Welcome to the American Transmission Company Budget and Rates Page

Budget Information Informational Filings True-Up Data and Notices
2024 Budget - Update 01/09/24
2024 Budget
2023 Budget - Update 02/17/23
2023 Budget - Update 10/5/22
2023 Budget
2022 Budget Update - 01/20/22
2022 Budget
2021 Budget
2020 Budget Update - 12/18/19
2020 Budget Update - 10/24/19
ATC Response to 2020 Budget Information Request - 10/11/19
2020 Budget

ATC Response to 2019 Budget Information Request - 10/16/18
2019 Budget Update - 10/10/18
2019 Budget

2018 Budget - Update 4/6/18
ATC Response to 2018 Budget Information Request - 11/14/17
ATC Response to 2018 Budget Information Request - 10/26/17
ATC Response to 2018 Budget Information Request - 10/12/17
2018 Budget

ATC Response to 2017 Budget Information Request - 10/18/16
2017 Budget Update - 10/10/16
2017 Budget

2016 Budget Update - 1/25/16
2016 Budget Update - 1/6/16
ATC Response to 2016 Budget Information Request - 11/04/15
ATC Response to 2016 Budget Information Request - 10/16/15
ATC Response to 2016 Budget Information Request - 10/08/15
2016 Budget

2015 Budget Update - 1/8/15
ATC Response to 2015 Budget Information Request - 1/5/15
ATC Response to 2015 Budget Information Request - 11/13/14
2015 Budget Update - 10/24/14
ATC Response to 2015 Budget Information Request - 10/20/14
ATC Response to 2015 Budget Information Request - 10/10/14
ATC Respones to 2015 Budget Information Request - 10/07/14
2015 Budget

2014 Budget Update - 1/17/14
2014 Budget

2013 Budget - Update 1/07/13
2013 Budget

2012 Budget Update - 1/10/12
2012 Budget Update - 10/18/11
2012 Budget Update - 10/4/11
2012 Budget

2011 Budget - Update 12/17/10
2011 Budget - Attachment GG
2011 Budget - Update 10/13/10
2011 Budget

2010 Rate Implementation
2010 Budget

2009 Rate Implementation
2009 Budget

ATC Formula Rate Protocol Informational Filing - 3/8/24
ATC Formula Rate Protocol Informational Filing - 3/10/23
ATC Formula Rate Protocol Informational Filing - 3/14/22
ATC Formula Rate Protocol Informational Filing - 3/11/21
ATC Formula Rate Protocol Informational Filing - 3/12/20
ATC Formula Rate Protocol Informational Filing - 3/11/19
ATC Formula Rate Protocol Informational Revised Filing - 4/12/18
ATC Formula Rate Protocol Informational Filing - 3/12/18
ATC Formula Rate Protocol Informational Filing - 3/16/17
ATC Formula Rate Protocol Informational Filing - 3/14/16
ATC Informational Filing - 3/13/15
Notice of 2022 True-Up Stakeholder Meeting
ATC 2022 True-Up Data Available
Notice of 2021 True-Up Stakeholder Meeting
ATC 2021 True-Up Data Available
Notice of 2020 True-Up Stakeholder Meeting
ATC 2020 True-Up Data Available
Notice of 2019 True-Up Stakeholder Meeting
ATC 2019 True-Up Data Available
ATC Notice of 2018 True-Up Stakeholder Meeting
ATC 2018 True-Up Data - 5/28/19

Revised ATC 2017 True-Up Data - 10/10/18
ATC Notice of 2017 True-Up Stakeholder Meeting
Revised ATC 2017 True-Up Data - 6/25/18
ATC 2017 True-Up Data Available

Notice of 2016 True-Up Data and Stakeholder Meeting
ATC 2016 True-Up Data Available

2015 True-Up Data Update - 10/28/16
ATC Response to 2015 True-Up Data Information Requests - 6/9/16
Notice of 2015 True-Up Data and Stakeholder Meeting

ATC Response to 2014 True-Up Data Information Requests - 6/10/15
Notice of 2014 True-Up Data Stakeholder Meeting
ATC 2014 True-Up Data Available

ATC Response to 2013 True-Up Data Information Request – 8/13/14
ATC Response to 2013 True-Up Data Information Request – 7/14/14
ATC Response to 2013 True-Up Data Information Request – 7/9/14
ATC Response to 2013 True-Up Data Information Request – 7/2/14
2013 ATC True-Up Data Stakeholder Meeting – Update 7/3/14
Notice of 2013 True-Up Data Stakeholder Meeting
ATC 2013 True-Up Data Available

ATC 2012 True-Up Data Available

ATC 2011 True-Up Data Available

ATC 2010 True-Up Data Available

ATC 2009 True-Up Data – Updated 2/16/11
ATC 2009 True-Up Data Available

ATC 2008 True-Up Data Available

Other Postings

ATC 2013 Billing Procedure
ATC 2012 Regional Cost Sharing True-up Data Available


ATC Formula Rate Protocol Informational Filing - 3/8/24

On March 06, 2024, American Transmission Company LLC submitted an Informational Filing, docket number ER24-1418-000, comprised of a letter and supporting materials ("Informational Filing") that reflect American Transmission's projected net revenue requirement effective January 1, 2024, and American Transmission's 2022 Annual True-Up under Attachment O of the MISO Tariff.

Budget 2024 - Update 01/09/24

ATC has reposted the projections for: 2024 Attachment O, 2024 Schedules 7 & 8 (Point-to-Point) rates, and Schedule 9 projections through 2028 . These changes are due to updated coincident load data received from its customers. The load change does not result in a change to ATC's projected annual revenue requirement.

Rate Formula (Attachment O)
2024 Transmission Service Rates (Schedule 7 & 8)
ATC Rate Projections through 2028

The details of the calculations for the above are included in the following attachment.

Please submit all information requests or informal challenges to atcrates@atcllc.com.

Budget 2024

ATC will host a stakeholder meeting to discuss the 2024 Budget on Wednesday, October 11th at 2:00 p.m. (CDT). The 2024 Budget will be presented in detail and stakeholders will have an opportunity to discuss the budget information. We encourage you to extend this invitation to all appropriate staff in your organization. This meeting is offered as a teleconference/web meeting only.

Participation information for Microsoft Teams is as follows:

To join the web conference on your computer or mobile app, click HERE.

If you are unable to join via the web conference, you can also join by audio only. Enter phone number and conference ID below.
Phone Number:+1 608-620-9719
Conference ID: 339 180 800#

All available information on the 2024 Budget and Rates has been posted below to provide interested parties with an equal opportunity to review the documents.

Budget Presentation

Rate Formula (Attachment O)
2024 Attachment GG
2024 Attachment MM
ATC Schedule 1
2024 Transmission Service Rates (Schedule 7 & 8)
ATC Rate Projections through 2028

The details of the calculations for the above are included in the following attachment.

Please submit all information requests or informal challenges to atcrates@atcllc.com.

Trevor Stiles
Director, Customer Engagement

Notice of 2022 True-Up Stakeholder Meeting

ATC will host a teleconference/web-conference to discuss the 2022 True-Up data with stakeholders on June 26, at 1:00 p.m. (CST). During this time, ATC will present the 2022 True-Up data in detail and interested parties will have an opportunity to discuss the information. The information that will be shared during this time is available in the following presentation.

Participation information for Microsoft Teams is as follows:

To join the web conference on your computer or mobile app, click HERE.

If you are unable to join via the web conference, you can also join by audio only. Enter phone number and conference ID below.
Phone Number:+1 262-771-0437
Conference ID: 858926755#

Please submit all information requests or informal challenges to atcrates@atcllc.com.

ATC 2022 True-Up Data Available
ATC released its 2022 Actual Network Revenue Requirement Calculation and Reconciliation to Actual Billed Network Revenues ("True-Up") on May 30, 2023. The actual network revenue requirement was approximately $2.7 million lower than the forecasted revenue requirement that was billed in 2022. The details of the calculation are included in the following attachment.

Please submit all information requests or informal challenges to atcrates@atcllc.com.

ATC Formula Rate Protocol Informational Filing - 3/10/23
On March 08, 2023, American Transmission Company LLC submitted an Informational Filing, docket number ER23-1267-000, comprised of a letter and supporting materials ("Informational Filing") that reflect American Transmission's projected net revenue requirement effective January 1, 2023 and American Transmission's 2021 Annual True-Up under Attachment O of the MISO Tariff.

2023 Budget - Update 02/17/23

ATC has reposted its "Rate Projections" through 2026, its projected 2023 Point-to-Point Rates (Schedules 7 & 8) and Attachment O (Schedule 9). These changes are due to updated coincident load data received from its customers. The load change does not result in a change to ATC's projected annual revenue requirement.

Rate Formula (Attachment O)
2023 Transmission Service Rates (Schedule 7 & 8)
ATC Rate Projections through 2026

The details of the calculations for the above are included in the following attachment.

Budget 2023 - Update 10/5/22

As indicated in the previous budget posting, the 2023 budget presentation that will be reviewed on October 13, 2022 is now available.

Budget Presentation

Trevor Stiles
Director, Customer Engagement

Budget 2023

ATC will host a stakeholder meeting to discuss the 2023 Budget on Thursday, October 13, 2022 at 1:00 p.m. (CDT). The 2023 Budget will be presented in detail and stakeholders will have an opportunity to discuss the budget information. We encourage you to extend this invitation to all appropriate staff in your organization. This meeting is offered as a teleconference/web meeting only.

Participation information for Microsoft Teams is as follows:

To join the web conference on your computer or mobile app, click HERE.

If you are unable to join via the web conference, you can also join by audio only. Enter phone number and conference ID below.
Phone Number:+1 608-620-9719
Conference ID: 314 700 904#

All available information on the 2023 Budget and Rates has been posted below to provide interested parties with an equal opportunity to review the documents.

Rate Formula (Attachment O)
2023 Attachment GG
2023 Attachment MM
ATC Schedule 1
2023 Transmission Service Rates (Schedule 7 & 8)
ATC Rate Projections through 2026

The details of the calculations for the above are included in the following attachment.

Please note that the Budget Presentation reviewed during this call will be posted prior to the stakeholder meeting.

Please submit all information requests or informal challenges to atcrates@atcllc.com.

Trevor Stiles
Director, Customer Engagement

Notice of 2021 True-Up Stakeholder Meeting

ATC will host a teleconference/web-conference to discuss the 2021 True-Up data with stakeholders on Thursday, June 30, at 10:30 a.m. (CST). During this time, ATC will present the 2021 True-Up data in detail and interested parties will have an opportunity to discuss the information. The information that will be shared during this time is available in the following presentation.

Participation information for Microsoft Teams is as follows:

To join the web conference on your computer or mobile app, click HERE.

If you are unable to join via the web conference, you can also join by audio only. Enter phone number and conference ID below.
Phone Number:+1 608-620-9719
Conference ID: 890343120#

Please submit all information requests or informal challenges to atcrates@atcllc.com.

ATC 2021 True-Up Data Available
ATC released its 2021 Actual Network Revenue Requirement Calculation and Reconciliation to Actual Billed Network Revenues ("True-Up") on May 26, 2022. The actual network revenue requirement was approximately $6.2 million lower than the forecasted revenue requirement that was billed in 2021. The details of the calculation are included in the following attachment.

Please submit all information requests or informal challenges to atcrates@atcllc.com.

ATC Formula Rate Protocol Informational Filing - 3/14/22
On March 10, 2022, American Transmission Company LLC submitted an Informational Filing, docket number ER22-1260-000, comprised of a letter and supporting materials ("Informational Filing") that reflect American Transmission's projected net revenue requirement effective January 1, 2022 and American Transmission's 2020 Annual True-Up under Attachment O of the MISO Tariff.

2022 Budget Update - 01/20/22
ATC has reposted "Rate Projections" through 2025, projected 2022 Point-to-Point Rates (Schedules 7 & 8) and Attachment O (Schedule 9). These changes are due to updates to the coincident load data received from our customers. The load change does not result in a change to ATC's projected annual revenue requirement.

Rate Formula (Attachment O)
2022 Transmission Service Rates (Schedule 7 & 8)
ATC Rate Projections through 2025

The details of the calculations for the above are included in the following attachment.

2022 Budget

ATC will host a stakeholder meeting to discuss the 2022 Budget on Wednesday, October 13, 2021 at 11:00 a.m. (CDT). The 2022 Budget will be presented in detail and stakeholders will have an opportunity to discuss the budget information. We encourage you to extend this invitation to all appropriate staff in your organization. This meeting is offered as a teleconference/web meeting only.

Participation information for Microsoft Teams is as follows:

To join the web conference on your computer or mobile app, click HERE.

If you are unable to join via the web conference, you can also join by audio only. Enter phone number and conference ID below.
Phone Number:+1 608-620-9719
Conference ID: 663313459#

All available information on the 2022 Budget and Rates has been posted below to provide interested parties with an equal opportunity to review the documents.

Budget Presentation
Rate Formula (Attachment O)
2022 Attachment GG
2022 Attachment MM
ATC Schedule 1
2022 Transmission Service Rates (Schedule 7 & 8)
ATC Rate Projections through 2025

The details of the calculations for the above are included in the following attachment.

Please submit all information requests or informal challenges to atcrates@atcllc.com.

Tom Finco
Vice President, External Affairs

Notice of 2020 True-Up Stakeholder Meeting

ATC will host a teleconference/web-conference to discuss the 2020 True-Up data with stakeholders on Thursday, August 19, at 12:00 p.m. (CST). During this time, ATC will present the 2020 True-Up data in detail and interested parties will have an opportunity to discuss the information. The information that will be shared during this time is available in the following presentation.

Participation information for Microsoft Teams is as follows:

To join the web conference on your computer or mobile app, click HERE.

If you are unable to join via the web conference, you can also join by audio only. Enter phone number and conference ID below.
Phone Number:+1 608-620-9719
Conference ID: 931596837#

Please submit all information requests or informal challenges to atcrates@atcllc.com.

ATC 2020 True-Up Data Available
ATC released its 2020 Actual Network Revenue Requirement Calculation and Reconciliation to Actual Billed Network Revenues ("True-Up") on May 27, 2021. The actual network revenue requirement was approximately $4.9 million lower than the forecasted revenue requirement that was billed in 2020. The details of the calculation are included in the following attachment.

Please submit all information requests or informal challenges to atcrates@atcllc.com.

ATC Formula Rate Protocol Informational Filing - 3/11/21
On March 10, 2021, American Transmission Company LLC submitted an Informational Filing, docket number ER21-1311-000, comprised of a letter and supporting materials ("Informational Filing") that reflect American Transmission's projected net revenue requirement effective January 1, 2021 and American Transmission's 2019 Annual True-Up under Attachment O of the MISO Tariff.

2021 Budget

ATC will host a stakeholder meeting to discuss the 2021 Budget on Tuesday, October 13, 2020 at 10:00 a.m. (CDT). The 2021 Budget will be presented in detail and stakeholders will have an opportunity to discuss the budget information. We encourage you to extend this invitation to all appropriate staff in your organization. This meeting is offered as a teleconference/web meeting only.

Participation information is as follows:

Teleconference Information:
Call-in Number: 888-330-1716
Access Code: 7142569198

Web-conference Information:
Web Meeting Address: https://www.webmeeting.att.com
Meeting Number: 8883301716
Access Code: 7142569198

All available information on the 2021 Budget and Rates has been posted below to provide interested parties with an equal opportunity to review the documents.

Budget Presentation
Rate Formula (Attachment O)
2021 Attachment GG
2021 Attachment MM
ATC Schedule 1
2021 Transmission Service Rates (Schedule 7 & 8)
ATC Rate Projections through 2024

The details of the calculations for the above are included in the following attachment.

Please submit all information requests or informal challenges to atcrates@atcllc.com.

Tom Finco
Vice President, External Affairs

Notice of 2019 True-Up Stakeholder Meeting

ATC will host a teleconference/web-conference to discuss the 2019 True-Up data with stakeholders on Thursday, August 20, at 10:30 a.m. (CST). During this time, ATC will present the 2019 True-Up data in detail and interested parties will have an opportunity to discuss the information. The information that will be shared during this time is available in the following presentation.

Participation information is as follows:

Teleconference Information:
Call-in Number: 888-330-1716
Access Code: 7142569198

Web-conference Information:
Web Meeting Address: https://www.webmeeting.att.com
Meeting Number: 8883301716
Access Code: 7142569198

Please submit all information requests or informal challenges to atcrates@atcllc.com.

ATC 2019 True-Up Data Available
ATC released its 2019 Actual Network Revenue Requirement Calculation and Reconciliation to Actual Billed Network Revenues ("True-Up") on May 27, 2020. The actual network revenue requirement was approximately $0.7 million higher than the forecasted revenue requirement that was billed in 2019. The details of the calculation are included in the following attachment.

Please submit all information requests or informal challenges to atcrates@atcllc.com.

ATCFormula Rate Protocol Informational Filing - 3/12/20
On March 10, 2020, American Transmission Company LLC submitted an Informational Filing, docket number ER20-1234-000, comprised of a letter and supporting materials ("Informational Filing") that reflect American Transmission's projected net revenue requirement effective January 1, 2020 and American Transmission's 2018 Annual True-Up under Attachment O of the MISO Tariff.

2020 Budget Update - 12/18/19
ATC has reposted its projected 2020 Attachment O, GG (Schedule 26), MM (Schedule 26-A), Transmission Service Rates (Schedule 7 & 8), and Rate Projections through 2023 to reflect the order received from FERC on November 21, 2019. This order, Opinion No. 569, was issued in Docket Nos. EL12-14 and EL15-45 and resolved two long-standing FERC complaints challenging the Return on Equity component of ATC's transmission rates. Specifically, Opinion No. 569 authorized a base ROE of 9.88% for ATC that, when combined with the 50bp RTO adder granted by FERC on January 5, 2015, results in a new aggregate ROE for ATC of 10.38%. ATC's previous 2020 rate projections posted had assumed a ROE of 10.82% (inclusive of the 50bp adder).

The 44 BP reduction in ATC's ROE results in an approximate decrease of $12,000,000 to ATC's 2020 projected revenue requirement. The reduction in 2020 rates related to ROE is partially offset by an adjustment for excess deferred tax amortization resulting from the ROE refund, as required by IRS regulations. The change in excess deferred tax amortization results is an increase of $9,600,000 in the 2020 projected revenue requirement. The net impact of the ROE change in ATC's 2020 projected rates is therefore a net decrease of approximately $2,300,000.

ATC made two changes in addition to the changes related to ATC's compliance with Opinion No. 569. First, ATC revised its projected Attachment GG to exclude Project 17525 (J870/J871 GIC Highland Generator Interconnection Facilities and Network Upgrades). It has been determined that this project will not qualify for regional cost sharing in 2020. This results in a decrease of approximately $15,000 from the revenue requirement calculated under Attachment GG and an increase in the net revenue requirement (Network/Schedule 9) on Attachment O. Second, ATC revised Rate Projections through 2023 for Schedules 9 (Network) and 7 & 8 (Point-to-Point Rates) due to updated coincident load data received from its customers. The load change does not result in a change to ATC's projected 2020 annual revenue requirement.

Rate Formula (Attachment O)
2020 Attachment GG
2020 Attachment MM
2020 Transmission Service Rates (Schedule 7 & 8)
ATC Rate Projections through 2023

The details of the calculations for the above are included in the following attachment.

2020 Budget Update - 10/24/19
ATC has reposted its 2020 Attachments GG and MM due to a minor change in the allocation of the 2018 true-up to individual projects. The 2020 total annual revenue requirement for Attachments GG and MM has not changed from what was posted on October 1, 2019.

2020 Attachment GG
2020 Attachment MM

The details of the calculations for the above are included in the following attachment.

ATC Response to 2020 Budget Information Request - 10/11/19

On October 11, 2019, Alliant Energy inquired as to details of ATC's 2020 projected budget and rates. ATC's response to this inquiry is included in the following attachment.

2020 Budget

ATC will host a stakeholder meeting to discuss the 2020 Budget on Tuesday, October 8, 2019 at 10:00 a.m. (CDT). The 2020 Budget will be presented in detail and stakeholders will have an opportunity to discuss the budget information. We encourage you to extend this invitation to all appropriate staff in your organization. This meeting is offered as a teleconference/web meeting only.

Participation information is as follows:

Teleconference Information:
Call-in Number: 888-330-1716
Access Code: 7142569198

Web-conference Information:
Web Meeting Address: https://www.webmeeting.att.com
Meeting Number: 8883301716
Access Code: 7142569198

All available information on the 2020 Budget and Rates has been posted below to provide interested parties with an equal opportunity to review the documents.

Budget Presentation
Rate Formula (Attachment O)
2020 Attachment GG
2020 Attachment MM
ATC Schedule 1
2020 Transmission Service Rates (Schedule 7 & 8)
ATC Rate Projections through 2023

The details of the calculations for the above are included in the following attachment.

Please submit all information requests or informal challenges to atcrates@atcllc.com.

Tom Finco
Vice President, External Affairs

Notice of 2018 True-Up Stakeholder Meeting

ATC will host a teleconference/web-conference to discuss the 2018 True-Up data with stakeholders on Wednesday, June 19, at 9:30 a.m. (CST). During this time, ATC will present the 2018 True-Up data in detail and interested parties will have an opportunity to discuss the information. The information that will be shared during this time is available in the following presentation.

Participation information is as follows:
Teleconference Information:
Call-in Number:888-330-1716
Access Code: 7142569198

Web-conference Information:
Web Meeting Address: https://www.webmeeting.att.com
Meeting Number: 8883301716
Access Code: 7142569198

Please submit all information requests or informal challenges to atcrates@atcllc.com.

ATC 2018 True-Up Data Available

ATC released its 2018 Actual Network Revenue Requirement Calculation and Reconciliation to Actual Billed Network Revenues (“True-Up”) on May 28, 2019. The actual network revenue requirement was approximately $9.9 million less than the forecasted revenue requirement that was billed in 2018. The details of the calculation are included in the following attachment.

Please submit all information requests or informal challenges to atcrates@atcllc.com.

ATC Formula Rate Protocol Informational Filing - 3/11/19

On March 11, 2019, American Transmission Company LLC submitted an Informational Filing, docket number ER19-1236-000, comprised of a letter and supporting materials (“Informational Filing”) that reflect American Transmission’s projected net revenue requirement effective January 1, 2019 and American Transmission’s 2017 Annual True-Up under Attachment O of the MISO Tariff.

ATC Response to 2019 Budget Information Request - 10/16/18

On October 4, 2018, WPPI Energy inquired as to details of ATC's 2019 projected budget and rates. ATC's response to this inquiry is included in the following attachment.

2019 Budget Update - 10/10/18

ATC has reposted its 2019 Attachments GG (Schedule 26) and MM (Schedule 26-A) due to a minor change in the true-up amounts allocated to individual projects. The 2019 total annual revenue requirement for Attachments GG and MM is unchanged from the October 1, 2018 posted amounts.

2019 Attachment GG
2019 Attachment MM

The details of the calculations for the above are included in the following attachment.

Additionally, ATC has reposted the 2018 Transmission Service Rates and the 2019 Budget Presentation as shown below due to a rounding correction of the 2019 projected network revenue requirement.

Budget Presentation
2019 Transmission Service Rates (Schedule 7 & 8)

Please submit all information requests or informal challenges to atcrates@atcllc.com.

Revised ATC 2017 True-Up Data - 10/10/18

ATC has reposted its 2017 Attachments GG (Schedule 26) and MM (Schedule 26-A) due to a minor change in the 2015 true-up amounts allocated to individual projects. The 2017 total true-up for Attachments GG and MM is unchanged from the previously posted amounts. The details of the calculation are included in the following attachment.

2019 Budget

ATC will host a stakeholder meeting to discuss the 2019 Budget on Thursday, October 11, 2018 at 10:00 a.m. (CDT). The 2019 Budget will be presented in detail and stakeholders will have an opportunity to discuss the budget information. We encourage you to extend this invitation to all appropriate staff in your organization. This meeting is offered as a teleconference/web meeting only.

Participation information is as follows:

Teleconference Information:
Call-in Number: 888-330-1716
Access Code: 7142569198

Web-conference Information:
Web Meeting Address: https://www.webmeeting.att.com
Meeting Number: 8883301716
Access Code: 7142569198

All available information on the 2019 Budget and Rates has been posted below to provide interested parties with an equal opportunity to review the documents.

Budget Presentation
Rate Formula (Attachment O)
2019 Attachment GG
2019 Attachment MM
ATC Schedule 1
2019 Transmission Service Rates (Schedule 7 & 8)
ATC Rate Projections through 2022

The details of the calculations for the above are included in the following attachment.

Please submit all information requests or informal challenges to atcrates@atcllc.com.

Tom Finco
Vice President, External Affairs

Revised ATC 2017 True-Up Data - 6/25/18

ATC has reposted its 2017 Actual Network Revenue Requirement Calculation and Reconciliation to Actual Billed Network Revenues (“True-up”) to correct for an immaterial and insignificant reclassification between network and Schedule 26 revenues. The network revenue true-up was revised from $2.088 million to $2.060 million. The details of the calculation are included in the following attachment.

Notice of 2017 True-Up Stakeholder Meeting

ATC will host a teleconference/web-conference to discuss the 2017 True-Up data with stakeholders on Monday, June 25, at 9:30 a.m. (CST). During this time, ATC will present the 2017 True-Up data in detail and interested parties will have an opportunity to discuss the information. The information that will be shared during this time is available in the following presentation.

Participation information is as follows:
Teleconference Information:
Call-in Number: 888-330-1716
Access Code: 7142569198

Web-conference Information:
Web Meeting Address: https://www.webmeeting.att.com
Meeting Number: 8883301716
Access Code: 7142569198

Please submit all information requests or informal challenges to atcrates@atcllc.com.

ATC 2017 True-Up Data Available

ATC released its 2017 Actual Network Revenue Requirement Calculation and Reconciliation to Actual Billed Network Revenues (“True-Up”) on May 31, 2018. The actual network revenue requirement was approximately $2.1 million more than the forecasted revenue requirement that was billed in 2017. The details of the calculation are included in the following attachment.

Please submit all information requests or informal challenges to atcrates@atcllc.com.

ATC Formula Rate Protocol Informational Revised Filing - 4/12/18

Due to the lowered corporate tax rate implemented in the Tax Cuts and Jobs Act, American Transmission Company LLC resubmitted the Information Filing, docket number ER 18-989-001, comprised of a letter and supporting materials (“Informational Filing”) that reflect American Transmission’s projected net revenue requirement effective January 1, 2018 and American Transmission’s 2016 Annual True-Up under Attachment O of the MISO Tariff.

2018 Budget - Update 4/6/18

American Transmission Co. received permission from the Federal Energy Regulatory Commission to modify certain provisions of the Midcontinent Independent System Operator Tariff, which determines how transmission customers are charged for transmission services. The waiver granted by FERC allows transmission customers to benefit sooner from the lowered corporate tax rate implemented in the Tax Cuts and Jobs Act, which reduced corporate tax rates from 35 percent to 21 percent. As a result, the following information has been updated to reflect the impact of the lowered corporate tax rate:

Rate Formula (Attachment O)
2018 Attachment GG
2018 Attachment MM
2018 Transmission Service Rates (Schedule 7 & 8)
ATC Rate Projections through 2022

The details of the calculations for the above are included in the following attachment.

Please submit all information requests or informal challenges to atcrates@atcllc.com.

Tom Finco
Vice President, External Affairs

ATC Formula Rate Protocol Informational Filing - 3/12/18

On March 12, 2018, American Transmission Company LLC submitted an Informational Filing, docket number ER18-989-000, comprised of a letter and supporting materials (“Informational Filing”) that reflect American Transmission’s projected net revenue requirement effective January 1, 2018 and American Transmission’s 2016 Annual True-Up under Attachment O of the MISO Tariff.

ATC Response to 2018 Budget Information Request - 11/14/17

On October 27, 2017, WEC Energy Group inquired as to details of ATC's 2018 projected budget and rates. ATC's response to this inquiry is included in the following attachment.

ATC Response to 2018 Budget Information Request - 10/26/17

On October 11, 2017 and October 12, 2017, WEC Energy Group inquired as to details of ATC's 2018 projected budget and rates. ATC's response to this inquiry is included in the following attachment.

ATC Response to 2018 Budget Information Request - 10/12/17

Following ATC's stakeholder meeting to discuss the 2018 Budget on Tuesday, October 10, 2017, ATC is providing a response to an inquiry in the following attachment.

2018 Budget

ATC will host a stakeholder meeting to discuss the 2018 Budget on Tuesday, October 10, 2017 at 10:00 a.m. (CDT). The 2018 Budget will be presented in detail and stakeholders will have an opportunity to discuss the budget information. We encourage you to extend this invitation to all appropriate staff in your organization. This meeting is offered as a teleconference/web meeting only.

Participation information is as follows:

Teleconference Information:
Call-in Number: 888-330-1716
Access Code: 7142569198

Web-conference Information:
Web Meeting Address: https://www.webmeeting.att.com
Meeting Number: 8883301716
Access Code: 7142569198

All available information on the 2018 Budget and Rates has been posted below to provide interested parties with an equal opportunity to review the documents.

Budget Presentation
Rate Formula (Attachment O)
2018 Attachment GG
2018 Attachment MM
ATC Schedule 1
2018 Transmission Service Rates (Schedule 7 & 8)
ATC Rate Projections through 2022

The details of the calculations for the above are included in the following attachment.

Please submit all information requests or informal challenges to atcrates@atcllc.com.

Tom Finco
Vice President, External Affairs

Notice of 2016 True-Up Data and Stakeholder Meeting

ATC will host a teleconference/web-conference to discuss the 2016 True-Up data with stakeholders on Tuesday, July 18, at 10:30 a.m. (CST). During this time, ATC will present the 2016 True-Up data in detail and interested parties will have an opportunity to discuss the information. The information that will be shared during this time is available in the following presentation.

Participation information is as follows:
Teleconference Information:
Call-in Number: 888-330-1716
Access Code: 7142569198

Web-conference Information:
Web Meeting Address: https://www.webmeeting.att.com
Meeting Number: 8883301716
Access Code: 7142569198

Please submit all information requests or informal challenges to atcrates@atcllc.com.

ATC 2016 True-Up Data Available

ATC released its 2016 Actual Network Revenue Requirement Calculation and Reconciliation to Actual Billed Network Revenues (“True-Up”) on May 31, 2017. The actual network revenue requirement was approximately $7.4 million less than the forecasted revenue requirement that was billed in 2016. The details of the calculation are included in the following attachment.

Please submit all information requests or informal challenges to atcrates@atcllc.com.

ATC Formula Rate Protocol Informational Filing - 3/16/17
On March 14, 2017, American Transmission Company LLC submitted an Informational Filing, docket number ER17-1209-000, comprised of a letter and supporting materials (“Informational Filing”) that reflect American Transmission’s projected net revenue requirement effective January 1, 2017 and American Transmission’s 2015 Annual True-Up under Attachment O of the MISO Tariff.

2015 True-Up Data Update - 10/28/16
ATC has reposted its 2015 Attachment MM (Schedule 26-A) True-up with a minor revision. This revision is limited to the allocation of the 2013 true-up by project. The total annual adjusted revenue requirement of $2.7 million is unchanged and the correction has no impact on the calculation of Schedule 26-A rates. Allocation of the 2013 true-up to project 2844 is $(188,019) rather than $238,910 and to project 3127 is $(4,349,970) rather than $(4,776,898).

2015 Attachment O GG MM

ATC Response to 2017 Budget Information Request - 10/18/16

Following ATC's stakeholder meeting to discuss the 2017 Budget on Tuesday, October 11, 2016, ATC is providing responses to inquiries made during and after the meeting in the following attachment.

2017 Budget Update - 10/10/16

As indicated in the previous budget posting, the 2017 budget presentation that will be reviewed on October 11, 2016 is now available.

Budget Presentation

Tom Finco
Vice President, External Affairs

2017 Budget

ATC will host a stakeholder meeting to discuss the 2017 Budget on Tuesday, October 11, 2016 at 9:30 a.m. (CDT). The 2017 Budget will be presented in detail and stakeholders will have an opportunity to discuss the budget information. We encourage you to extend this invitation to all appropriate staff in your organization. This meeting is offered as a teleconference/web meeting only.

Participation information is as follows:

Teleconference Information:
Call-in Number: 888-330-1716
Access Code: 7142569198

Web-conference Information:
Web Meeting Address: https://www.webmeeting.att.com
Meeting Number: 8883301716
Access Code: 7142569198

All available information on the 2017 Budget and Rates has been posted below to provide interested parties with an equal opportunity to review the documents.

Rate Formula (Attachment O)
2017 Attachment GG
2017 Attachment MM
ATC Schedule 1
2017 Transmission Service Rates (Schedule 7 & 8)
ATC Rate Projections through 2021

The details of the calculations for the above are included in the following attachment.

Please note that the Budget Presentation reviewed during this call will be posted prior to the stakeholder meeting.

Please submit all information requests or informal challenges to atcrates@atcllc.com.

Tom Finco
Vice President, External Affairs

ATC Response to 2015 True-Up Data Information Requests - 6/9/16

During the stakeholder meeting on 06/07/2016 to review ATC’s 2015 network true-up information, WEC Energy Group inquired about an update on a past matter, where discrepancies existed between ATC’s and MISO’s projections of Schedule 26 charges. The response from ATC during the meeting was that this variance has not been an issue recently. The drivers contributing to the variance between the ATC and MISO projections in the past included that a growing proportion of Schedule 26 charges in the ATC footprint were being contributed to by other MISO TOs and ATC and MISO used differing methodologies to calculate their projections. Over time, MISO has revised its approach, resulting in more-accurate projections of Schedule 26.

Notice of 2015 True-Up Data and Stakeholder Meeting

ATC released its 2015 Actual Network Revenue Requirement Calculation and Reconciliation to Actual Billed Network Revenues (“True-Up”) on May 26, 2016. The actual network revenue requirement was approximately $0.9 million less than the forecasted revenue requirement that was billed in 2015. The details of the calculation are included in the following attachment. ATC will host a teleconference/web-conference to discuss the 2015 True-Up data with stakeholders on Tuesday, June 7, 2016 at 11:00 a.m. (CST). During this time, ATC will present the 2015 True-Up data in detail and interested parties will have an opportunity to discuss the information. The information that will be shared during this time is available in the following presentation.

Participation information is as follows:

Teleconference Information:
Call-in Number: 888-330-1716
Access Code: 7142569198

Web-conference Information:
Web Meeting Address: https://www.webmeeting.att.com
Meeting Number: 8883301716
Access Code: 7142569198

Please submit all information requests or informal challenges to atcrates@atcllc.com.

ATC Formula Rate Protocol Informational Filing - 3/14/16

On March 11, 2016, American Transmission Company LLC submitted an Informational Filing, docket number ER16-1149, comprised of a letter and supporting materials (“Informational Filing”) that reflect American Transmission’s projected net revenue requirement effective January 1, 2016 and American Transmission’s 2014 Annual True-Up under Attachment O of the MISO Tariff.

2016 Budget Update - 1/25/16

ATC has reposted its “Rate Projections” through 2020 to correct the coincident load projections and projected rates indicated for 2017-2020 that were posted on 1/6/16 to reflect the annual 0.65% load growth assumption. The change does not impact ATC’s 2016 rate projection or the projected annual revenue requirement, nor the projected revenue requirements for 2017-2020.

ATC Rate Projections through 2020

2016 Budget Update - 1/6/16

ATC has reposted its “Rate Projections” through 2020, its projected 2016 Point-to-Point Rates (Schedules 7 & 8) and Attachment O (Schedule 9). These changes are due to updated coincident load data received from its customers. The load change does not result in a change to ATC’s projected annual revenue requirement.

Rate Formula (Attachment O)
2016 Transmission Service Rates (Schedule 7 & 8)
ATC Rate Projections through 2020

The details of the calculations for the above are included in the following attachment.

ATC Response to 2016 Budget Information Request - 11/04/15

On Nov. 3, 2015, Alliant Energy inquired as to details of ATC's 2016 projected budget and rates. ATC's response to this inquiry is included in the following attachment.

ATC Response to 2016 Budget Information Request - 10/16/15

During the stakeholder meeting on October 13, 2015 to discuss the 2016 projected annual revenue requirement and budget, Wisconsin Public Service inquired about the $2.6 million under-collection that is shown in the “2016 Budget” column on slide 20 of the presentation and what was driving that amount (this amount is also reflected on slide 5). ATC responded by indicating that this amount is composed of three sources. First, there is a refund of $1.8 million from the 2014 over-collection of Schedule 9 (Network Integration Transmission Service) revenues. The total 2014 over-collection was $6.8 million. The company had projected a $5 million over-collection at the end of 2014 (a practice we use to accommodate MISO billing processes) and we refunded that amount in the 2015 Network Service rate. Second, in 2014, it was discovered that ATC inadvertently recovered $3.9 million of costs for three 138/69 kV transformers that were part of a Baseline Reliability Project (Project #352) between 2009 and 2013 through Schedule 26 (RECB) instead of Schedule 9. This requires refunding Schedule 26 customers about $4.6 million (inclusive of interest) and then charging approximate $4 million to ATC’s Network customers through Schedule 9 (inclusive of interest). The third source is that ATC inadvertently recovered through Schedule 26 rather than Schedule 9 $500,000 in depreciation expense for a group of Generator Interconnection Projects (Project #s 1616, 2452/3160, 2837, and 2793) between 2010 and 2014. This was discovered in 2015 and requires ATC to refund Schedule 26 by this amount, which will then be charged to Schedule 9. Note that both the Project #352 and GIP corrections – and corresponding offsets between Schedules 9 and 26 – have a minimal impact to our Network customers as almost all of the amounts that will be refunded under Schedule 26 will be received by ATC Network customers. The calculations for the two corrections are described in the workpapers for the projected 2015 revenue requirement that were posted on OASIS on September 30, 2015.

ATC Response to 2016 Budget Information Request - 10/08/15

On October 6, 2015, We-Energies posed the following questions to ATC: “Given all the pending complaints on ROE, could ATC please address its perspective on the magnitude of the dollar impacts. Has ATC calculated the effect of an 8%, 9% or 10% (or other variable) ROE? If so, can this information be shared?” ATC on October 7, 2015 responded by indicating that though ATC is affirmatively defending our current 12.2% return on equity (ROE), the company estimates that in the event the ROE is reduced as a result of the two pending FPA Sec. 206 complaints filed at the Federal Energy Regulatory Commission (dockets EL14-12 and EL15-45), the company’s annual revenue requirement would be reduced by $2.5 million for every 10 basis point reduction.

2016 Budget

ATC will host a stakeholder meeting to discuss the 2016 Budget on Tuesday, October 13, 2015 at 1:00 p.m. (CDT). The 2016 Budget will be presented in detail and stakeholders will have an opportunity to discuss the budget information. We encourage you to extend this invitation to all appropriate staff in your organization. This meeting is offered as a teleconference/web meeting only.

Participation information is as follows:

Teleconference Information:
Call-in Number: 888-330-1716
Access Code: 7142569198

Web-conference Information:
Web Meeting Address: https://www.webmeeting.att.com
Meeting Number: 8883301716
Access Code: 7142569198

Please submit all information requests or informal challenges to atcrates@atcllc.com.

All available information on the 2016 Budget and Rates has been posted below to provide interested parties with an equal opportunity to review the documents.

Budget Presentation
Rate Formula (Attachment O)
2016 Attachment GG
2016 Attachment MM
ATC Schedule 1
2016 Transmission Service Rates (Schedule 7 & 8)
ATC Rate Projections through 2020

The details of the calculations for the above are included in the following attachment.

Tom Finco
Vice President, External Affairs

ATC Response to 2014 True-Up Data Information Requests - 6/10/15

During the stakeholder meeting on 6/10/15 to review ATC’s 2014 true-up information, Wisconsin Public Service inquired if the $538.3 million shown in column B of slide 5 of the meeting presentation was the Network revenue requirement actually billed in 2014. The response from ATC during the meeting was that about $528 million was actually billed in 2014 because the $538.3 million was offset by prior year true-ups (a $2.1 million under-collection from 2012 and $12.4 million over-collection from 2013).

Following the stakeholder meeting on 6/10/15 to review ATC’s 2014 true-up information, Madison Gas & Electric inquired as to the nexus between the 2014 true-up and the outcomes of two pending Federal Power Act Sec. 206 complaints that have been filed at the Federal Energy Regulatory Commission (FERC) against ATC’s and other MISO transmission owners’ return on equity (ROE) for investment in electric transmission. ATC responded to Madison Gas & Electric on 6/12/15 that the $6.5 million over-collection reflected in the 2014 Network true-up calculation will not be directly impacted by the outcome of the two pending ROE complaints. This amount will offset customers’ Network rates in 2015 and 2016, with most of that offset likely occurring before a final decision is reached by FERC in the ROE complaint proceedings. ATC anticipates that any adjustment to its ROE, such as in the form of a refund, will be handled separately in accordance with FERC orders addressing those complaints (in dockets EL14-12 and EL15-45)..

Notice of 2014 True-Up Data Stakeholder Meeting

ATC will host a teleconference/web-conference to discuss the 2014 True-Up data with stakeholders on Wednesday, June 10, 2015 at 1:00 p.m. (CST). During this time, ATC will present the 2014 True-Up data in detail and interested parties will have an opportunity to discuss the information. The presentation that will be shared during this time is available in the following attachment.

Participation information is as follows:

Teleconference Information:
Call-in Number: 888-330-1716
Access Code: 7142569198

Web-conference Information:
Web Meeting Address: https://www.webmeeting.att.com
Meeting Number: 8883301716
Access Code: 7142569198

ATC 2014 True-Up Data Available

ATC released its 2014 Actual Network Revenue Requirement Calculation and Reconciliation to Actual Billed Network Revenues (“True-Up”) on May 28, 2015. The actual network revenue requirement was approximately $6.5 million less than the forecasted revenue requirement that was billed in 2014. The details of the calculation are included in the following attachment.

Please submit all information requests or informal challenges to atcrates@atcllc.com.

ATC Formula Rate Protocol Informational Filing - 3/13/15

On March 13, 2015, American Transmission Company LLC submitted an Informational Filing, docket number ER15-1262, comprised of a letter and supporting materials (“Informational Filing”) that reflect American Transmission’s projected net revenue requirement effective January 1, 2015 and American Transmission’s 2013 Annual True-Up under Attachment O of the MISO Tariff.

2015 Budget Update - 1/8/15

ATC has reposted its “Rate Projections” through 2019, its projected 2015 Point-to-Point Rates (Schedules 7 & 8) and Attachment O (Schedule 9). These changes are due to updated coincident load data received from its customers. The load change does not result in a change to ATC’s projected annual revenue requirement.

Rate Formula (Attachment O)
2015 Transmission Service Rates (Schedule 7 & 8)
ATC Rate Projections through 2019

The details of the calculations for the above are included in the following attachment.

ATC Response to 2015 Budget Information Request - 1/5/15
On December 18, 2014, WPPI Energy requested the allocation of costs to each transmission pricing zone determined by MISO for ATC’s projects that have costs recovered under Attachment GG-ATCLLC. On January 5, 2015, ATC provided WPPI Energy with the requested information in the following attachment.

ATC Response to 2015 Budget Information Request - 11/13/14

On October 27, 2014, Alliant Energy inquired as to details of ATC's 2015 projected budget and rates. ATC's response to this inquiry is included in the following attachment.

2015 Budget Update - 10/24/14

ATC has reposted its projected 2015 Attachment MM (Schedule 26-A) with a minor revision. This revision is limited to the allocation of the 2013 true-up by project. The total annual adjusted revenue requirement of $6.0 million is unchanged and the correction will not impact the calculation of Schedule 26-A rates.

2015 Attachment MM

The details of the calculations for the above are included in the following attachment.

ATC Response to 2015 Budget Information Request - 10/20/14

During the Oct. 16, 2015 MISO TO Joint Regional Cost Sharing Informational Meeting, the Illinois Commerce Commission inquired about the cause of the 2013 Attachment MM true-up of $4,537,989. ATC responded that a factor driving this was that when ATC developed the 2013 projected annual revenue requirement for the Cardinal – Eden – Hickory Creek line, it was assumed that the company would be constructing 100% of the project. On Feb. 7, 2013, FERC issued an order in docket EL13-13 requiring ATC to share ownership of the project equally with ITC-Midwest. Given this development, ATC’s revenue requirement for the project was reduced, thus resulting in an over-collection that will be trued-up, inclusive of interest, in 2015 rates.

ATC Response to 2015 Budget Information Request - 10/10/14

On October 9, 2014, during the stakeholder meeting on 2015 projected budget and rates, Wisconsin Public Service inquired as to the Discounted Cash Flow (DCF) methodology used in the FERC June 19, 2014 order in NE-ISO ROE complaint case. WPS also inquired as to the schedules of some of ATC's major capital projects. ATC's response to these inquiries is included in the following attachment.

ATC Response to 2015 Budget Information Request - 10/07/14

On October 3, 2014, Wisconsin Public Service inquired as to ATC's 2015 projected budget and rates regarding MISO Schedule 33 costs. ATC's response to this inquiry is included in the following attachment.

2015 Budget

ATC will host a stakeholder meeting to discuss the 2015 Budget on Thursday, October 9, 2014, 1:00 - 2:00 p.m. (CDT). The 2015 Budget will be presented in detail and stakeholders will have an opportunity to discuss the budget information. We have planned this single meeting for review of the budget materials to meet the needs of all stakeholders. This meeting will be very comprehensive and we encourage you to extend this invitation to all appropriate staff in your organization. This meeting is offered as a teleconference/web meeting only.

Participation information is as follows:

Teleconference Information:
Call-in Number: 888-330-1716
Access Code: 1834529

Web-conference Information:
Web Meeting Address: https://www.webmeeting.att.com
Meeting Number: 8883301716
Access Code: 1834529

Please submit all information requests or informal challenges to atcrates@atcllc.com.

All available information on the 2015 Budget and Rates has been posted below to provide interested parties with an equal opportunity to review the documents.

Budget Presentation
Rate Formula (Attachment O)
2015 Attachment GG
2015 Attachment MM
2015 Schedule 1
2015 Transmission Service Rates (Schedule 7 & 8)
ATC Rate Projections through 2019

The details of the calculations for the above are included in the following attachment.

Tom Finco
Vice President, External Relations

ATC Response to 2013 True-Up Data Information Request – 8/13/14

On 7/25/14, Alliant Energy posed the following questions, to which ATC on 8/12/14 provided the following responses in the attachment.

ATC Response to 2013 True-Up Data Information Request – 7/14/14

On 6/26/14, the Michigan Public Service Commission posed the following questions, to which ATC on 7/14/14 provided the following responses in the attachment.

ATC Response to 2013 True-Up Data Information Request – 7/9/14

During the stakeholder meeting on 7/8/14 to review ATC’s 2013 true-up information, We Energies inquired as to if the $16,689,973 over-collection for Network Service from 2013 will show up as a decrease in revenue requirement for 2015 and reflected in 2015 rates. The response from ATC during the meeting was that $12,048,612, plus accrued interest, is currently being refunded in 2014 Network Service rates, with the remainder to be refunded in 2015, with interest.

Following the stakeholder meeting on 7/8/14 to review ATC’s 2013 true-up information, We Energies inquired as to the $12,048,612, plus accrued interest, to be refunded in 2014 Network Service rates and whether that dollar amount would be spread across several months (concluding within 2014) or would it be a one-time adjustment. Additionally, We Energies inquired as to what month the refund would begin or the adjustment would occur and where on their customer bill the adjustment could be found. The response from ATC on 7/9/14 was that ATC is refunding 1/12th of $12,438,984 ($12,048,612 true-up plus $390,372 of accrued interest) each month to network customers through their Schedule 9 bill in 2014. The true-up is not identified on customer bills, per se, as it is subtracted from the projected amount of annual revenue requirement recovered from Network Service customers, 1/12th of which is billed each month to ATC’s Network Service customers.

ATC Response to 2013 True-Up Data Information Request – 7/2/14

On 7/2/14 Alliant Energy inquired as to how the $16,689,973 over-collection for Network Service from 2013 will be reflected in 2014 rates. The response from ATC on 7/3/14 was that $12,048,612, plus accrued interest, is currently being refunded in 2014 Network Service rates, with the remainder to be refunded in 2015.

2013 ATC True-Up Data Stakeholder Meeting – Update 7/3/14

As indicated in the previous posting, ATC will host a meeting at 10:30 a.m. (CST) on July 8, 2014 to discuss the 2013 True-Up data with interested parties. The presentation that will be shared during this time is available in the following attachment.

Notice of 2013 True-Up Data Stakeholder Meeting

ATC has revised the date on which we will discuss the 2013 True-Up data with stakeholders. ATC will host this teleconference/web-conference on Tuesday, July 8, at 10:30 a.m. (CST). During this time, ATC will present the 2013 True-Up data in detail and interested parties will have an opportunity to discuss the information.

Participation information is as follows:

Teleconference Information:
Call-in Number: 888-330-1716
Access Code: 1834529

Web-conference Information:
Web Meeting Address: https://www.webmeeting.att.com
Meeting Number: 8883301716
Access Code: 1834529

ATC 2013 True-Up Data Available

ATC released its 2013 Actual Network Revenue Requirement Calculation and Reconciliation to Actual Billed Network Revenues (“True-Up”) on May 28, 2014. The actual network revenue requirement was approximately $16.69 million less than the forecasted revenue requirement that was billed in 2013. The details of the calculation are included in the following attachment.

Please submit all information requests or informal challenges to atcrates@atcllc.com.

2014 Budget Update - 1/17/14

ATC has reposted its “Rate Projections” through 2018, its projected 2014 Point-to-Point Rates (Schedules 7 & 8) and Attachment O (Schedule 9). These changes are due to updated coincident load data received from its customers. The load change does not result in any change to ATC’s projected annual revenue requirement.

Rate Formula (Attachment O)
2014 Transmission Service Rates (Schedule 7 & 8)
ATC Rate Projections through 2018

2014 Budget

ATC will host a teleconference/web-conference to discuss the 2014 Budget on Tuesday, October 8, at 10:30 a.m. (CST). The 2014 Budget will be presented in detail and customers will have an opportunity to discuss the budget information. We have planned this single meeting for review of the budget materials to meet the needs of all customers. This meeting will be very comprehensive and we encourage you to extend this invitation to all appropriate staff in your organization. Participation information is as follows.

Teleconference Information:
Call-in Number: 888-330-1716
Access Code: 4003177

Web-conference Information:
Web Meeting Address: https://www.webmeeting.att.com
Meeting Number: 8883301716
Access Code: 4003177

All available information on the 2014 Budget and Rates has been posted below to provide our customers with an equal opportunity to review the documents.

Budget Presentation
Rate Formula (Attachment O)
2014 Attachment GG
2014 Attachment MM
2014 Transmission Service Rates (Schedule 7 & 8)
ATC Rate Projections through 2018

Tom Finco
Vice President, External Relations

ATC 2012 Regional Cost Sharing True-Up Data Available – Update 9/25/13

ATC released its 2012 actual Attachment GG and Attachment MM revenue requirement calculations and reconciliations to actual amounts received (“True-Ups”) on September 25, 2013. The actual Attachment GG revenue requirement was approximately $1.462 million lower than revenues received under Schedule 26 in 2012. On behalf of ATC, MISO will refund this amount, plus interest, through 2014 Schedule 26 billings to regional customers. Additionally, the actual Attachment MM revenue requirement was approximately $4.367 million higher than revenues received under Schedule 26A in 2012. On behalf of ATC, MISO will collect this amount, plus interest, through 2014 Schedule 26A billings to regional customers. The details of both calculations are included in the following attachments:

2012 Attachment GG
2012 Attachment MM

ATC 2013 Billing Procedure

July, 1, 2013: ATC has developed this procedure to describe how it will account for Michigan Retail Choice customers in accordance with the provisions of Attachment T of MISO’s Tariff. ATC has drafted this billing procedure to provide additional information to: (1) Alternative Electric Suppliers (AES) that conduct business in portions of American Transmission’s footprint that are subject to Michigan’s Retail Choice; and (2) incumbent Load-Serving Entities (LSE) that are MISO NITS customers in portions of American Transmission’s footprint that are subject to Michigan’s Retail Choice.The details of this procedure are included in the following attachment.

If you have questions pertaining to this procedure, please contact Marty Martinez, Senior Business Accountant, at mmartinez@atcllc.com or by phone at (262) 506-6168.

ATC 2012 True-Up Data Available

ATC released its 2012 actual network revenue requirement calculation and reconciliation to actual billed network revenues (“True-Up”) on May 28, 2013. The actual network revenue requirement was approximately $2.055 million more than the forecasted revenue requirement that was billed in 2012. ATC will collect this amount, plus interest, in its 2014 network customer bills. The details of the calculation are included in the following attachment.

If you have questions, please contact Bob Rusch, Director – Finance & Accounting, at brusch@atcllc.com or by phone at (262) 832-8637.

2013 Budget - Update 1/07/13

ATC has reposted its “Rate Projections” through 2017, its projected 2013 Point-to-Point Rates (Schedules 7 & 8) and Attachment O (Schedule 9). These changes are due to updated coincident load data received from its customers. The load change does not result in any change to ATC’s projected annual revenue requirement. ATC has also reposted its projected 2013 Attachment GG (Schedule 26) with a minor revision. This revision does not change the total revenue requirement of $73.4 million, but rather only changes the allocation of charges for ATC RECB projects relative to the entire MISO footprint. ATC expects the revised allocation to result in less than $7,000 in additional costs to the ATC Zone.

Rate Formula (Attachment O)
2013 Attachment GG
2013 Transmission Service Rates (Schedule 7 & 8)
ATC Rate Projections through 2017

If you have any questions, please contact Mike Degenhardt (mdegenhardt@atcllc.com) or Bob Rusch (brusch@atcllc.com).

Tom Finco
Vice President, External Relations

2013 Budget

ATC will host a customer teleconference/web-conference to discuss the 2013 Budget on Wednesday, October 3, 2012 at 2:00 p.m. (CST). The 2013 Budget will be presented and customers will have an opportunity to discuss the budget information during this time. We have planned this single meeting for review of the budget materials to meet the needs of all customers. We encourage you to extend this invitation to all appropriate staff in your organization. The participation information is included below.

Dial In Number: (866) 621-2153
Access Code: 4003177

Web Meeting Address: https://www.webmeeting.att.com
Meeting Number: 8666212153
Access Code: 4003177

All available information on the 2013 Budget and Rates has been posted below to provide our customers with an equal opportunity to review the documents.

Budget Presentation
Rate Formula (Attachment O)
2013 Attachment GG
2013 Attachment MM
2013 Transmission Service Rates (Schedule 7 & 8)
ATC Rate Projections through 2017

Tom Finco
Director, External Relations

ATC 2011 True-Up Data Available

ATC released its 2011 Actual Network Revenue Requirement Calculation and Reconciliation to Actual Billed Network Revenues (“True-Up”) on June 1, 2012. The actual network revenue requirement was approximately $8.928 million less than the forecasted revenue requirement that was billed in 2011. The details of the calculation are included in the following attachment.

If you have questions, please contact Bob Rusch, Director – Finance & Accounting, at brusch@atcllc.com or by phone at (262) 832-8637.

2012 Budget - Update 1/10/12

FERC recently approved a filing that slightly changes the projected 2012 revenue requirement for MVP projects. As a result, ATC had to refile its attachment MM with MISO. The impact was a reduction in attachment MM of $43,450. This reduction also results in an increase in revenue requirement for attachment O by a similar $43,450. Due to these minor changes, ATC is now reposting the attachments with the updated revenue requirements.

Rate Formula (Attachment O)
2012 Attachment GG
2012 Attachment MM
2012 Transmission Service Rates (Schedule 7 & 8)
ATC Rate Projections through 2016

If you have questions, please contact Bob Rusch, Director – Finance & Accounting, at brusch@atcllc.com or by phone at (262) 832-8637.

Tom Finco
Director, External Relations

2012 Budget - Update 10/18/11

Before the end of October, ATC plans to propose new depreciation rates, with an effective date of January 1,2012, for its facilities in a FERC rate filing. Based on a depreciation study to be submitted to FERC, ATC’s 2012 revenue requirement is estimated to increase by $248,000.

For questions regarding the filing, please contact Mal Bertsch at (262) 506-6736 or by email at mbertsch@atcllc.com.

2012 Budget - Update 10/4/11

As indicated in the previous budget posting, the presentation that will be reviewed on the October 10, 2012 Budget, conference call is now available.

Budget Presentation

Tom Finco
Director, External Relations

2012 Budget

Please find the links to ATC's 2012 Budget and Rates below. This information is posted in order to provide our customers with an equal opportunity to review the documents.

ATC will host a teleconference/web-conference to discuss the 2012 Budget on Monday, October 10, at 2:30 p.m. (CST). The 2012 Budget will be presented in detail and customers will have an opportunity to discuss the budget information. We have planned this single meeting for review of the budget materials to meet the needs of all customers. This meeting will be very comprehensive and we encourage you to extend this invitation to all appropriate staff in your organization. Participation information is as follows.

Dial In Number: (866) 621-2153
Access Code: 4003177

Web Meeting Address: https://www.webmeeting.att.com
Meeting Number: 8666212153
Access Code: 4003177

Rate Formula (Attachment O)
2012 Attachment GG
2012 Attachment MM
2012 Transmission Service Rates (Schedule 7 & 8)
ATC Rate Projections through 2016

Please note that the Budget Presentation reviewed during this call will be posted by Tuesday, October 4, 2011.

Please indicate your participation to Marcia Louden at mlouden@atcllc.com.

Tom Finco
Director, External Relations

ATC 2010 True-Up Data Available

ATC released its 2010 Actual Network Revenue Requirement Calculation and Reconciliation to Actual Billed Network Revenues (“True Up”) on June 1, 2011. The actual network revenue requirement was approximately $10.716 million less than the forecasted revenue requirement that was billed in 2010.

In accordance with ATC’s tariff and Attachment O, ATC is currently refunding these amounts, plus accrued interest, in its 2011 monthly network billings. The details of the calculation are included in the following attachment.

If you have questions, please contact Bob Rusch, Director – Finance & Accounting, at brusch@atcllc.com or by phone at (262) 832-8637.

ATC 2009 True-Up Data – Updated 2/16/11

ATC released its 2009 Actual Network Revenue Requirement Calculation and Reconciliation to Actual Billed Network Revenues (“True Up”) on June 1, 2010. The actual network revenue requirement was approximately $972 thousand more than the forecasted revenue requirement that was billed in 2009.

In accordance with ATC’s tariff and Attachment O, ATC will collect these amounts, plus interest, in its 2011 monthly network billings. The details of the calculation are included in the following attachment.attachment.

If you have questions, please contact Bob Rusch, Director – Finance & Accounting, at brusch@atcllc.com or by phone at (262) 832-8637.

2011 Budget - Update 12/17/10

Listed below please find the links to ATC’s 2011 Attachment O & Attachment GG, incorporating the new Attachment GG template approved by the FERC on December 3, 2010. As a result, revisions have been made to Schedules 7 & 8 and are included below for your reference.

Rate Formula (Attachment O)
2011 Attachment GG
2011 Transmission Service Rates (Schedule 7 & 8)
ATC Rate Projections through 2015

If you have questions, please contact Bob Rusch, Director – Finance & Accounting, at brusch@atcllc.com or by phone at (262) 832-8637.

Tom Finco
Director, External Relations

2011 Budget - Attachment GG

Listed below please find the links to ATC's 2011 Attachment GG. This information was posted to OASIS on October 19, 2010 in order to provide our customers with an equal opportunity to review the documents.

2011 Attachment GG

2011 Budget - Update 10/13/10

ATC posted 2011 Budget and Rates information on October 1, 2010. Subsequently, an error was discovered on page 6, line 15, of the 2011 Budget Presentation related to the 2009 Network True-up which impacts the 2011 revenue requirement. As filed on October 1, the amount of the Network True-up was $977,000. The amount should have been $371,000. The revised presentation shows the correct 2009 Network True-up amount. As a result of this change, the 2011 projected network billed revenue requirement will decline from $500.1 million to $499.5 million.

As a result of this correction revisions have been made to Schedules 7 & 8 as well as the ATC Rate Phase-in and Projections through 2015. Links to the revised documents are included below for your reference.

2011 Transmission Service Rates (Schedule 7 & 8)
ATC Rate Projections through 2015
Budget Presentation


If you have questions, please contact Bob Rusch, Director – Finance & Accounting, at brusch@atcllc.com or by phone at (262) 832-8637.

Tom Finco
Director, External Relations

2011 Budget

Listed below please find the links to ATC's 2011 Budget and Rates. This information is posted in order to provide our customers with an equal opportunity to review the documents.

ATC will host a customer meeting to discuss the 2011 Budget on Wednesday, October 13, 2010, from 10-11am. The 2011 Budget will be presented in detail and customers will have an opportunity to discuss the budget information. We have planned this single meeting for review of the budget materials to meet the needs of all customers. This meeting will be very comprehensive and we encourage you to extend this invitation to all appropriate staff in your organization.

This meeting is offered as a teleconference/web meeting only. The participation information is as follows.

Dial In Number: (866) 621-2153
Access Code: 4003177

Web Meeting Address: https://www.webmeeting.att.com
Meeting Number: 8666212153
Access Code: 4003177

Please indicate your participation and direct any questions to Marcia Burbach at mburbach@atcllc.com.

We look forward to seeing you on Wednesday.

Tom Finco
Director, External Relations

Rate Formula (Attachment O)
2011 Transmission Service Rates (Schedule 7 & 8)
ATC Rate Projections through 2015
Budget Presentation



ATC 2009 True-Up Data Available

ATC released its 2009 Actual Network Revenue Requirement Calculation and Reconciliation to Actual Billed Network Revenues (“True Up”) on June 1, 2010. The actual network revenue requirement was approximately $368 thousand more than the forecasted revenue requirement that was billed in 2009.

In accordance with ATC’s tariff and Attachment O, ATC will collect these amounts in its 2011 monthly network billings. The details of the calculation are included in the following attachment.



2010 Rate Implementation

ATC has posted below updated Rate Formula (Attachment O), 2010 Transmission Service Rates (Schedule 7&8) and ATC Rate Phase-in and Projections through 2014 on Friday, February 5. Please note these updates were made to the 2010 Budget files previously posted in Fall 2009.

Please contact your regional manager with any questions. Thank you.

Tom Finco
Director of External Relations and Policy

Rate Formula (Attachment O)
2010 Transmission Service Rates (Schedule 7 & 8)
ATC Rate Phase-In and Projections through 2014



2010 Budget

Listed below please find the links to ATC's 2010 Budget and Rates. This information is posted in order to provide our customers with an equal opportunity to review the documents.

ATC will host a customer meeting to discuss the 2010 Budget on Wednesday, October 7, from 9:30am-10:30am at ATC's Pewaukee office. The 2010 budget will be presented in detail and customers will have an opportunity to discuss the budget information. We have planned this single meeting for review of the budget materials and encourage you to extend this invitation to all appropriate staff within your organization.

A teleconference option is available for this meeting. The dial-in information is as follows.
Dial In Number: (866) 621-2153
Access Code: 4003177
Please indicate your participation either in person or via phone and direct any questions to Marcia Burbach at mburbach@atcllc.com.

We look forward to seeing you on Wednesday.

Tom Finco
Director, External Relations and Policy

Rate Formula (Attachment O)
2010 Transmission Service Rates (Schedule 7 & 8)
ATC Rate Phase-In and Projections through 2014
Budget Presentation



ATC 2008 True-Up Data Available


ATC released its 2008 Actual Network Revenue Requirement Calculation and Reconciliation to Actual Billed Network Revenues (“True Up”) on June 1, 2009. The actual network revenue requirement was approximately $15.5 million [revised to $16.1 million, October 6, 2009] less than the forecasted revenue requirement that was billed in 2008. The difference is primarily due to lower preliminary survey and investigation costs during 2008 as compared to budget and higher point-to-point revenues received during 2008 as compared to budget.

In accordance with ATC’s tariff and Attachment O, these amounts are being refunded to network customers in 2009 monthly billings. The details of the calculation are included in the following attachment [updated on 10/6/09, 11/5/09, and 12/17/09]




2009 Rate Implementation

ATC has posted below updated Rate Formula (Attachment O), 2009 Transmission Service Rates (Schedule 7&8) and ATC Rate Phase-in and Projections through 2013 on Monday, February 2. Please note these updates were made to the 2009 Budget files previously posted in Fall 2008.

Please contact your regional manager with any questions. Thank you.

Tom Finco
Director of External Relations and Policy

Rate Formula (Attachment O)
2009 Transmission Service Rates (Schedule 7 & 8)
ATC Network Rate Projections through 2013



2009 Budget

Listed below please find the links to ATC's 2009 Budget and Rates. This information is posted in order to provide our customers with an equal opportunity to review the documents.

ATC will host a customer meeting to discuss the 2009 Budget on Tuesday, October 7 from 9-10am at ATC's Pewaukee office. The 2009 Budget will be presented in detail and customers will have an opportunity to discuss the budget information. We have planned this single meeting for review of the budget materials to meet the needs of all customers. This meeting will be very comprehensive and we encourage you to extend this invitation to all appropriate staff in your organization.

A teleconference option is available for this meeting. The dial-in information is as follows.
Dial In Number: (866) 621-2153
Access Code: 3749584

Please indicate your participation either in person or via phone to Terry Peterson, tpeterson@atcllc.com.

We look forward to seeing you on Tuesday.

Tom Finco
Director, External Relations and Policy

Rate Formula (Attachment O)
2009 Transmission Service Rates (Schedule 7 & 8)
ATC Rate Phase-In and Projections through 2013
Budget Presentation