 08:00 
  2025-04-29 08:00 

  2025-04-29 08:37 
  2025-04-29 08:37 
  2025-04-29 08:37 

  2025-05-04 16:00 
  2025-05-04 16:00 
  2025-05-04 16:00   
  2025-04-29 08:37 
  2025-04-29 08:37 
  2025-04-29 08:37 

  2025-05-04 16:00 
  2025-05-04 16:00 
  2025-05-04 16:00 

  2025-05-05 16:00 
  2025-05-05 16:00 
  2025-05-05 16:00   
  ACTIVE     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Replacing structures between Jefferson and Big Grassy subs:BGSY-GSHN & GSHN-BGSY = 0 Big Grassy 69 kV Load will be served by NWE from Millcreek via Dillon/Dell. Network Load Service Arrangements may be required.:     2025-04-10 13:00     165466     2025-04-29 08:42  
  PPW 25-07627     17877     PPW     IPCO Borah: C343 Series Cap (Populus #2)          NUT-PATHC(PPW) 

  JBSN-JB345(PPW) 
  NUT-PATHC(PPW) 

  NUT-PATHC(PPW) 

  NUT-PATHC(PPW)   
  1060.0 

  1600.0 
  1060.0 

  1060.0 

  1060.0   
  1060.0 

  1600.0 
  1060.0 

  1060.0 

  1060.0   
  1060.0 

  1600.0 
  800.0 

  1060.0 

  1060.0   
  2025-04-29 09:00 

  2025-04-29 09:13 
  2025-04-29 09:13 

  2025-04-29 12:54 

  2025-05-02 14:00   
  2025-04-29 09:13 

  2025-04-29 12:54 
  2025-04-29 12:54 

  2025-05-02 14:00 

  2025-05-02 16:00   
  COMPLETED     TRANSMISSION     URGENT      ONPATH     PPW     continuous:Maintenance on series capacitor bank.:NUT-PATHC = 800 Summer/900 Winter.:     2025-04-28 13:59     166733     2025-04-29 12:57  
  PPW 25-05786     17796     PPW     Freezeout-Standpipe 230 kV line          AEOLUS-STANDPIPE(PPW) 
  AEOLUSGEN-AEOLUS(PPW) 
  OUTAGE-WYOCENTRAL(PPW) 
  STANDPIPE-AEOLUS(PPW) 
  TOT4B-WYONORTH(PPW) 
  WAPAEAST-WAPANORTH(PPW) 
  WYOEAST-AEOW(PPW)   
  860.0 
  2000.0 
  1.0 
  860.0 
  631.0 
  249.0 
  0.0   
  860.0 
  2000.0 
  1.0 
  860.0 
  631.0 
  249.0 
  0.0   
  860.0 
  2000.0 
  1.0 
  860.0 
  631.0 
  249.0 
  0.0   
  2025-04-29 09:38 
  2025-04-29 09:38 
  2025-04-29 09:38 
  2025-04-29 09:38 
  2025-04-29 09:38 
  2025-04-29 09:38 
  2025-04-29 09:38   
  2025-04-29 13:38 
  2025-04-29 13:38 
  2025-04-29 13:38 
  2025-04-29 13:38 
  2025-04-29 13:38 
  2025-04-29 13:38 
  2025-04-29 13:38   
  CANCELLED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:test:AW/4B Curve 105. WAPAEAST-WAPANORTH = 228. WYOEAST-AEOW (Aeolus West) = 1539. TOT4B-WYONORTH = 604. TOT 4B = 832. AEOLUS Export = 570. Potential Real Time Impact to Wyoming Generation:     2025-03-28 09:45     164884     2025-03-28 09:47  
  PPW 25-07698     17883     PPW     BarX-Echo Springs section of the Point of Rocks-Latham 230 kV line          AEOLUSGEN-AEOLUS(PPW) 
  OUTAGE-WYOCENTRAL(PPW) 
  STANDPIPE-WYOCENTRAL(PPW) 
  TOT4B-WYONORTH(PPW) 
  WAPAEAST-WAPANORTH(PPW) 
  WYOCENTRAL-STANDPIPE(PPW) 
  WYOEAST-AEOW(PPW) 

  AEOLUSGEN-AEOLUS(PPW) 
  OUTAGE-WYOCENTRAL(PPW) 
  TOT4B-WYONORTH(PPW) 
  WAPAEAST-WAPANORTH(PPW) 
  WYOEAST-AEOW(PPW)   
  2000.0 
  1.0 
  331.0 
  631.0 
  249.0 
  331.0 
  0.0 

  2000.0 
  1.0 
  631.0 
  249.0 
  0.0   
  2000.0 
  1.0 
  331.0 
  631.0 
  249.0 
  331.0 
  0.0 

  2000.0 
  1.0 
  631.0 
  249.0 
  0.0   
  2000.0 
  1.0 
  331.0 
  631.0 
  249.0 
  331.0 
  0.0 

  2000.0 
  1.0 
  631.0 
  249.0 
  0.0   
  2025-04-30 06:26 
  2025-04-30 06:26 
  2025-04-30 06:26 
  2025-04-30 06:26 
  2025-04-30 06:26 
  2025-04-30 06:26 
  2025-04-30 06:26 

  2025-04-30 08:00 
  2025-04-30 08:00 
  2025-04-30 08:00 
  2025-04-30 08:00 
  2025-04-30 08:00   
  2025-04-30 08:00 
  2025-04-30 08:00 
  2025-04-30 08:00 
  2025-04-30 08:00 
  2025-04-30 08:00 
  2025-04-30 08:00 
  2025-04-30 08:00 

  2025-05-02 17:30 
  2025-05-02 17:30 
  2025-05-02 17:30 
  2025-05-02 17:30 
  2025-05-02 17:30   
  COMPLETED     TRANSMISSION     URGENT      ONPATH     PPW     continuous:Repair loose pins in bell.:AW/4B Curve 107. WAPAEAST-WAPANORTH = 233. WYOEAST-AEOW (Aeolus West) = 1541. TOT4B-WYONORTH = 592. TOT 4B = 825. AEOLUS Export = 570. Potential Real Time Impact to Wyoming Generation:     2025-04-29 15:49     166804     2025-04-30 15:25  
  PPW 25-07737     17885     PPW     West Valley: 138 kV North Bus               0.0      0.0      0.0      2025-04-30 12:56      2025-04-30 15:59      COMPLETED     TRANSMISSION     FORCED      ONPATH     PPW     continuous:Investigate CB 152 relay failure:     2025-04-30 13:36     166843     2025-04-30 16:00  
  PPW 25-07004     17851     PPW     Path 25 Schedule Limitation (Cascade 115 kV Tie)          CRAG-CRAGVIEW(PPW) 
  CRAGVIEW-CRAG(PPW) 

  CRAG-CRAGVIEW(PPW) 
  CRAGVIEW-CRAG(PPW) 

  CRAG-CRAGVIEW(PPW) 
  CRAGVIEW-CRAG(PPW)   
  45.0 
  80.0 

  45.0 
  80.0 

  45.0 
  80.0   
  45.0 
  80.0 

  45.0 
  80.0 

  45.0 
  80.0   
  45.0 
  80.0 

  0.0 
  28.0 

  45.0 
  80.0   
  2025-04-30 11:48 
  2025-04-30 11:48 

  2025-04-30 23:00 
  2025-04-30 23:00 

  2025-05-01 05:00 
  2025-05-01 05:00   
  2025-04-30 23:00 
  2025-04-30 23:00 

  2025-05-01 05:00 
  2025-05-01 05:00 

  2025-05-01 15:48 
  2025-05-01 15:48   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Repair jumper:CRAG-CRAGVIEW = 0; CRAGVIEW-CRAG = 28:     2025-04-17 11:57     166106     2025-04-30 16:55  
  PPW 25-06196     17812     PPW     PG&E Cascade-Cottonwood 115 kV line          CRAG-CRAGVIEW(PPW) 
  CRAGVIEW-CRAG(PPW)   
  45.0 
  80.0   
  45.0 
  80.0   
  0.0 
  28.0   
  2025-04-30 23:00 
  2025-04-30 23:00   
  2025-05-01 05:00 
  2025-05-01 05:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Repair jumper on structure.:CRAG-CRAGVIEW = 0 (North). CRAGVIEW-CRAGV = 28 (South):     2025-04-04 12:18     165294     2025-04-04 12:18  
  PPW 25-01590     17618     PPW     Bonanza-Mona 345 kV line          THERMALGEN-PACE(PPW) 

  THERMALGEN-PACE(PPW)   
  9999.0 

  9999.0   
  9999.0 

  9999.0   
  0.0 

  9999.0   
  2025-05-01 06:00 

  2025-05-23 15:30   
  2025-05-23 15:30 

  2025-05-29 15:30   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Replacing insulators.:Bonanza West (Path 33) = 140. BOZ-MDGT & MDGT-BOZ = 0 Bonanza generation restricted to 300 MW for duration of this outage for reliability concerns:     2025-01-22 14:20     160666     2025-01-27 15:42  
  PPW 25-04512     17800     PPW     Crag View-Weed Junction section of the PG&E Cascade-Weed Junction 115 kV line          CRAG-CRAGVIEW(PPW) 
  CRAGVIEW-CRAG(PPW) 
  CRAGVIEW-PACW(PPW) 
  PACW-CRAGVIEW(PPW)   
  45.0 
  80.0 
  108.0 
  115.0   
  45.0 
  80.0 
  108.0 
  115.0   
  10.0 
  0.0 
  0.0 
  0.0   
  2025-05-01 07:00 
  2025-05-01 07:00 
  2025-05-01 07:00 
  2025-05-01 07:00   
  2025-05-01 16:00 
  2025-05-01 16:00 
  2025-05-01 16:00 
  2025-05-01 16:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Change bad order bells @ 9/41:CRAGVIEW-PACW & PACW-CRAGVIEW = 0; CRAGVIEW-CRAG = 0; CRAG-CRAGVIEW = Crag View Load (Approx 10 mw); Crag View will be radial from Weed. Network Load Service Arrangements may be required.:     2025-03-31 12:48     163600     2025-04-25 11:26  
  PPW 25-07072     17864     PPW     Buckhorn Road-Dixonville section of the Dixonville-Soda Springs 115 kV line               0.0      0.0      0.0      2025-05-01 08:00      2025-05-01 16:30      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Add second ratio to Line #46 PT.:Total Umpqua Hydro Project Generation is limited to 112 Summer /154 Winter MVA.:     2025-04-21 08:53     166174     2025-04-21 08:53  
  PPW 25-06425     17823     PPW     Path 25 Schedule Limitation (Cascade 115 kV Tie)          CRAG-CRAGVIEW(PPW) 
  CRAGVIEW-CRAG(PPW)   
  45.0 
  80.0   
  45.0 
  80.0   
  10.0 
  80.0   
  2025-05-02 06:00 
  2025-05-02 06:00   
  2025-05-02 17:00 
  2025-05-02 17:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:LOCATE AND REPAIR OIL LEAK ON #3-230/60KV TRANSFORMER:CRAG-CRAGVIEW = 10; CRAGVIEW-CRAG = 80:     2025-04-09 09:33     165523     2025-04-09 09:33  
  PPW 25-02805     17669     PPW     COPCO No. 2-Ager section of COPCO No. 2-Yreka 115 kV line          CRAGVIEW-CRAG(PPW) 

  CRAGVIEW-CRAG(PPW) 

  CRAGVIEW-CRAG(PPW) 

  CRAGVIEW-CRAG(PPW) 

  CRAGVIEW-CRAG(PPW)   
  80.0 

  80.0 

  80.0 

  80.0 

  80.0   
  80.0 

  80.0 

  80.0 

  80.0 

  80.0   
  80.0 

  80.0 

  80.0 

  80.0 

  60.0   
  2025-03-26 06:00 

  2025-04-01 06:00 

  2025-04-03 06:00 

  2025-04-18 06:00 

  2025-05-02 06:00   
  2025-03-26 17:00 

  2025-04-02 17:00 

  2025-04-04 17:00 

  2025-04-18 17:00 

  2025-05-02 17:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Replace hot splices identified with IR flight:CRAGVIEW-CRAG = 60 summer/ 80 winter.:     2025-02-10 09:50     161884     2025-04-10 14:09  
  PPW 25-07074     17866     PPW     Dixonville: 115 kV Main Bus          HYDROGEN-PACW(PPW)      9999.0      9999.0      9999.0      2025-05-02 08:00      2025-05-02 16:30      CANCELLED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Rewire trip circuit for CB2U3 from the bus differential and breaker fail lockouts.:     2025-04-21 13:29     166176     2025-04-22 08:21  
  PPW 25-06582     17837     PPW     Swift #2: Unit #22 Main Transformer - T2103          HYDROGEN-PACW(PPW)      9999.0      9999.0      0.0      2025-05-03 07:00      2025-05-07 16:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Swift 22 annual maintenance. :Swift hydro unit 22 unavailable.:     2025-04-11 08:42     165683     2025-04-11 08:42  
  PPW 25-04613     17740     PPW     Swift #2: Unit #22 Main Transformer - T2103          HYDROGEN-PACW(PPW) 

  HYDROGEN-PACW(PPW)   
  9999.0 

  9999.0   
  9999.0 

  9999.0   
  0.0 

  9999.0   
  2025-05-03 07:00 

  2025-05-07 16:00   
  2025-05-07 16:00 

  2025-05-09 16:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Swift 22 annual maintenance. Headgate lowered and penstock/draft tube DEWATERED. :Swift #2 unit 22 unavailable.:     2025-03-07 10:33     163701     2025-03-14 13:59  
  PPW 25-00559     17611     PPW     IPC Midpoint-Hemingway 500 kV line,IPCo Midpoint: 500/345 kV Bank T-501          H500-M500(PPW) 
  M500-H500(PPW) 
  PACW-NTLOAD(PPW) 

  H500-M500(PPW) 
  M500-H500(PPW) 
  PACW-NTLOAD(PPW) 

  H500-M500(PPW) 
  M500-H500(PPW) 
  PACW-NTLOAD(PPW) 

  H500-M500(PPW) 
  M500-H500(PPW) 
  PACW-NTLOAD(PPW)   
  800.0 
  1090.0 
  9999.0 

  800.0 
  1090.0 
  9999.0 

  800.0 
  1090.0 
  9999.0 

  800.0 
  1090.0 
  9999.0   
  800.0 
  1090.0 
  9999.0 

  800.0 
  1090.0 
  9999.0 

  800.0 
  1090.0 
  9999.0 

  800.0 
  1090.0 
  9999.0   
  800.0 
  1090.0 
  9999.0 

  800.0 
  1090.0 
  9999.0 

  800.0 
  1090.0 
  9999.0 

  350.0 
  350.0 
  0.0   
  2025-02-03 06:00 
  2025-02-03 06:00 
  2025-02-03 06:00 

  2025-02-24 06:00 
  2025-02-24 06:00 
  2025-02-24 06:00 

  2025-05-01 06:00 
  2025-05-01 06:00 
  2025-05-01 06:00 

  2025-05-05 06:00 
  2025-05-05 06:00 
  2025-05-05 06:00   
  2025-02-24 06:00 
  2025-02-24 06:00 
  2025-02-24 06:00 

  2025-05-01 06:00 
  2025-05-01 06:00 
  2025-05-01 06:00 

  2025-05-05 06:00 
  2025-05-05 06:00 
  2025-05-05 06:00 

  2025-06-06 16:00 
  2025-06-06 16:00 
  2025-06-06 16:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:This outage is for relocating the existing Midpoint T501 345kV/500kV transformer to a new 345kV station bay.:M500-H500 & H500-M500= 350. BORA-M500 = 959. No impact to Bridger West. Jim Bridger Generation may be restricted real time (as determined by Northwest Path Flow). Network Load Service Arrangements may be required for Southern Oregon Load. Note: TTC Schedules on Path 75 East & West are 0. However, the SOL is 350 West / 325 East (Limited by Bowmont Xfmrs). However, there is a potential of up to 300 mw of actual unscheduled inadvertent flow between Hemingway & Summer Lake. JBSN-JB345 = 2200. PacifiCorp = 1467. IPCo = 733. Jim Bridger Generation may be restricted real time (as determined by Northwest Path Flow).:     2025-01-17 09:01     159624     2025-03-05 14:07  
  PPW 25-07611     17880     PPW     Red Blanket-Prospect #3 section of the Prospect #3-Prospect Central 69kV line          HYDROGEN-PACW(PPW)      9999.0      9999.0      0.0      2025-05-05 06:00      2025-05-07 16:30      SCHEDULED     TRANSMISSION     URGENT      ONPATH     PPW     continuous:Replace poles at 16/6 and 17/6:Prospect #3 unavailable.:     2025-04-29 09:15     166717     2025-04-29 09:15  
  PPW 25-05774     17799     PPW     Albina-Knott 115 kV Line          PACW-PACW.PGE(PPW) 
  PACW.PGE-PACW(PPW) 

  PACW-PACW.PGE(PPW) 
  PACW.PGE-PACW(PPW) 

  PACW-PACW.PGE(PPW) 
  PACW.PGE-PACW(PPW) 

  PACW-PACW.PGE(PPW) 
  PACW.PGE-PACW(PPW)   
  325.0 
  325.0 

  325.0 
  325.0 

  325.0 
  325.0 

  325.0 
  325.0   
  325.0 
  325.0 

  325.0 
  325.0 

  325.0 
  325.0 

  325.0 
  325.0   
  325.0 
  325.0 

  325.0 
  325.0 

  325.0 
  325.0 

  201.0 
  201.0   
  2025-04-22 07:00 
  2025-04-22 07:00 

  2025-04-26 07:00 
  2025-04-26 07:00 

  2025-04-28 07:00 
  2025-04-28 07:00 

  2025-05-05 07:00 
  2025-05-05 07:00   
  2025-04-24 17:00 
  2025-04-24 17:00 

  2025-04-26 17:00 
  2025-04-26 17:00 

  2025-05-02 17:00 
  2025-05-02 17:00 

  2025-05-09 17:00 
  2025-05-09 17:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:REPLACE POLE 276403 IN CLOSE PROXIMITY TO LINE:PACW-PACW.PGE & PGE.PACW-PACW = 201 Summer/299 Winter:     2025-03-31 12:15     164872     2025-04-24 14:33  
  PPW 25-07016     17858     PPW     Pendleton-Athena section of the Pendleton-Walla Walla 69 kV line          WINDGEN-PACW(PPW)      9999.0      9999.0      0.0      2025-05-05 08:00      2025-05-07 17:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     1234567 Daily:Replacing structure 1/002:Combine Hills Generation is restricted to 20 MW only during the line switching process (at the beginning and end of the line outage). Chopin Wind is restricted to 0 MW for the whole duration while tied to Central:     2025-04-18 12:25     166118     2025-04-28 12:18  
  PPW 25-02009     17660     PPW     Populus: 345 kV Series Capacitor #2,Populus: 345 kV Series Capacitor #2 (C1),Populus: 345 kV Series          JBSN-JB345(PPW)      1600.0      1600.0      1367.0      2025-05-05 09:00      2025-05-09 16:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:GE is coming to fix all the problems and when finished have cap fully functional.:JBSN-JB345 = 2150. PacifiCorp = 1433. IPCo = 717.:     2025-02-07 15:33     161086     2025-02-07 15:38  
  PPW 25-04357     17731     PPW     Antelope-Amps-Peterson (NWE) 230 kV line          ANTE-MLCK(PPW) 
  MLCK-ANTE(PPW) 

  ANTE-MLCK(PPW) 
  MLCK-ANTE(PPW) 

  ANTE-MLCK(PPW) 
  MLCK-ANTE(PPW)   
  66.0 
  90.0 

  66.0 
  90.0 

  66.0 
  90.0   
  66.0 
  90.0 

  66.0 
  90.0 

  66.0 
  90.0   
  66.0 
  90.0 

  66.0 
  90.0 

  0.0 
  0.0   
  2025-04-02 10:00 
  2025-04-02 10:00 

  2025-04-14 10:00 
  2025-04-14 10:00 

  2025-05-05 10:00 
  2025-05-05 10:00   
  2025-04-03 10:00 
  2025-04-03 10:00 

  2025-04-27 10:00 
  2025-04-27 10:00 

  2025-05-19 10:00 
  2025-05-19 10:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Land new cables on PT from new control house and move panel from old building to the new control house. :MLCK-ANTE & ANTE-MLCK = 0.:     2025-03-05 09:13     163443     2025-03-25 08:41  
  PPW 25-07389     17873     PPW     Chiloquin: CB 5L57               0.0      0.0      0.0      2025-05-05 10:00      2025-05-16 15:00      SCHEDULED     DISTRIBUTION     PLANNED      ONPATH     PPW     continuous:Replace 5L57 breaker relay with SEL-751 with high impedance fault detection. :Chiloquin Solar off-line for duration of the outage:     2025-04-23 19:35     166494     2025-04-23 19:35  
  PPW 25-05895     17878     PPW     Jefferson (ID): CB 161,Jefferson (ID): CB 163          BGSY-GSHN(PPW) 
  GSHN-BGSY(PPW) 

  BGSY-GSHN(PPW) 
  GSHN-BGSY(PPW) 

  BGSY-GSHN(PPW) 
  GSHN-BGSY(PPW)   
  35.0 
  143.0 

  35.0 
  143.0 

  35.0 
  143.0   
  35.0 
  143.0 

  35.0 
  143.0 

  35.0 
  143.0   
  35.0 
  143.0 

  35.0 
  143.0 

  0.0 
  0.0   
  2025-04-21 13:00 
  2025-04-21 13:00 

  2025-04-29 13:00 
  2025-04-29 13:00 

  2025-05-05 13:00 
  2025-05-05 13:00   
  2025-04-21 14:00 
  2025-04-21 14:00 

  2025-04-29 14:00 
  2025-04-29 14:00 

  2025-05-05 14:00 
  2025-05-05 14:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:BIOA's on each breaker:BGSY-GSHN & GSHN-BGSY = 0 Big Grassy 69 kV Load will be served by NWE from Millcreek via Dillon/Dell. Network Load Service Arrangements may be required.:     2025-04-29 08:36     164993     2025-04-29 15:09  
  PPW 25-06653     17847     PPW     Huntington: MO.134A,McFadden: SWITCH 133A,McFadden: SWITCH 153A          OTHERGEN-PACE(PPW)      9999.0      9999.0      0.0      2025-05-06 08:00      2025-05-06 15:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Reframing structure 37 on the Huntington - Mcfadden 138kv line section.:Castle Solar limited to 20MW maximum.:     2025-04-16 10:42     165754     2025-04-16 10:42  
  PPW 25-06595     17838     PPW     Path 25 Schedule Limitation (Cascade 115 kV Tie)          CRAG-CRAGVIEW(PPW) 
  CRAGVIEW-CRAG(PPW)   
  45.0 
  80.0   
  45.0 
  80.0   
  10.0 
  80.0   
  2025-05-07 07:00 
  2025-05-07 07:00   
  2025-05-07 18:00 
  2025-05-07 18:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Replace pole and repair woodpecker holes.:CRAG-CRAGVIEW = 10; CRAGVIEW-CRAG = 80:     2025-04-11 10:54     165696     2025-04-11 10:54  
  PPW 25-06921     17848     PPW     Black Rock-Osceola 230 kV line          GON.PAV-PAVANT(PPW) 
  PAVANT-GON.PAV(PPW)   
  130.0 
  139.0   
  130.0 
  139.0   
  0.0 
  0.0   
  2025-05-07 07:30 
  2025-05-07 07:30   
  2025-05-07 16:00 
  2025-05-07 16:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Changing wing arm structure 490 A Condition:PAVANT-GON.PAV = 0. GON.PAV-PAVANT = 0.:     2025-04-16 11:34     166023     2025-04-16 11:37  
  PPW 25-06599     17839     PPW     Path 25 Schedule Limitation (Cascade 115 kV Tie)          CRAG-CRAGVIEW(PPW) 
  CRAGVIEW-CRAG(PPW)   
  45.0 
  80.0   
  45.0 
  80.0   
  10.0 
  80.0   
  2025-05-08 07:00 
  2025-05-08 07:00   
  2025-05-09 18:00 
  2025-05-09 18:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Replace poles and repair hardware.:CRAG-CRAGVIEW = 10; CRAGVIEW-CRAG = 80:     2025-04-11 11:13     165700     2025-04-11 11:13  
  PPW 25-07480     17876     PPW     Culver-Cove section of the Redmond-Cove 69 kV line          PACW-NTLOAD(PPW)      9999.0      9999.0      0.0      2025-05-08 08:00      2025-05-08 15:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Correct FPI "A" condition involving loose/missing hardware on energized components of structure:Crooked River & Culver will be switched over to BPA Redmond via Pacific Power Redmond. Opal Springs Generation will be tie to BPA Redmond. Network Load Service Arrangements may be required.:     2025-04-26 08:04     166586     2025-04-28 09:06  
  PPW 25-06548     17843     PPW     Craner Flat: SCADA/RTU          THERMALGEN-PACE(PPW) 

  THERMALGEN-PACE(PPW)   
  9999.0 

  9999.0   
  9999.0 

  9999.0   
  9999.0 

  0.0   
  2025-05-01 09:00 

  2025-05-08 09:00   
  2025-05-02 17:00 

  2025-05-09 17:00   
  SCHEDULED     TELECOM     PLANNED      ONPATH     PPW     continuous:1) Movin three existing DS1 circuits from Coastcom channel bank to Loop channel bank 2) Re-route Black Mtn - UTB DS1 to Black Mtn - Horseshoe via the new MW path:US Mag generation unavailable.:     2025-04-15 10:36     165649     2025-04-30 11:34  
  PPW 25-06374     17818     PPW     Dynamo: XFMR 2          THERMALGEN-PACE(PPW)      9999.0      9999.0      0.0      2025-05-10 12:00      2025-05-16 16:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Unit outage:Lakeside #1 Unit 12 unavailable.:     2025-04-08 13:55     165472     2025-04-08 13:55  
  PPW 25-06051     17802     PPW     Talbot-AVA Dry Creek 230 kV line          DRYCREEK-TALBOT(PPW) 
  TALBOT-DRYCREEK(PPW)   
  240.0 
  240.0   
  240.0 
  240.0   
  0.0 
  0.0   
  2025-05-12 08:00 
  2025-05-12 08:00   
  2025-05-16 16:00 
  2025-05-16 16:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Replacing cross-arms and structures.:DRYCREEK-TALBOT & TALBOT-DRYCREEK = 0.:     2025-04-02 10:26     165149     2025-04-02 11:18  
  PPW 25-03363     17755     PPW     BPA Tumble Creek-Jones Canyon section of Santiam-Jones Canyon 230kV Line          WINDGEN-PACW(PPW)      9999.0      9999.0      9999.0      2025-05-12 08:00      2025-05-15 15:00      CANCELLED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Ungrounded clearance.:Leaning Juniper 1 unavailable. Leaning Juniper total maximum generation limited to 40MW.:     2025-03-14 15:00     162445     2025-03-20 10:21  
  PPW 25-00009     16952     PPW     Hemingway-Summer Lake 500 kV line          H500-SMLK(PPW) 
  PACW-NTLOAD(PPW) 
  SMLK-H500(PPW)   
  1500.0 
  9999.0 
  100.0   
  1500.0 
  9999.0 
  100.0   
  0.0 
  0.0 
  0.0   
  2025-05-12 08:00 
  2025-05-12 08:00 
  2025-05-12 08:00   
  2025-05-23 18:00 
  2025-05-23 18:00 
  2025-05-23 18:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Spacer replacements:H500-SMLK & SMLK-H500 = 0; BORA-M500 = 959; Network Load Service Arrangements may be required for Southern Oregon Load.:     2024-04-30 09:20     144657     2024-05-06 09:36  
  PPW 25-06275     17849     PPW     Slide Creek: 115/7 kV GSU XFMR          HYDROGEN-PACW(PPW)      9999.0      9999.0      0.0      2025-05-12 08:00      2025-05-14 15:30      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Slide Creek GSU Maintenance:Slide Creek Hydro unavailable.:     2025-04-16 11:46     165373     2025-04-16 11:53  
  PPW 25-06565     17845     PPW     Klamath Co-Gen: CB 11L12,Klamath Co-Gen: CB 11L22,Klamath Co-Gen: CB 11L25          THERMALGEN-PACW(PPW)      9999.0      9999.0      0.0      2025-05-13 08:00      2025-05-14 16:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     1234567 Daily:Test bus differentials and roll 86B2:Klamath Co-Gen Steam Turbine Unavailable.:     2025-04-15 13:17     165666     2025-04-15 13:17  
  PPW 25-06636     17840     PPW     Path 25 Schedule Limitation (Cascade 115 kV Tie)          CRAG-CRAGVIEW(PPW) 
  CRAGVIEW-CRAG(PPW)   
  45.0 
  80.0   
  45.0 
  80.0   
  10.0 
  80.0   
  2025-05-17 05:00 
  2025-05-17 05:00   
  2025-05-17 19:00 
  2025-05-17 19:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Replace structures.:CRAG-CRAGVIEW = 10; CRAGVIEW-CRAG = 80:     2025-04-11 13:52     165737     2025-04-11 13:52  
  PPW 25-07005     17852     PPW     Path 25 Schedule Limitation (Cascade 115 kV Tie)          CRAG-CRAGVIEW(PPW) 
  CRAGVIEW-CRAG(PPW)   
  45.0 
  80.0   
  45.0 
  80.0   
  0.0 
  28.0   
  2025-05-18 07:00 
  2025-05-18 07:00   
  2025-05-21 18:00 
  2025-05-21 18:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Replace poles and insulators:CRAG-CRAGVIEW = 0; CRAGVIEW-CRAG = 28:     2025-04-17 12:18     166107     2025-04-17 12:18  
  PPW 25-07501     17875     PPW     Mona-IPP #1 345 kV line          MDWP-MPAC(PPW) 
  MPAC-MDWP(PPW)   
  1400.0 
  1400.0   
  1400.0 
  1400.0   
  600.0 
  600.0   
  2025-05-19 05:00 
  2025-05-19 05:00   
  2025-05-26 18:00 
  2025-05-26 18:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Line patrol, repair conductor:MDWP-MPAC & MPAC-MDWP restricted to 600 mw.:     2025-04-25 10:41     166607     2025-04-25 10:41  
  PPW 25-07053     17853     PPW     Red Lake (TB Flats 1): 230/34.5 kV XFMR T1,Red Lake (TB Flats 1): 34.5kV Bus 1          WINDGEN-PACW(PPW)      9999.0      9999.0      0.0      2025-05-19 06:00      2025-05-19 18:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Install avian guarding.:Red Lake/TB Flats 1 circuits 11, 12, 13, and 14 (71 MW) unavailable.:     2025-04-18 11:25     166155     2025-04-18 11:25  
  PPW 25-02324     17638     PPW     Red Lake (TB Flats 1): 230/34.5 kV XFMR T1          WINDGEN-PACW(PPW)      9999.0      9999.0      9999.0      2025-05-19 06:00      2025-05-19 18:00      CANCELLED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Install avian guarding.:Red Lake/TB Flats 1 circuits 11, 12, 13, and 14 (71 MW) unavailable.:     2025-01-31 13:17     161403     2025-04-18 11:11  
  PPW 25-06357     17865     PPW     Windstar-Yellowcake section of the Windstar-Teckla 230 kV line          ANTELOPE-WYOEAST(PPW) 
  PACE-NTLOAD(PPW) 
  WYOEAST-ANTELOPE(PPW)   
  376.0 
  9999.0 
  376.0   
  376.0 
  9999.0 
  376.0   
  36.0 
  0.0 
  0.0   
  2025-05-19 07:00 
  2025-05-19 07:00 
  2025-05-19 07:00   
  2025-05-23 14:00 
  2025-05-23 14:00 
  2025-05-23 14:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Make corrections for punch list items on the Windstar-Yellowcake 230 kV line.:WYOE-ANTE = 0. ANTE-WYOE = Antelope Mine & Yellowcake loads. Antelope Mine & Yellowcake radial from WyoDak. Network Load Service Arrangements may be required.:     2025-04-21 12:22     165455     2025-04-21 12:24  
  PPW 25-07672     17881     PPW     Muddy Creek-Mountain Wind 138 kV line          WINDGEN-PACW(PPW)      9999.0      9999.0      0.0      2025-05-19 07:00      2025-05-23 16:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Replace poles.:Mountain Wind Collector offline.:     2025-04-29 10:11     166778     2025-04-29 10:11  
  PPW 25-07327     17882     PPW     Fish Creek - Grace 161 kV line          GSHN-PATHC(PPW) 
  NUT-PATHC(PPW) 
  PATHC-GSHN(PPW)   
  348.0 
  1060.0 
  148.0   
  348.0 
  1060.0 
  148.0   
  200.0 
  900.0 
  0.0   
  2025-05-19 08:00 
  2025-05-19 08:00 
  2025-05-19 08:00   
  2025-05-30 15:00 
  2025-05-30 15:00 
  2025-05-30 15:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:WO# 7351640 Replace 161kv STR 8, 39, 77, 79, 103:NUT-PATHC = 900 GSHN-PATHC = 200. PATHC-GSHN = 0:     2025-04-29 11:50     166432     2025-04-29 11:52  
  PPW 25-07656     17879     PPW     IPCO Kinport: Series Cap C341          JBSN-JB345(PPW) 
  NUT-PATHC(PPW)   
  1600.0 
  1060.0   
  1600.0 
  1060.0   
  1467.0 
  600.0   
  2025-05-19 08:00 
  2025-05-19 08:00   
  2025-05-23 14:00 
  2025-05-23 14:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Maintenance on capacitor bank.:NUT-PATHC = 600 Summer/900 Winter.:     2025-04-29 09:01     166762     2025-04-29 09:01  
  PPW 25-06823     17842     PPW     Seven Mile Hill: 230/34 kV Bank #1          WINDGEN-PACW(PPW)      9999.0      9999.0      0.0      2025-05-19 08:00      2025-05-21 11:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Isolate transformer and feeder breakers to install 34.5kV breaker.:Seven Mile Hill wind unavailable.:     2025-04-15 09:52     165925     2025-04-15 09:52  
  PPW 25-07059     17854     PPW     Red Lake (TB Flats 1): 230/34.5 kV XFMR T1,Red Lake (TB Flats 1): 230/34.5 kV XFMR T2,Red Lake (TB F          WINDGEN-PACW(PPW)      9999.0      9999.0      0.0      2025-05-20 06:00      2025-05-20 18:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Install avian guarding.:Red Lake/TB Flats 1 circuits 11, 12, 13, and 14 (71 MW) unavailable. TB Flats 1/Red Lakes circuits 21, 22, 23, 24, and 25 are unavailable (112 MW).:     2025-04-18 11:43     166161     2025-04-18 11:43  
  PPW 25-02325     17639     PPW     Red Lake (TB Flats 1): 230/34.5 kV XFMR T1,Red Lake (TB Flats 1): 230/34.5 kV XFMR T2          WINDGEN-PACW(PPW)      9999.0      9999.0      9999.0      2025-05-20 06:00      2025-05-20 18:00      CANCELLED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Install avian guarding.:Red Lake/TB Flats 1 circuits 11, 12, 13, and 14 (71 MW) unavailable. TB Flats 1/Red Lakes circuits 21, 22, 23, 24, and 25 are unavailable (112 MW).:     2025-01-31 13:27     161404     2025-04-18 11:30  
  PPW 25-02326     17640     PPW     Red Lake (TB Flats 1): 230/34.5 kV XFMR T2          WINDGEN-PACW(PPW)      9999.0      9999.0      9999.0      2025-05-21 06:00      2025-05-21 18:00      CANCELLED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Install avian guarding.:TB Flats 1/Red Lakes circuits 21, 22, 23, 24, and 25 are unavailable (112 MW).:     2025-01-31 13:30     161405     2025-04-18 11:45  
  PPW 25-07061     17855     PPW     Red Lake (TB Flats 1): 230/34.5 kV XFMR T2,Red Lake (TB Flats 1): 34.5kV Bus 2          WINDGEN-PACW(PPW)      9999.0      9999.0      0.0      2025-05-21 06:00      2025-05-21 18:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Install avian guarding.:TB Flats 1/Red Lakes circuits 21, 22, 23, 24, and 25 are unavailable (112 MW).:     2025-04-18 11:53     166163     2025-04-18 11:53  
  PPW 25-06053     17803     PPW     Walla Walla-AVA Saddle Mountain 230 kV line          MIDC-WALLAWALLA(PPW) 
  WALLAWALLA-MIDC(PPW)   
  240.0 
  240.0   
  240.0 
  240.0   
  0.0 
  0.0   
  2025-05-21 08:00 
  2025-05-21 08:00   
  2025-05-23 16:00 
  2025-05-23 16:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Replacing cross-arms.:MIDC-WALLAWALLA & WALLAWALLA-MIDC = 0. Affects Stateline Wind deliveries to Wanapum & Avista Dry Creek. Affects Avistas Transfer Rights from Wanapum to Dry Creek. Affects ability to deliver Network Load Service from the Walla Walla Area to the Yakima Area. Affects ability to deliver Network Load Service from Mid-Columbia to the Walla Walla Area.:     2025-04-02 11:11     165151     2025-04-02 11:18  
  PPW 25-02327     17641     PPW     Red Lake (TB Flats 1): 230/34.5 kV XFMR T2,Red Lake (TB Flats 1): 230/34.5 kV XFMR T3          WINDGEN-PACW(PPW)      9999.0      9999.0      9999.0      2025-05-22 06:00      2025-05-22 18:00      CANCELLED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Install avian guarding.:TB Flats 1/Red Lakes circuits 21, 22, 23, 24, and 25 are unavailable (112 MW). TB Flats 1/Red Lakes circuits 31, 32, 33, and 34 are unavailable (116 MW).:     2025-01-31 13:36     161406     2025-04-18 12:00  
  PPW 25-07065     17856     PPW     Red Lake (TB Flats 1): 230/34.5 kV XFMR T2,Red Lake (TB Flats 1): 230/34.5 kV XFMR T3,Red Lake (TB F          WINDGEN-PACW(PPW)      9999.0      9999.0      0.0      2025-05-22 06:00      2025-05-22 18:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Install avian guarding.:TB Flats 1/Red Lakes circuits 21, 22, 23, 24, and 25 are unavailable (112 MW). TB Flats 1/Red Lakes circuits 31, 32, 33, and 34 are unavailable (116 MW).:     2025-04-18 12:00     166167     2025-04-18 12:00  
  PPW 25-03393     17754     PPW     BPA Tumble Creek-Jones Canyon section of Santiam-Jones Canyon 230kV Line          WINDGEN-PACW(PPW) 

  WINDGEN-PACW(PPW)   
  9999.0 

  9999.0   
  9999.0 

  9999.0   
  9999.0 

  0.0   
  2025-05-19 08:00 

  2025-05-22 08:00   
  2025-05-22 08:00 

  2025-05-22 15:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Ungrounded clearance.:Leaning Juniper 1 unavailable. Leaning Juniper site restricted to 40MW total maximum generation.:     2025-03-14 14:51     162475     2025-03-20 10:21  
  PPW 25-07066     17857     PPW     Red Lake (TB Flats 1): 230/34.5 kV XFMR T3,Red Lake (TB Flats 1): 34.5kV Bus 3          WINDGEN-PACW(PPW)      9999.0      9999.0      0.0      2025-05-23 06:00      2025-05-23 18:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Install avian guarding.:TB Flats 1/Red Lakes circuits 31, 32, 33, and 34 are unavailable (116 MW).:     2025-04-18 12:18     166168     2025-04-18 12:18  
  PPW 25-02328     17642     PPW     Red Lake (TB Flats 1): 230/34.5 kV XFMR T3          WINDGEN-PACW(PPW)      9999.0      9999.0      9999.0      2025-05-23 06:00      2025-05-23 18:00      CANCELLED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Install avian guarding.:TB Flats 1/Red Lakes circuits 31, 32, 33, and 34 are unavailable (116 MW).:     2025-01-31 13:40     161407     2025-04-18 12:05  
  PPW 25-06373     17867     PPW     Painter-Railroad 138kV line          WINDGEN-PACE(PPW)      9999.0      9999.0      0.0      2025-05-26 07:30      2025-05-28 15:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     1234567 Daily:NERC relay maintenance.:Longhollow and Mtn Wind are restricted to a total of 232 MW Potential impact to PACE-UINTA & UINTA-PACE.:     2025-04-22 12:31     165471     2025-04-23 12:30  
  PPW 25-00812     17597     PPW     Windstar-Top of the World 230 kV line,Top of the World (Duke Energy): 230/34 kV T1,Top of the World          WINDGEN-PACE(PPW) 
  WINDGEN-PACW(PPW)   
  9999.0 
  9999.0   
  9999.0 
  9999.0   
  9999.0 
  0.0   
  2025-05-28 07:00 
  2025-05-28 07:00   
  2025-05-30 17:00 
  2025-05-30 17:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Site annual maintenance.:Top of the World Wind Farm Generation unavailable (200.2 mw).:     2025-01-08 10:32     159887     2025-02-06 14:46  
  PPW 23-13404     17846     PPW     Pilot Butte: T-3949 Bank #4          OTHERGEN-PACW(PPW)      9999.0      9999.0      0.0      2025-05-29 21:00      2025-05-30 21:00      SCHEDULED     DISTRIBUTION     PLANNED      ONPATH     PPW     continuous:Drop and Pick Dobbin, Klondike and Drake Feeders onto Mobile T-3830 to prepare for the 69kV Main Bus Outage. Remove Lowside Jumpers from Mobile on Go Back. :     2025-04-16 10:24     126774     2025-04-16 10:24  
  PPW 23-13403     17821     PPW     Pilot Butte: 69 kV West Bus,Pilot Butte-CEC Tap 69 kV line,China Hat-Pilot Butte 69 kV line          OTHERGEN-PACW(PPW)      9999.0      9999.0      0.0      2025-05-29 23:30      2025-05-30 08:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Take outage on the 69kV West Bus to string SO Loop Line #2 conductor and 69kV CEC Line conductor from Substation dead-end to new deadend, including line jumpers and Jumpers to bus. Energize CEC Tap Line on the go back for this outage.:Bear Creek solar unavailable. Neff Solar unavailable. Collier Solar unavailable.:     2025-04-09 09:02     126773     2025-04-09 09:02  
  PPW 25-00090     17538     PPW     Ben Lomond-Populus #2 345 kV line,Ben Lomond: 345 kV East Bus,Ben Lomond: CB 366          JBSN-JB345(PPW) 
  NUT-PATHC(PPW) 
  PATHC-NUT(PPW)   
  1600.0 
  1060.0 
  1600.0   
  1600.0 
  1060.0 
  1600.0   
  1427.0 
  788.0 
  1600.0   
  2025-05-30 08:00 
  2025-05-30 08:00 
  2025-05-30 08:00   
  2025-05-30 17:00 
  2025-05-30 17:00 
  2025-05-30 17:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:To return CB366 a clearance boundary on the east bus, and Ben Lomond-Populus line, and CB 366 is required. :JBSN-JB345 = 2200. PacifiCorp = 1427. IPCo = 733. NUT-PATHC = 800 Summer/900 Winter. PATHC-NUT = 1410 Summer.:     2024-12-05 12:36     158140     2024-12-05 12:43  
  PPW 25-02628     17748     PPW     Fish Creek Tap-Slide Creek Tap section of the Soda Springs-Toketee Switch Station 115 kV line,Slide          HYDROGEN-PACW(PPW)      9999.0      9999.0      0.0      2025-06-02 06:00      2025-06-08 16:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Replacing structures 1/3, 2/3 and 7/3. Including replacing switches 2U345 and 2U344 at Slide Cr.tap.:Toketee, Clearwater, Fish Creek, and Lemolo Plant combined generation 114 Summer/154 Winter MVA:     2025-03-11 14:23     161707     2025-03-11 14:28  
  PPW 25-03490     17720     PPW     Atlantic City: CB 1H120,Atlantic City-Rock Springs 230 kV line          TOT4B-WYONORTH(PPW) 
  WAPAEAST-WAPANORTH(PPW) 
  WYOCENTRAL-WYOEAST(PPW) 
  WYOEAST-AEOW(PPW) 
  WYOEAST-WYOCENTRAL(PPW)   
  631.0 
  249.0 
  574.0 
  0.0 
  574.0   
  631.0 
  249.0 
  574.0 
  0.0 
  574.0   
  571.0 
  235.0 
  287.0 
  0.0 
  287.0   
  2025-06-02 07:00 
  2025-06-02 07:00 
  2025-06-02 07:00 
  2025-06-02 07:00 
  2025-06-02 07:00   
  2025-06-04 10:00 
  2025-06-04 10:00 
  2025-06-04 10:00 
  2025-06-04 10:00 
  2025-06-04 10:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Breaker Minor Maintenance:AW/4B Curve 117. WAPAEAST-WAPANORTH = 235. WYOEAST-AEOW (Aeolus West) = 1632. TOT4B-WYONORTH = 571. TOT 4B = 806. Potential Real Time Impact to Wyoming Generation:     2025-02-27 14:05     162572     2025-02-27 14:05  
  PPW 25-06418     17868     PPW     Clover: Transformer #3          CLOVER-PACE(PPW) 
  PACE-CLOVER(PPW)   
  1700.0 
  1000.0   
  1700.0 
  1000.0   
  1600.0 
  900.0   
  2025-06-02 07:00 
  2025-06-02 07:00   
  2025-06-06 14:00 
  2025-06-06 14:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Clover XFMR #3 Outage to Replace Tertiary Bushings:CLOVER-PACE=1600. PACE-CLOVER=900.:     2025-04-22 13:30     165516     2025-04-22 13:30  
  PPW 23-13405     17822     PPW     Pilot Butte - Cleveland line 2 section of Pilot Butte - China Hat 69 kV line,Pilot Butte: Mobile T-3          OTHERGEN-PACW(PPW)      9999.0      9999.0      9999.0      2025-06-02 08:00      2025-06-02 17:00      CANCELLED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Remove High side Jumpers and remove Mobile T-3830 and Install Pilot Butte-Cleveland Line #2 Jumpers. Energize Pilot Butte - Cleveland Line #2:     2025-04-09 09:03     126775     2025-04-29 13:30  
  PPW 25-03491     17721     PPW     Atlantic City: LINE CB 1H116,Wyopo-Atlantic City section of the Riverton-Atlantic City 230 kV line          TOT4B-WYONORTH(PPW) 
  WAPAEAST-WAPANORTH(PPW) 
  WYOCENTRAL-WYOEAST(PPW) 
  WYOEAST-AEOW(PPW) 
  WYOEAST-WYOCENTRAL(PPW)   
  631.0 
  249.0 
  574.0 
  0.0 
  574.0   
  631.0 
  249.0 
  574.0 
  0.0 
  574.0   
  571.0 
  235.0 
  287.0 
  0.0 
  287.0   
  2025-06-04 11:00 
  2025-06-04 11:00 
  2025-06-04 11:00 
  2025-06-04 11:00 
  2025-06-04 11:00   
  2025-06-06 16:30 
  2025-06-06 16:30 
  2025-06-06 16:30 
  2025-06-06 16:30 
  2025-06-06 16:30   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Breaker Minor Maintenance 1H116:AW/4B Curve 117. WAPAEAST-WAPANORTH = 235. WYOEAST-AEOW (Aeolus West) = 1632. TOT4B-WYONORTH = 571. TOT 4B = 806. Potential Real Time Impact to Wyoming Generation:     2025-02-27 14:17     162573     2025-02-27 14:33  
  PPW 25-02001     17628     PPW     BPA Hood River: 115 kV Main Bus,BPA Hood River: CB B1680,BPA Hood River: SW B1690,BPA Hood River: CB          PACW-NTLOAD(PPW)      9999.0      9999.0      0.0      2025-06-07 23:00      2025-06-08 09:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:115K M/B PT DIAGNOSTIC SERVICE, 115KV M/B DISCONNECT SERVICE'S AND METERING CT DIAGNOSTIC SERVICE / HOOD RIVER:Tucker area load will be served radially from BPA Bald Mountain. Network load arrangements may be required.:     2025-01-28 11:51     161078     2025-01-28 11:51  
  PPW 25-02330     17643     PPW     Big Charlie (TB Flats 2): 230/34.5 kV XFMR T1          OTHERGEN-PACW(PPW) 

  WINDGEN-PACW(PPW)   
  9999.0 

  9999.0   
  9999.0 

  9999.0   
  9999.0 

  0.0   
  2025-05-09 06:00 

  2025-06-09 06:00   
  2025-05-09 18:00 

  2025-06-09 18:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Install avian guarding.:TB Flats 2/Big Charlie Circuits 11, 12, 13, and 14 unavailable (106 MW).:     2025-01-31 13:52     161409     2025-02-13 09:07  
  PPW 25-03821     17759     PPW     Glide Tap-Steamboat section of the Dixonville-Toketee Switch Station 115 kV line          HYDROGEN-PACW(PPW)      9999.0      9999.0      0.0      2025-06-09 06:00      2025-06-09 18:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Replace 2 fly structures. 3/23, 6/23:Umpqua River Hydro Project Restriction = 174 Summer/199 Winter.:     2025-03-18 10:30     162903     2025-03-18 10:35  
  PPW 25-02331     17644     PPW     Big Charlie (TB Flats 2): 230/34.5 kV XFMR T1,Big Charlie (TB Flats 2): 230/34.5 kV XFMR T2          OTHERGEN-PACW(PPW) 

  WINDGEN-PACW(PPW)   
  9999.0 

  9999.0   
  9999.0 

  9999.0   
  9999.0 

  0.0   
  2025-05-10 06:00 

  2025-06-10 06:00   
  2025-05-10 18:00 

  2025-06-10 18:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Install avian guarding.:TB Flats 2/Big Charlie Circuits 11, 12, 13, and 14 unavailable (106 MW). TB Flats 2/Big Charlie Circuits 21, 22, 23, and 24 unavailable (91 MW).:     2025-01-31 14:01     161410     2025-02-13 09:08  
  PPW 25-02333     17645     PPW     Big Charlie (TB Flats 2): 230/34.5 kV XFMR T2          OTHERGEN-PACW(PPW) 

  OTHERGEN-PACW(PPW) 
  WINDGEN-PACW(PPW)   
  9999.0 

  9999.0 
  9999.0   
  9999.0 

  9999.0 
  9999.0   
  9999.0 

  9999.0 
  0.0   
  2025-05-11 06:00 

  2025-06-11 06:00 
  2025-06-11 06:00   
  2025-05-11 18:00 

  2025-06-11 18:00 
  2025-06-11 18:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Install avian guarding.:TB Flats 2/Big Charlie Circuits 21, 22, 23, and 24 unavailable (91 MW).:     2025-01-31 14:04     161412     2025-02-06 14:48  
  PPW 25-02334     17646     PPW     Big Charlie (TB Flats 2): 230/34.5 kV XFMR T1          OTHERGEN-PACW(PPW) 

  OTHERGEN-PACW(PPW) 
  WINDGEN-PACW(PPW)   
  9999.0 

  9999.0 
  9999.0   
  9999.0 

  9999.0 
  9999.0   
  9999.0 

  9999.0 
  0.0   
  2025-05-12 06:00 

  2025-06-12 06:00 
  2025-06-12 06:00   
  2025-05-12 18:00 

  2025-06-12 18:00 
  2025-06-12 18:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Install avian guarding.:TB Flats 2/Big Charlie Circuits 11, 12, 13, and 14 unavailable (106 MW).:     2025-01-31 14:08     161413     2025-02-06 14:49  
  PPW 25-02335     17647     PPW     Big Charlie (TB Flats 2): 230/34.5 kV XFMR T2          OTHERGEN-PACW(PPW) 

  WINDGEN-PACW(PPW)   
  9999.0 

  9999.0   
  9999.0 

  9999.0   
  9999.0 

  0.0   
  2025-05-13 06:00 

  2025-06-13 06:00   
  2025-05-13 18:00 

  2025-06-13 18:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Install avian guarding.:TB Flats 2/Big Charlie Circuits 21, 22, 23, and 24 unavailable (91 MW).:     2025-01-31 14:15     161414     2025-02-06 14:41  
  PPW 25-04514     17747     PPW     Crag View-PG&E Cascade section of the PG&E Cascade-Weed Junction 115 kV line          CRAG-CRAGVIEW(PPW) 
  CRAGVIEW-CRAG(PPW) 

  CRAG-CRAGVIEW(PPW) 
  CRAGVIEW-CRAG(PPW)   
  45.0 
  80.0 

  45.0 
  80.0   
  45.0 
  80.0 

  45.0 
  80.0   
  45.0 
  80.0 

  0.0 
  0.0   
  2025-04-10 07:00 
  2025-04-10 07:00 

  2025-06-23 07:00 
  2025-06-23 07:00   
  2025-04-11 16:30 
  2025-04-11 16:30 

  2025-06-27 16:30 
  2025-06-27 16:30   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:change b/o bells 2/58,1/63:CRAG-CRAGVIEW & CRAGVIEW-CRAG = 0.:     2025-03-11 11:13     163602     2025-04-04 12:24  
  PPW 25-03418     17689     PPW     Crag View-PG&E Cascade section of the PG&E Cascade-Weed Junction 115 kV line          CRAG-CRAGVIEW(PPW) 
  CRAGVIEW-CRAG(PPW)   
  45.0 
  80.0   
  45.0 
  80.0   
  0.0 
  0.0   
  2025-06-30 07:00 
  2025-06-30 07:00   
  2025-10-31 17:00 
  2025-10-31 17:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Reconductor between structures.:CRAG-CRAGVIEW & CRAGVIEW-CRAG = 0.:     2025-02-18 12:38     162500     2025-02-18 12:45  
  PPW 25-07147     17872     PPW     BPA Salem-Dallas section of the BPA Salem-Monpac 115 kV line               0.0      0.0      0.0      2025-06-30 07:00      2025-06-30 17:30      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:POLE REPLACEMENT, STRUCTURE 17/11:Network Load Service may need to arranged for Dallas & Independence via Monpac. (Monpac Sw 2M88 will be closed & Dallas Sw 2M150 will be open) BPA to Stay Normal at Salem on CB B52 & Albany CB B518.:     2025-04-23 09:54     166249     2025-04-23 09:54  
  PPW 25-02017     17629     PPW     Crag View-PG&E Cascade section of the PG&E Cascade-Weed Junction 115 kV line          CRAG-CRAGVIEW(PPW) 
  CRAGVIEW-CRAG(PPW)   
  45.0 
  80.0   
  45.0 
  80.0   
  0.0 
  0.0   
  2025-07-01 06:00 
  2025-07-01 06:00   
  2025-09-30 17:00 
  2025-09-30 17:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Line reconductoring. Replacing structures.:CRAG-CRAGVIEW & CRAGVIEW-CRAG = 0.:     2025-01-28 13:43     161094     2025-01-28 13:43  
  PPW 24-09589     17009     PPW     PG&E Cascade: CB 122          CRAG-CRAGVIEW(PPW) 
  CRAGVIEW-CRAG(PPW) 
  PACW-CRAGVIEW(PPW) 

  CRAG-CRAGVIEW(PPW) 
  CRAGVIEW-CRAG(PPW) 
  PACW-CRAGVIEW(PPW) 

  CRAG-CRAGVIEW(PPW) 
  CRAGVIEW-CRAG(PPW) 
  PACW-CRAGVIEW(PPW)   
  45.0 
  80.0 
  115.0 

  45.0 
  80.0 
  150.0 

  45.0 
  80.0 
  115.0   
  45.0 
  80.0 
  115.0 

  45.0 
  80.0 
  150.0 

  45.0 
  80.0 
  115.0   
  45.0 
  80.0 
  115.0 

  45.0 
  80.0 
  150.0 

  0.0 
  0.0 
  0.0   
  2024-08-05 07:00 
  2024-08-05 07:00 
  2024-08-05 07:00 

  2024-12-25 07:00 
  2024-12-25 07:00 
  2024-12-25 07:00 

  2025-07-04 07:00 
  2025-07-04 07:00 
  2025-07-04 07:00   
  2024-08-09 16:00 
  2024-08-09 16:00 
  2024-08-09 16:00 

  2024-12-25 16:00 
  2024-12-25 16:00 
  2024-12-25 16:00 

  2025-07-04 16:00 
  2025-07-04 16:00 
  2025-07-04 16:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Install pott relaying to the Crag View - Cascade 115kV line.:CRAG-CRAGVIEW & CRAGVIEW-CRAG = 0.:     2024-06-06 13:30     147422     2024-12-02 07:13  
  PPW 25-02485     17693     PPW     Clausen (Cedar Springs 2): XFMR T2          WINDGEN-PACW(PPW) 

  WINDGEN-PACW(PPW)   
  9999.0 

  9999.0   
  9999.0 

  9999.0   
  0.0 

  9999.0   
  2025-07-07 07:00 

  2025-07-11 23:55   
  2025-07-11 23:55 

  2025-08-07 23:55   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Avian Guarding Project 2025:Cedar Springs 2 Wind Farm unavailable.:     2025-02-20 14:34     161564     2025-02-25 12:58  
  PPW 24-04189     16311     PPW     Cove (OR): 230/69 kV Bank #2 (T3398)          COVEPACW-ROUNDBUTTE(PPW) 
  ROUNDBUTTE-COVEPACW(PPW) 

  COVEPACW-ROUNDBUTTE(PPW) 
  ROUNDBUTTE-COVEPACW(PPW) 

  COVEPACW-ROUNDBUTTE(PPW) 
  ROUNDBUTTE-COVEPACW(PPW) 

  COVEPACW-ROUNDBUTTE(PPW) 
  ROUNDBUTTE-COVEPACW(PPW)   
  123.0 
  123.0 

  123.0 
  123.0 

  123.0 
  123.0 

  123.0 
  123.0   
  123.0 
  123.0 

  123.0 
  123.0 

  123.0 
  123.0 

  123.0 
  123.0   
  123.0 
  123.0 

  123.0 
  123.0 

  123.0 
  123.0 

  60.0 
  60.0   
  2024-07-01 12:00 
  2024-07-01 12:00 

  2024-10-14 12:00 
  2024-10-14 12:00 

  2025-04-28 12:00 
  2025-04-28 12:00 

  2025-07-07 12:00 
  2025-07-07 12:00   
  2024-07-21 12:00 
  2024-07-21 12:00 

  2024-11-01 12:00 
  2024-11-01 12:00 

  2025-05-30 12:00 
  2025-05-30 12:00 

  2025-08-01 12:00 
  2025-08-01 12:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:T-3398 LTC Maintenance and Bushing Replacement:COVEPACW-ROUNDBUTTE & ROUNDBUTTE-COVEPACW = 60.:     2024-03-15 09:39     142013     2025-03-25 09:46  
  PPW 25-06480     17832     PPW     WAPA Flaming Gorge: 230/138 kV XFMR KY2A          FGE-WYOCENTRAL(PPW) 
  WYOCENTRAL-FGE(PPW)   
  200.0 
  200.0   
  200.0 
  200.0   
  0.0 
  200.0   
  2025-07-08 06:30 
  2025-07-08 06:30   
  2025-07-10 11:00 
  2025-07-10 11:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Transformer maintenance.:FGE-WYOCENTRAL = 0. WYOCENTRAL-FGE = Little Mtn load.:     2025-04-10 08:41     165579     2025-04-10 08:41  
  PPW 25-06540     17869     PPW     Dunlap: 230/34 kV Bank #1          WINDGEN-PACW(PPW)      9999.0      9999.0      0.0      2025-07-14 08:00      2025-07-17 13:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:WECC maintenance for T1, CB 1H2016 & 230kV Bus:Dunlap Wind restricted to 0 MW and de-energized.:     2025-04-22 13:57     165641     2025-04-22 13:57  
  PPW 25-07718     17884     PPW     Sunbeam-Moonshine 230 kV line          WINDGEN-PACE(PPW)      9999.0      9999.0      9999.0      2025-07-15 05:00      2025-07-15 21:00      CANCELLED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Substation offline maintenance.:Moonshine Generation unavailable (45 mw).:     2025-04-30 10:00     166824     2025-04-30 10:03  
  PPW 25-06448     17825     PPW     Moonshine: 230/34.5 kV Bank T-1          WINDGEN-PACE(PPW)      9999.0      9999.0      0.0      2025-07-15 06:00      2025-07-15 21:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Site outage for substation offline maintenance.:Moonshine generation unavailable.:     2025-04-09 13:28     165547     2025-04-09 13:31  
  PPW 25-03420     17859     PPW     Ekola Flats: 230/34.5 kV T1,Ekola Flats: 34.5kV Bus 1          WINDGEN-PACW(PPW)      9999.0      9999.0      0.0      2025-08-04 09:00      2025-08-04 18:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Install bird guarding.:Ekola Flats Feeder 11, 12, 13, 14, and 15 unavailable (125MW).:     2025-04-18 14:26     162502     2025-04-28 09:50  
  PPW 25-07188     17870     PPW     Fry-Parrish Gap 230 kV line          PACW-PACW.PGE(PPW) 
  PACW.PGE-PACW(PPW)   
  325.0 
  325.0   
  325.0 
  325.0   
  159.0 
  159.0   
  2025-08-04 22:00 
  2025-08-04 22:00   
  2025-08-05 08:00 
  2025-08-05 08:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Replace arm at structure 4/1:PACW-PGE.PACW & PACW.PGE-PACW = 159 Summer/149 Winter Network Load Service Arrangements may be required.:     2025-04-22 14:03     166290     2025-04-22 14:06  
  PPW 25-03929     17736     PPW     Alturas-Cedarville Tap section of the Alturas-Bullard 115 kV line          OTHERGEN-PACW(PPW)      9999.0      9999.0      0.0      2025-08-05 07:00      2025-08-08 13:30      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:REPLACE POLES 6/49 8/49 5/50 8/50 :Airport Solar and Garrett Solar restricted to 0 MW during switching.:     2025-03-06 13:59     163011     2025-03-06 13:59  
  PPW 25-03422     17860     PPW     Ekola Flats: 230/34.5 kV T1,Ekola Flats: 230/34.5 kV T2,Ekola Flats: 34.5kV Bus 1,Ekola Flats: 34.5k          WINDGEN-PACW(PPW)      9999.0      9999.0      0.0      2025-08-05 09:00      2025-08-05 18:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Install bird guarding.:Ekola Flats Feeders 11, 12, 13, 14, 15, 21, 22, 23, 24, and 25 unavailable (250MW total).:     2025-04-18 14:29     162504     2025-04-28 09:49  
  PPW 25-07192     17871     PPW     Fry-Calapooya section of the Diamond Hill-Fry 230 kV line          PACW-NTLOAD(PPW)      9999.0      9999.0      0.0      2025-08-05 22:00      2025-08-06 08:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Replace arms at structure 4/14:Network Load Service must be arranged for Calapooya, Diamond Hill & EWEB McKenzie. Eliminates ability to move Network Load Service from Alvey to Gresham. Eliminates C&T Point to Point Service from Troutdale to Summer Lake.:     2025-04-22 14:06     166294     2025-04-22 14:11  
  PPW 25-03423     17861     PPW     Ekola Flats: 230/34.5 kV T2,Ekola Flats: 34.5kV Bus 2          WINDGEN-PACW(PPW)      9999.0      9999.0      0.0      2025-08-06 09:00      2025-08-06 18:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Install bird guarding.:Ekola Flats Feeders 21, 22, 23, 24, and 25 unavailable (125MW):     2025-04-18 14:35     162505     2025-04-28 09:47  
  PPW 25-03424     17862     PPW     Ekola Flats: 230/34.5 kV T1,Ekola Flats: 34.5kV Bus 1          WINDGEN-PACW(PPW)      9999.0      9999.0      0.0      2025-08-07 09:00      2025-08-07 18:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Install bird guarding.:Ekola Flats Feeder 11, 12, 13, 14, and 15 unavailable (125MW).:     2025-04-18 14:39     162506     2025-04-28 09:46  
  PPW 25-03426     17863     PPW     Ekola Flats: 230/34.5 kV T2,Ekola Flats: 34.5kV Bus 2          WINDGEN-PACW(PPW)      9999.0      9999.0      0.0      2025-08-08 09:00      2025-08-08 18:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Install bird guarding.:Ekola Flats Feeders 21, 22, 23, 24, and 25 unavailable (125MW).:     2025-04-18 14:50     162508     2025-04-28 09:45  
  PPW 25-03360     17687     PPW     Dave Johnston-TSGT Laramie River Station 230 kV line          DJ-WYOEAST(PPW) 
  WYOEAST-AEOW(PPW) 
  WYOEAST-DJ(PPW)   
  790.0 
  0.0 
  790.0   
  790.0 
  0.0 
  790.0   
  442.0 
  0.0 
  442.0   
  2025-09-02 07:00 
  2025-09-02 07:00 
  2025-09-02 07:00   
  2025-09-19 15:00 
  2025-09-19 15:00 
  2025-09-19 15:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:2025 structure replacements.:DJ-WYOEAST & WYOEAST-DJ = 442 (Dave Johnston-WAPA Stegall 230 kV line rating):     2025-02-17 14:22     162442     2025-02-17 14:28  
  PPW 25-03417     17688     PPW     Malin-PG&E Round Mountain #1 500 kV line          MALIN500-RDM500(PPW) 
  RDM500-MALIN500(PPW) 

  MALIN500-RDM500(PPW) 
  RDM500-MALIN500(PPW)   
  800.0 
  612.0 

  800.0 
  612.0   
  800.0 
  612.0 

  800.0 
  612.0   
  625.0 
  416.0 

  800.0 
  612.0   
  2025-09-08 06:00 
  2025-09-08 06:00 

  2025-09-29 06:00 
  2025-09-29 06:00   
  2025-09-12 17:00 
  2025-09-12 17:00 

  2025-10-03 17:00 
  2025-10-03 17:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Install lab measurement and fault initiating test equipment on primary conductors (Grounded).:MALIN500-RDM500 = 625. RDM500-MALIN500 = 416.:     2025-02-18 12:23     162499     2025-04-10 08:52  
  PPW 25-05028     17750     PPW     Pryor Mountain Wind: 34.5kV Bus 2,Pryor Mountain Wind: 34.5kV Bus 1          WINDGEN-PACW(PPW) 

  WINDGEN-PACW(PPW)   
  9999.0 

  9999.0   
  9999.0 

  9999.0   
  9999.0 

  0.0   
  2025-07-07 08:00 

  2025-09-08 08:00   
  2025-07-09 11:00 

  2025-09-10 11:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Install avian protection.:Pryor Mountain Wind unavailable.:     2025-03-14 11:07     164124     2025-03-17 12:01  
  PPW 25-05029     17751     PPW     Circuit 1,Circuit 2,Circuit 3,Circuit 4,Circuit 5,Circuit 6,Pryor Mountain Wind: 34.5kV Bus 1          WINDGEN-PACW(PPW) 

  WINDGEN-PACW(PPW)   
  9999.0 

  9999.0   
  9999.0 

  9999.0   
  0.0 

  9999.0   
  2025-07-09 11:00 

  2025-09-08 08:00   
  2025-07-11 16:00 

  2025-09-12 16:00   
  CANCELLED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Install avian protection.:Pryor Mountain Wind circuits 1-6 (120.6MW) unavailable.:     2025-03-14 11:21     164125     2025-03-17 12:03  
  PPW 25-03879     17708     PPW     Sweet Home: Main Bus Disc CB 4M94,Sweet Home: Bypass Bus Disc CB 4M94,Sweet Home: Line Disc CB 4M94          HYDROGEN-PACW(PPW)      9999.0      9999.0      0.0      2025-09-15 08:00      2025-09-19 15:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Breaker maintenance.:Fall Creek Hydro Units 1, 2, and 3 unavailable.:     2025-02-25 10:20     162961     2025-02-25 10:20  
  PPW 25-06481     17833     PPW     Malin-PG&E Round Mountain #1 500 kV line          MALIN500-RDM500(PPW) 
  RDM500-MALIN500(PPW)   
  800.0 
  612.0   
  800.0 
  612.0   
  625.0 
  416.0   
  2025-09-17 06:00 
  2025-09-17 06:00   
  2025-09-19 17:00 
  2025-09-19 17:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Install lab measurement and fault initiating test equipment on primary conductors (Grounded).:MALIN500-RDM500 = 625. RDM500-MALIN500 = 416.:     2025-04-10 08:55     165580     2025-04-10 08:55  
  PPW 25-00010     16953     PPW     Hemingway-Summer Lake 500 kV line          H500-SMLK(PPW) 
  PACW-NTLOAD(PPW) 
  SMLK-H500(PPW) 

  H500-SMLK(PPW) 
  PACW-NTLOAD(PPW) 
  SMLK-H500(PPW)   
  1500.0 
  9999.0 
  100.0 

  1500.0 
  9999.0 
  100.0   
  1500.0 
  9999.0 
  100.0 

  1500.0 
  9999.0 
  100.0   
  1500.0 
  9999.0 
  100.0 

  0.0 
  0.0 
  0.0   
  2025-04-01 08:00 
  2025-04-01 08:00 
  2025-04-01 08:00 

  2025-10-17 08:00 
  2025-10-17 08:00 
  2025-10-17 08:00   
  2025-09-14 18:00 
  2025-09-14 18:00 
  2025-09-14 18:00 

  2025-10-31 18:00 
  2025-10-31 18:00 
  2025-10-31 18:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Spacer Replacements:H500-SMLK & SMLK-H500 = 0; BORA-M500 = 959; Network Load Service Arrangements may be required for Southern Oregon Load.:     2024-04-30 09:25     144659     2024-12-20 09:45  
  PPW 25-04089     17722     PPW     Spanish Fork: 138 kV West/Operating Bus          OTHERGEN-PACE(PPW) 
  PACE-NTLOAD(PPW) 
  THERMALGEN-PACE(PPW) 
  VNL-PACE(PPW) 

  OTHERGEN-PACE(PPW) 
  PACE-NTLOAD(PPW) 
  THERMALGEN-PACE(PPW) 
  VNL-PACE(PPW) 

  OTHERGEN-PACE(PPW) 
  PACE-NTLOAD(PPW) 
  THERMALGEN-PACE(PPW) 
  VNL-PACE(PPW) 

  OTHERGEN-PACE(PPW) 
  PACE-NTLOAD(PPW) 
  THERMALGEN-PACE(PPW) 
  VNL-PACE(PPW) 

  OTHERGEN-PACE(PPW) 
  PACE-NTLOAD(PPW) 
  THERMALGEN-PACE(PPW) 
  VNL-PACE(PPW)   
  9999.0 
  9999.0 
  9999.0 
  138.0 

  9999.0 
  9999.0 
  9999.0 
  138.0 

  9999.0 
  9999.0 
  9999.0 
  138.0 

  9999.0 
  9999.0 
  9999.0 
  138.0 

  9999.0 
  9999.0 
  9999.0 
  138.0   
  9999.0 
  9999.0 
  9999.0 
  138.0 

  9999.0 
  9999.0 
  9999.0 
  138.0 

  9999.0 
  9999.0 
  9999.0 
  138.0 

  9999.0 
  9999.0 
  9999.0 
  138.0 

  9999.0 
  9999.0 
  9999.0 
  138.0   
  9999.0 
  9999.0 
  9999.0 
  138.0 

  9999.0 
  9999.0 
  9999.0 
  138.0 

  9999.0 
  9999.0 
  9999.0 
  138.0 

  9999.0 
  9999.0 
  9999.0 
  138.0 

  0.0 
  0.0 
  0.0 
  0.0   
  2025-03-31 08:00 
  2025-03-31 08:00 
  2025-03-31 08:00 
  2025-03-31 08:00 

  2025-04-07 08:00 
  2025-04-07 08:00 
  2025-04-07 08:00 
  2025-04-07 08:00 

  2025-04-14 08:00 
  2025-04-14 08:00 
  2025-04-14 08:00 
  2025-04-14 08:00 

  2025-05-05 08:00 
  2025-05-05 08:00 
  2025-05-05 08:00 
  2025-05-05 08:00 

  2025-12-31 08:00 
  2025-12-31 08:00 
  2025-12-31 08:00 
  2025-12-31 08:00   
  2025-04-07 08:00 
  2025-04-07 08:00 
  2025-04-07 08:00 
  2025-04-07 08:00 

  2025-04-14 08:00 
  2025-04-14 08:00 
  2025-04-14 08:00 
  2025-04-14 08:00 

  2025-04-18 16:00 
  2025-04-18 16:00 
  2025-04-18 16:00 
  2025-04-18 16:00 

  2025-05-09 16:00 
  2025-05-09 16:00 
  2025-05-09 16:00 
  2025-05-09 16:00 

  2025-12-31 16:00 
  2025-12-31 16:00 
  2025-12-31 16:00 
  2025-12-31 16:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:Building/Welding bus extension to new distribution yard. Commissioning 7C21.:Graphite Solar limited to 10 MW maximum output. Possible real-time restriction to Lakeside 1 (Dynamo) generation. PACE-VNL = 0. VNL-PACE = 0. load. Network Load Service Arrangements are required for Ashley, Emma Park, Mounds, Mathington, Carbon, Helper, Columbia, Tamarisk . TOT-1A & CRSP Schedules are impacted by this outage.:     2025-02-28 13:36     163171     2025-04-24 13:03  
  PPW 26-00002     17627     PPW     IPC Midpoint-Hemingway 500 kV line,IPCo Midpoint: 500/345 kV Bank T-501          H500-M500(PPW) 
  M500-H500(PPW) 
  PACW-NTLOAD(PPW)   
  800.0 
  1090.0 
  9999.0   
  800.0 
  1090.0 
  9999.0   
  350.0 
  350.0 
  0.0   
  2026-02-23 08:00 
  2026-02-23 08:00 
  2026-02-23 08:00   
  2026-05-29 15:00 
  2026-05-29 15:00 
  2026-05-29 15:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     continuous:This outage is for relocating the existing Midpoint T501 345kV/500kV transformer to a new 345kV station bay.:M500-H500 & H500-M500= 350. BORA-M500 = 959. No impact to Bridger West. Jim Bridger Generation may be restricted real time (as determined by Northwest Path Flow). Network Load Service Arrangements may be required for Southern Oregon Load. Note: TTC Schedules on Path 75 East & West are 0. However, the SOL is 350 West / 325 East (Limited by Bowmont Xfmrs). However, there is a potential of up to 300 mw of actual unscheduled inadvertent flow between Hemingway & Summer Lake. JBSN-JB345 = 2200. PacifiCorp = 1467. IPCo = 733. Jim Bridger Generation may be restricted real time (as determined by Northwest Path Flow).:     2025-01-28 09:16     161059     2025-01-28 09:16  